| 1 | Dismantling old unserviceable ACSR conductor of assorted sizes as in overhead lines from poles and taken on credit complete all as specified and as directed. Note: The weight of ACSR conductor only shall be measured as per preamble given in Sl page No 384 of SSR Part-II 2010. |
| 2 | Dismantling old unserviceable cross arms of mild steel channel or angle sections etcfrom poles and taken on credit complete all as specified and as directed.Note: The porcelain insulators shall also be dismantled alongwith the conductors and taken on credit. |
| 3 | Excavation in trenches not exceeding 1.5 m wide and not exceeding 1.5 m depth and getting out soft / loose soil for laying cables / pipes / erection of poles etc all as specified and as directed. |
| 4 | Removing excavated material (soil) not exceeding 50 m and depositing where directed at a level not exceeding 1.5 m above the starting point all as specified and as directed. |
| 5 | Returning filling in soil including spreading leveling watering well ramming in layers not exceeding 25 cm each all as specified and as directed. |
| 6 | Laying in trenches fine sieved excavated dry soilincluding spreading / leveling, cushioning for underground cables all as specified and as directed. |
| 7 | Supply and laying of common burnt clay building bricks, sub class B of size 230x115x75mm for cable protection all as specified and as directed. |
| 8 | Material and labour for XLPE insulated, armoured, heavy duty electric cable with aluminum conductor, 1100 volts grade, 2/3.5/4 in replacement of the following sizes cross-sectionl area including taking down of old unserviceable cable complete all as specified and as directed:- (NOTE : Earth work including excavation ,returning Filling,removing,soil coushioning,brick covering for mechanical protection of cable etc will be measured and paid separately under respective items of schedule) |
| 9 | 35 sq mm 4 core |
| 10 | 50 sq mm 3.5 Core |
| 11 | 70 sq mm 3.5 Core |
| 12 | 95 sq mm 3.5 Core |
| 13 | Material and labour for GI tubing light grade for cable protection laid in trenches in road crossing or fixed to wall/Pole of following sizes including taking down old unserviceable one complete all as specified and as directed. |
| 14 | Bore of tube 40mm |
| 15 | Bore of tube 50mm |
| 16 | Bore of tube 80mm |
| 17 | Supply and fix cable jointing kit for 1.1 KV grade cable for straight through , heat shrink type, joint complete with jointing material and accessories suitable for 3.5 core XLPE, armoured, Al conductor cable of following sizes :- |
| 18 | 3.5 core , 35 to 50 Sqmm |
| 19 | 3.5 core , 70 to 95 Sqmm |
| 20 | M & L for cable route indicator duly marked with LT cable, working voltage, size of cable and route made out of GI plate 3mm thick, 150mm dia fixed on angle iron ISA 25mm x 25mm x 3mm, 500mm long, suitably embedded in PCC 1:2:4 , type B1 using 20mm graded stone aggregate of size 300mm x 300mm x 300mm on ground and the mild steel surfaces shall be painted with two coats of synthetic enamel paint over a coat of red oxide ptimer complete all as specified and as directed. |
| 21 | Cutting existing bituminous road surfaces to a depth not more than 150mm and making good the surface with PCC 1:3:6, type C1, usind 20mm graded stone aggregate to match to the adjacent surface after laying pipes/ cable including removal of debris to a distance not exceeding 50m and depositing where ditected at a level not exceeding 1.5m above the starting point complete all as specified and as directed.Note: The plan area of the road surface cut for laying pipes shall be measured for purpose of payment. |