Schedule Of Rates & Quantum Of Work For Increasing Capacity Of T / Fs By Chain Rule System From 16 Kva To 25 Kva 1Ø ( 05 Nos ) , 16 Kva To 25 Kva 3 Ø ( 04 Nos. ) , From 25 Kva To 63 Kva 1Ø ( 55 Nos. ) , From 25 Kva To 63 Kva 3Ø ( 07 Nos. ) , 16 Kva To 63 Kva ( 01 Nos. ) , And Installation Of New 25 Kva T / F ( 04 Nos. ) , ( Total T / F77 Nos. ) Under Supply Area Of Edd Dalmauat Difference Places Of Geographical Area Of Executive Engineer, Electricity Distibution Division-Dalmau Under Business Plan 2023-24, In Jurisduction Of Electricity Distribution Division-Dalmau, Raebareli.
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 10-Oct-2023 | REVISION OF TENDER FORM95 | Financial Bid | 12-Oct-2023 |
BOQ
| Sl. No. | Item Description |
| 1 | INCREASING CAPACITY OF T/FS BY CHAIN RULE SYSTEM FROM 16 KVA TO 25 KVA 1Ø IN VILLAGE PURE MOHAN SINGH, PURE GAURI KAILI, KETAULI, RAUSI & PURE BABU(05 NOS) ,FROM 16 KVA TO 25 KVA 3 Ø IN VILLAGE MATAULI PUR, NARHARPUR, PURE NATHU, PURE GADARIAN (04 NOS.), 25 KVA TO 63 KVA 1Ø IN VILLAGE PURE SOMVANSHI, KETAULI, GURUGANJ BAZAR, BINDAGANJ, BANIYAI, PURE KESHARI, PURE DAROGANI, PURE KCHHWAHAN, PURE MOHAN SINGH, PURE VIJAI, PURE BEECH DOMA PUR, RAUSI, RAUSI, MADUTPUR, GADARIAN, GADARIAN, MACHHIYA NARI, BHEERA, BELAHATA, HAZIYAPUR, SARISTAPUR, GHURWARA GANDHI VIDYALAY, KUTI GHURWARA, KAKRAHI GHURWARA, HEENGA MAU, LODIPUR, LODIPUR, BHEERA GOVINDPUR, BHEERA GOVINDPUR, PURE RANA BHEERA, PURE NARPATI SINGH, DEVANNA, PURE BAKKA, PURE KONHU, REFEEPUR RONARI, BHANAWA, PURE SURJU, GADOL, PURE BHAWAN, MUJJAFARPUR, AWASHERI, URE UMARAW, PURE MATIYARU, PURE HIRAU, MAUHARI, PURE SHIVE DUITT, PATTI HAR, PURE RAIKWARAN, PURE BINDA (PAKARA), PAKAR AMEERAN, SHAD BARA, KATGHAR, PURE VISHRAM, PURE SHIKARWAN, PURE MOHAN SINGH (55 NOS.), FROM 25 KVA TO 63 KVA 1Ø IN VILLAGE KHUSHIYA (ZAFARAPUR)- (01 NO.), FROM 25 KVA to 63 KVA 3 Ø IN VILLAGE LOOK CHANDPUR, NARHAR PUR, CHARMAPUR, THAKURDWARA, MATAULIPUR, EKDALA, PURE PASIN (07 NOS.), 16 KVA TO 63 KVA IN PURE GAUTAMAN (01 NOS.), 63 KVA TO 100 KVA IN VILLAGE BIJHHALAMAU (01 NO.) AND INSTALLATION OF NEW 25 KVA 3Ø T/F IN VILLAGE MATAULIPUR, PURE DHANU, PURE KESARI, PURE JHHANDA RAUSI (04 NOS.), (G. TOTAL T/F77 NOS.) UNDER SUPPLY AREA OF EDD DALMAUAT |
| 2 | Safe loading & carriage including Loading-unloading & proper stacking at a Place of work site of following store materials from ESC Tripula to site of work. |
| 3 | 25 KVA T/F |
| 4 | 63 KVA T/F |
| 5 | 100 KVA T/F |
| 6 | PCC Pole 8.5 Mtr.long |
| 7 | 11KV Disc Insulator with fitting |
| 8 | 11 KV Pin Insulators with fitting |
| 9 | 11 KV Cross Arms |
| 10 | M.S. \"T\" Off Channel |
| 11 | Top Channel |
| 12 | Earthing Set Complete |
| 13 | ASCR Weasal Conductor |
| 14 | S/S base Channel |
| 15 | Stay Set Complete |
| 16 | AB Cable 3 phase 95 Sq.mm. |
| 17 | Labor & ErectionCharges:- |
| 18 | Work for Dismantling of existing 16 KVA T/F on Pole alongwith all acessories. And stacking a place with loading-uploading. Asper estimate. |
| 19 | Work for Dismantling of existing 25 KVA T/F on Pole alongwith all acessories. And stacking a place with loading-uploading. Asper estimate. |
| 20 | Work for Dismantling of existing 63 KVA T/F on Pole alongwith all acessories. And stacking a place with loading-uploading. Asper estimate. |
| 21 | Digging of pits ofPCC Pole 8.5 Mtr. Long from dump site to pit site then errection of PCC poles with including all related accessories as per RESPO Norms. Asper estimate. |
| 22 | Grouting of PCC poles 8.5 Mtr. Long with grouting materials as per RESPO Norms. Asper estimate. |
| 23 | Digging of pits ofPCC Pole 8.5 Mtr. Long, then Making/Grouting of Double Pole Structureby PCCPole with grouting Materials and fitting of all required accessories. for mounting of T/F on D/Pole as per RESPO norms. Asper estimate. |
| 24 | Work for Mounting of 25 KVA Transformers on D/Pole alongwith fitting of all acessories, As per RESPO norms, Asper estimate. |
| 25 | Work for Mounting of 63 KVA Transformers on D/Pole alongwith fitting of all acessories, As per RESPO norms, Asper estimate. |
| 26 | Work for Mounting of 100 KVA Transformers on D/Pole alongwith fitting of all acessories, As per RESPO norms, Asper estimate. |
| 27 | Earthing of 25 KVA T/F Body & Neutral ofTransformers complete work as per RESSPO norms. |
| 28 | Earthing of 63 KVA T/F Body & Neutral ofTransformers complete work as per RESSPO norms. |
| 29 | Earthing of 100 KVA T/F Body & Neutral ofTransformers complete work as per RESSPO norms. |
| 30 | Digging of pits, fixing & grouting of stay rods as per RESSPO norms including with grouting materials. Then after fixing and nozzling of stay wire. |
| 31 | Earthing of S.T/PCC. Poles as per RESSPO Norms, AS Required. |
| 32 | Stringing, Laying & sagging of 11KV Line by ACSRWeasal conductor, as per RESSPO Norms. |
| 33 | Stringing, Laying & sagging of 11KV Line by AB Cable (3 phase 95 sq.mm , as per RESSPO Norms. |
| 34 | Fabrication of Line materials like \"V\" type X-arm/Top Channel/T off Channel/M.S. Channel/ M.S. Angle/Gaurding Angle and other misc work, as required, |
| 35 | Cutting of Tree Branches for cleaning of HT/LT Lines, as required. |
| 36 | Recd. back of 16 KVA T/Ffrom work site to ESC Tripula, Raebareli alongwith safe loading unloading. |
| 37 | Recd. back of 25 KVA T/Ffrom work site to ESC Tripula, Raebareli alongwith safe loading unloading. |
| 38 | Recd. back of 63 KVA T/Ffrom work site to ESC Tripula, Raebareli alongwith safe loading unloading. |
| 39 | Recd. back of other ScrapMaterials from work site to ESC Tripula, Raebareli after dismantling of T/Fs/Line from D/Pole/Four Pole Structure/ Plinth, alongwith loading unloading. |
| 40 | work for Installtion of Holding Clamp for PCC Pole, Material Provided by Contractor |
| 41 | work for Installtion of \"F\" Bracket, Material Provided by Contractor |
| 42 | work for Installtion of Clamp with Nuts & Bolt for for PCC Poles, Material Provided by Contractor |
| 43 | Work for Installation/fixing of Stone Pad (300X300X75mm), Material Provided by Contractor |
| 44 | Work for Installation/fixing of Danger Board with Clamp, Material Provided by Contractor |
| 45 | Work for Installation/fixing of \"EYE\" Hook for LT ABC Material Provided by Contractor |
| 46 | Work for Installation/fixing of Nuts & Bolt, Material Provided by Contractor |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender