| 1 | SUB WORK-1Pumping Machinary 5 BHP, Discharge = 2650 LPH, Head = 37 m |
| 2 | Providing, erecting and giving tests of submersible pump set confirming to IS 8034 and motor confirming to IS 9283, with water proof winding and discharge with stainless steel shaft. Mortar suitable for working on 415 V = 10% 3 phase 50 Hz A.C. supply with cable guard, thrush carbon/fible bearing to withstand entire hydraulic thrust with suitable suction strainer. Pump should have suitable discharge outlet as per manufacture\"s design. Antithrust streamlined non return valve shall be provided with the pump. 3 m submersible copper conductor cable in single / double run and 2 pairs of suitable size erection clamp 10 mm thick shall be provided with each pump.Submersible Pump 150 mm dia (with Bronze / Stainless steel (CF8M) Impeller) upto 8 stagesProvideduplicate set of submersible pump capable of discharging 2650 litres/hour against a total head 37 M be driven by 5 B.H.P electrical motor directly coupled to it . One pump will be in operation and one pump will be standby. |
| 3 | Supplyingand erecting Cupboard type panel board. |
| 4 | Supplying and erecting flat flexible 3 core 4 sq mm PVC sheathed submersible type copper cable suitably clamped at fixed intervals with column pipe assembly complete. |
| 5 | Providing & erecting ISI mark G.I. pipeof followingclassanddia. including all local and central taxes, octroi, inspection charges, transportation to stores, etc. complete65mm dia (heavy) on well |
| 6 | Providing, supplying and fixing ISI mark CI D/F Reflux valve (non-return valves of following dia including all taxes (central and local), railway freight, inspection charges, unloading from railway wagon, loading into truck, transportation upto departmental store/site, unloading, stacking etc. complete. Reflux valves as per I.S. 5312 part I (1984)a) Without bypass arrangement - PN - 165 mm dia |
| 7 | Providing and fixing double flanged sluice valve confirming for IS-2096/14846 including worn gear arrangements as per test pressure stainles steel spindle, caps including all taxes transportation etc complete.a) Sluice valve - PN - 1(Without bypass)65 mm dia |
| 8 | Lowering, laying and jointing in position following C.I.D/F Reflex valves, Butterfly valves and Sluice valves including cost of all labour jointing material, including nut bolts and giving satisfactory hydraulic testing etc. complete. (Rate for all class of valves.)a) Sluice valve - PN - 1(Without bypass)65 mm dia |
| 9 | Providing and erecting pressure gauge of required capacity complete with syphon tube, isolating cock suitable for 12mm dia GI pipe. Pressure gauge shall be installed as directed, with tapping on rising main pressure gauge (100 mm dia) |
| 10 | Providing pipe type earthing with 40mm dia G.I Pipe or 20 mm dia G.I Rod complete with all materials as per specifications no EA-EPPlate type Electrode (IS 3043)1. For panel board- 1No. |
| 11 | Supplying and erecting \"b\" class GI bend in position withnecessary material.65 mm dia |
| 12 | Supplying and erecting \"b\" classGI Teein position withnecessary material.65 mm dia |
| 13 | Supplying and erecting \"b\" classCoupling in position withnecessary material.65 mm dia |
| 14 | SUB WORK-2 Rising Main Total Length = 1300 m 75 ø (6 KG)mm HDPE PN6Providing and supplying in standard lengthsPolyethelene Pipes, confirming to IS 4984 /14151 / 12786 / 13488 with nesessary jointingmaterial like mechanical connector i. e. thread /insert joint / quick release coupler joint / compression fitting joint or flanged joint excluding coupler/specials, including transportation and freight charges, inspection charges, loading / unloading charges, conveyance to the departmental stores & stacking the same in closed shade duly protecting from sunrays & rains, excluding GST levied by GI & GOM in all respect etc. complete.75 ø (6 KG) |
| 15 | Providing & Supply of Electro Fusion Fittingsin accordance with BS EN12201: Part-3 suitablefor drinking water with in black/ blue colourmanufactured from compounded PE80/ PE100virgin polymer and compatible with PE80/PE100pipes, in pressure rating SDR11 with min PN12.5rated for water application and shall be inclusive ofall cost such as testing, inspection charges,transportation up to store, transit insurance,loading, unloading, stacking excluding GST leviedby GOI & GOM in all respect, etc. complete.Couplers 75 |
| 16 | Equal Tee 75 |
| 17 | LNPE 75 Spigot Long Neck Pipe End (Stub End) for Electro Fusion joint |
| 18 | Providing ISI mark G.I. pipe of following class and dia. excluding GST levied by GOI & GOM in all respect, inspection charges, transportation to stores, etc. complete as per IS-1239/2004. Note : One coupler shall be provided with each full length of pipe cost of which is included in rates below.Medium Pipe65 ø |
| 19 | Providing and supplying ISl mark CI D/F reflux valves (non-return valves ) of following dia including all taxes (Central and Local), railway freight, inspection charges unloding from railwaywagon,loadinginto truck, transportation upto departmentalstroes/ site, unloading, stacking etc. complete.Reflux valves as per I.S.5312 Part I (1984)Without by pass arrangement - PN -165 ø |
| 20 | Providing double flange sluice valve confirming for IS- 14846 including worn gear arrangements as per test pressure, stainless steel spindle, caps, including inspection charges, transportation upto departmental store, unloading, stacking excluding GST levied by GOt & GOM in all respect etc. completeWithout by pass arrangement - PN -1 Scour Valve80 ø |
| 21 | Providingandsupplying Air Valvesas per IS-10845and MJP’s standard specificationsdoubleorificetypecombinedwithscrewdownisolatingvalve,small orificeelasticballrestingonagunmetalorificenipple,largeorificevulcaniteball seatingon mouldedseatring,inletfaceanddrilled,includingall taxes(Centraland local), insurance, third party inspection charges, loading, unloding, transportatoin upto departmental stores / site, etc. complete. Air Valve Single Ball Flanged Type - PN -125 ø |
| 22 | Labour SectionExcavation for foundation / pipe trenches in earth, soils of all types, sand, gravel and soft murum, including removing the excavated material upto a distance of 50 metres and lifts as below, stacking and spreading as directed, manual dewatering, preparing the bed for foundation and excluding backfilling, etc. complete.Lift 0 to 1.5 |
| 23 | Excavation for foundation / pipe trenches in hard murum and boulders, W.B.M. road including removing the excavated material upto a distance of 50 M beyond the area and lifts as below, stacking and spreading as directed by Engineer-in-charge, normal dewatering, preparing the bed for foundation and excluding backfilling, etc. complete. (BdA-3/259)Lift 0 to 1.5 |
| 24 | Excavation for foundation / pipe trenches in soft rock and old cement and lime masonry foundation asphalt road including removing the excavated material upto a distance of 50 M beyond the area and lifts as below, stacking as directed by Engineer-in_x0002_charge, normal dewatering, preparing the bed for foundation and excluding backfilling, etc. complete. (Bd-A-4/259)Lift 0 to 1.5 |
| 25 | Excavation for foundation / pipe trenches in hard rock and concrete road by chiselling, wedging, line drilling by mechanical means or by all means other than blasting including trimming and levelling the bed, removing the excavated material upto a distance of 50 metres beyond the area and lifts as below, stacking as directed by Engineer-in-charge, normal dewatering, excluding backfilling, etc. complete by all means. (Bd-A-6/259)Lift 0 to 1.5 |
| 26 | Filling in plinth and floors murum bedding intrenches with approved murum from excavated materials from foundation in 15 cm to 20 cm layers including watering and compaction, etc. complete. (Bd-A-10/263)from excavated stuff |
| 27 | Lowering, Laying and Jointing H. D. P. E./M.D. P. E. pipes in proper position including allspecials by compression fitting/electrofusion and butt fusion jointing procedure as per relevent IS Code complete with all materials for jointing procedure like Electrofusion machine, Electric heater/butt fusion welding machine with hydraulicjack, top loading clamp etc. and all labours as directed by engineer in charge as per IS-7634 Part II75 ø (6 KG) |
| 28 | Hydraulic testing of H. D. P. E./ M. D. P. E. pipe line to specified pressure including cost of all materials and labour and water for testing for specified length including cutting, placing end cap making arrangement for filling safe water using reciprocating type pumps which should be able to provide specified test pressure gauges and other necessary equipments, labour, operation charges, etc. required for testing. The rate under this item shall also include cost of retesting, if necessary and reinstating to original position..Working pressure 6 kg/cm275 ø (6 KG) |
| 29 | Lowering, laying and jointing G. I. pipes and specials of following class and diameter including conveyance from stores to site of works, all labour, etc. complete either underground or in vertical position, as directed by Engineer-in-charge.Medium Pipe65 ø |
| 30 | Hydraulic testing of G. I. pipe line to specified pressure including cost of all materials and labour and water for testing for the length upto 1km using reciprocating type pumps which should be able to provide specified test pressure gauges and other necessary equipments, labour operation charges etc. required for testing, The rates under this item shall also include cost of retesting if necessary and reinstating to original postion.Medium Pipe65 ø |
| 31 | Lowering, laying, jointing in positionfollowing CI/DF Reflux, butterfly valves and sluice valves including cost of all labors jointing material including nutbolts and giving satisfactory hydraulic testing etc complete ( Rates for all class of valves )65 ø |
| 32 | Providing and fixing in position air valve shaft including providing and fixing GI Medium Class or 6 mm thick M.S. pipe shaft 2.70 M long over branch flange of air valve tee, providing PCC block of M-150 concrete, 150 mm thick around the air valve tee including encasing of vertical shaft in PCC M-150 as shown in type design together with providing and making flanged joints wherever required and fixing of air valve tee, etc. complete as per type design and as directed by Engineer -in- charge for following diameters of pipe lines (type design attached.)upto 140mm |
| 33 | ProvidingandconstructingB.B.masonryvalvechamberwith15cmthick1:2:4 proportionPCCbedding,excludingexcavation,B.B. masonryin C.M. 1:5 Proportion precast RCC frame and cover, etc. complete as directed by Engineer-in-charge.As above of 60x45cm internal size and depth upto 0.9 m with precast R.C.C slab and cover. |
| 34 | Providing and laying in situ Cement Concrete M-15 of trap/ granite / quartzite / gneiss metal for foundation and bedding including bailing out water, form work, compaction, curing, etc. complete. (Cement 5.90 bags / cum)Forencasingand reconstruction of road |
| 35 | Refillingthetrenches withavailableexcavated stuffwithsoftmaterialfirstover pipelineandthenhardmaterialin15cmlayerswithallleadsandliftsincluding consolidation, surcharging,etc. complete.Net Volume of Refilling |
| 36 | SUB WORK-3Distribution System Total Length = 4492 m 75 øto 90 ø mm HDPE PN6 Providing and supplying in standard lengths Polyethelene Pipes, confirming to IS 4984 / 14151 / 12786 / 13488 with nesessary jointing material like mechanical connector i. e. thread / insert joint / quick release coupler joint / compression fitting joint or flanged joint excluding coupler/specials, including transportation and freight charges, inspection charges, loading / unloading charges, conveyance to the departmental stores & stacking the same in closed shade duly protecting from sunrays & rains, excluding GSTlevied by GI & GOM in all respect etc. complete.75 ø |
| 37 | 90 ø |
| 38 | Providing & Supply of Electro Fusion Fittingsin accordance with BS EN12201: Part-3 suitablefor drinking water with in black/ blue colourmanufactured from compounded PE80/ PE100virgin polymer and compatible with PE80/PE100pipes, in pressure rating SDR11 with min PN12.5rated for water application and shall be inclusive ofall cost such as testing, inspection charges,transportation up to store, transit insurance,loading, unloading, stacking excluding GST leviedby GOI & GOM in all respect, etc. complete.Couplers 75 |
| 39 | Couplers 90 |
| 40 | Equal Tee 75 |
| 41 | Equal Tee 90 |
| 42 | Reducer 90x75 |
| 43 | LNPE 75 Spigot Long Neck Pipe End (Stub End) for Electro Fusion joint |
| 44 | LNPE 90 Spigot Long Neck Pipe End (Stub End) for Electro Fusion joint |
| 45 | Providing ISI mark G.I. pipe of following class and dia. excluding GST levied by GOI & GOM in all respect, inspection charges, transportation to stores, etc. complete as per IS-1239/2004. Note : One coupler shall be provided with each full length of pipe cost of which is included in rates below.Medium Pipe65 ø |
| 46 | 80 ø |
| 47 | Providing double flange sluice valve confirming for IS- 14846 including worn gear arrangements as per test pressure, stainless steel spindle, caps, including inspection charges, transportation upto departmental store, unloading, stacking excluding GST levied by GOt & GOM in all respect etc. complete.Without by pass arrangement - PN-1.65 ø |
| 48 | 80 ø |
| 49 | Excavation for foundation / pipe trenches in earth, soils of all types, sand, gravel and soft murum, including removing the excavated material upto a distance of 50 metres and lifts as below, stacking and spreading as directed, manual dewatering, preparing the bed for foundation and excluding backfilling, etc. complete.Lift 0 to 1.5 |
| 50 | Excavation for foundation / pipe trenches in hard murum and boulders, W.B.M. road including removing the excavated material upto a distance of 50 M beyond the area and lifts as below, stacking and spreading as directed by Engineer-in-charge, normal dewatering, preparing the bed for foundation and excluding backfilling, etc. complete. (BdA-3/259)Lift 0 to 1.5 |
| 51 | Excavation for foundation / pipe trenches in soft rock and old cement and lime masonry foundation asphalt road including removing the excavated material upto a distance of 50 M beyond the area and lifts as below, stacking as directed by Engineer-in_x0002_charge, normal dewatering, preparing the bed for foundation and excluding backfilling, etc. complete. (Bd-A-4/259)Lift 0 to 1.5 |
| 52 | Excavation for foundation / pipe trenches in hard rock and concrete road by chiselling, wedging, line drilling by mechanical means or by all means other than blasting including trimming and levelling the bed, removing the excavated material upto a distance of 50 metres beyond the area and lifts as below, stacking as directed by Engineer-in-charge, normal dewatering, excluding backfilling, etc. complete by all means. (Bd-A-6/259)Lift 0 to 1.5 |
| 53 | Filling in plinth and floors murum bedding intrenches with approved murum fromexcavated materials from foundation in 15cm to 20 cm layers including watering andcompaction, etc. complete. (Bd-A-10/263)from excavated stuff |
| 54 | Lowering, Laying and Jointing H. D. P. E./M.D. P. E. pipes in proper position including allspecials by compression fitting/electrofusion and butt fusion jointing procedure as per relevent IS Code complete with all materials for jointing procedure like Electrofusion machine, Electric heater/butt fusion welding machine with hydraulicjack, top loading clamp etc. and all labours as directed by engineer in charge as per IS-7634 Part IIWorking Pressure 6 kg/cm²75 ø |
| 55 | 90 ø |
| 56 | Hydraulic testing of H. D. P. E./ M. D. P. E.pipe line to specified pressure including cost ofall materials and labour and water for testing for specified length including cutting, placing end cap making arrangement for filling safe water using reciprocating type pumps which should be able to provide specified test pressure gauges and other necessary equipments, labour, operation charges, etc. required for testing. The rate under this item shall also include cost of retesting, if necessary and reinstating to original position...75 ø |
| 57 | 90 ø |
| 58 | Lowering, laying and jointing G. I. pipes and specials of following class and diameter including conveyance from stores to site of works, all labour, etc. complete either underground or in vertical position, as directed by Engineer-in-charge.Medium Pipe65 ø |
| 59 | 80 ø |
| 60 | Hydraulic testing of G. I. pipe line to specified pressure including cost of all materials and labour and water for testing for the length upto 1km using reciprocating type pumps which should be able to provide specified test pressure gauges and other necessary equipments, labour operation charges etc. required for testing, The rates under this item shall also include cost of retesting if necessary and reinstating to original postion.Medium Pipe65 ø |
| 61 | 80 ø |
| 62 | Lowering, laying, jointing in positionfollowing CI/DF Reflux, butterfly valves and sluice valves including cost of all labors jointing material including nutbolts and giving satisfactory hydraulic testing etc complete ( Rates for all class of valves )65 ø |
| 63 | 80 ø |
| 64 | Providing and fixing C.I. road box including loading, unloading and carting to site of work including all necessary excavation in all types of strata and fixing in murum packing, etc. complete100 mm x 225 mm (20 kg) |
| 65 | Providing and laying in situ Cement Concrete M-15 of trap/ granite / quartzite / gneiss metal for foundation and bedding including bailing out water, form work, compaction, curing, etc. complete. (Cement 5.90 bags / cum)For Road Reconstruction PCC M150 |
| 66 | Refilling the trenches with available excavated stuff with soft material first over pipeline and then hard material in 15 cm layers with all leads and lifts including consolidation, surcharging, etc. complete.Net volume of refilling |
| 67 | Making cross connection to existing distribution main of any type including excavation, breaking and removing existing pipes, lowering, laying of specials and pipes in their position, refilling, closing the water supply in that area, dewatering and restarting the water supply, etc. complete as directed by Engineer-in-charge for following diameters of existing pipeline, irrespective of diameter of branch line. (The number of joints involved will be paid separately depending upon the nature of joints and required pipes, valves and specials will be supplied free of cost at stores.)80mm |
| 68 | 100 mm |
| 69 | SUB WORK-4RCC GSR 10000 LITRESDesigning (aesthetically), and constructing RCC ground service reservoirs / RCC sumps in M-300 mix of required capacity including excavation in all types of strata, foundation concrete, container walls, bottom slab top RCC roof slab / or dome, 20 mm thick cement plaster with water proofing compound in CM 1:3 proportion to inside face of the container, including epoxy paint from inside including refilling and disposing of surplus stuff within lead of 50 M, all labour and material charges, for laying and jointing of pipe assembly for inlet, outlet washout, over flow and bypass arrangement consisting of C.I. M.S. D/F. pipes, specials and valves of given diameters, providing and fixing accessories such as M.S. ladder inside and outside, C.I. Manhole frame and cover, water top slab, B.B. masonry chamber for all valves, ventilating shafts, including giving satisfactory hydraulic test and water tightness test as per IS code and providing three coats of cement paints to all exposed surface of structure including roof surface etc. complete as per design data, criteria, obligatory requirements and detailed specifications. Anti-termite treatment shall be given for underground portion of the structure.For RCC GSRs RCC GSR Capacityfurther cost for 10000 litres @19.35Total cost oflitre GSR |
| 70 | Providing ISI mark G.I. pipe of following class and dia. excluding GST levied by GOI & GOM in all respect, inspection charges, transportation to stores, etc. complete as per IS-1239/2004. Note : One coupler shall be provided with each full length of pipe cost of which is included in rates below.Inlet 80 mm dia.GI.D./F pipes(heavy) |
| 71 | Outlet100 mm dia.GI.D./F pipes(heavy) |
| 72 | Washout 80 mm dia.GI.D./F pipes(heavy) |
| 73 | Providing and supplying ISI standard D. I. specials & fitting with sealing rubber gasket of S.B.R,complete with cast iron follower gland and M\" S. nut holts eoated or other\"wise protected from rusting and suitable for D.l.pipes including cost of labour, materials, and transpoffation to stores, loading and unloading excluding GST levied by GOI & GOM in allrespect etc. complete as per IS-9523.80 mm to 300 mm dia |
| 74 | Providing double flange sluice valve confirming for IS- 14846 including worn gear arrangements as per test pressure, stainless steel spindle, caps, including inspection charges, transportation upto departmental store, unloading, stacking excluding GST levied by GOt & GOM in all respect etc. completeSluice valves PN-1 without bye-pass arrangement100 mm dia. Sluice valve - Outlet/Distribution |
| 75 | 80 mm dia. Sluice valve - Inlet/Bypass |
| 76 | 80 mm dia. Sluice valve - Washout |
| 77 | SUB WORK-5INFORMATORY SIGN BOARDS, TRIAL RUN Commisioning running and maintaining the scheme to quantities, rate capacity, including manning necessory personnel such as operator, valveman, etc, as pr requirements of the scheme and who should also administer chemical dose for a period of one month for individual scheme together with training of personnel spared by MJP/ Local Body and handling over the scheme to Local Body after completion of the above period as directed by Engineer - in charge.For single village ( for 1 months ) |
| 78 | Providing and fixing road junction/ information sign boards of size 1.80 x 1.20 Meter Prepared 16 guage M.S.sheet on frame of size 40x40x5 mm with cross bracing of size 35x35 x 5 mm including painting with on coat of zinc cromate stoving primer and two coats each of green/white back ground and back side gray stove enamelled, bonded with red retro reflective sheet Engineering grade, border / letters / numeral /arrows, coated with non pealable crystal clear protective transperent coat retaining 100% reflection includingtwo angle iron post of size 65 x 65 x 6 mm of 3.65 m. long inflated at bottom drilled on top and painted in whiteand black bands of 30 cm. with 4 Nos. high strength G.I. bolts and nuts of size 10 mm dia. and 20 mm long sheet and angle iron post in one piece without joints including all taxes, conveying, fixing in ground with cement concrete 1:4:8 block of 60 cm x 60 cm x 75 cm size as directed by Engineer-in- charge etc. complete. Mild Steel Board with Engineering Grade |
| 79 | SUB WORK-6FUNCTIONAL HOUSEHOLD TAP CONNECTION (FHTC)Providing and making UPVC/MDPE pipe consumer service connection on Distribution main by drilling hole with suitable means , including all labour , UPVC/MDPE Pipe of required length with or without Road crossing as described below, including cost of specials like Saddle/Clamp Saddle of suitable material, and diameter suitable for Distribution main, 15mm /20mm/ 25mm respective Dia Heavy duty Brass/Polyprophylyne(Twin Jacketed ) Ferrule , Male and Female thread adapter Elbow, Bends,couplers ,Tees, Clamps of suitable material and sundry materials as per requirment, including providing and fixing medium duty 15.mm brass bib tap, GI casing pipe of suitable diameter of 32mm/ 40mm/ 50mm respectively of required length for Road crossing, including requird labour for excavation in all types of strata up to the depth of 0.75m or as per site requirement,all types of plumbing fittings, refilling , Closing the water supply in that area, dewatering, hydraulic testing and restarting the water supply ,transportation of material etc. complete as directed by Engineer inA) Household Connection without water meter (Comression Saddle+ISI Mark Ferrul) for HDPE & PVC pipeFor MDPE/UPVC Pipe Service Connection on Disribution main.(Without Road Crossing)For 15 mm Service connection |
| 80 | For MDPE/UPVC Pipe Service Connection on Disribution main.(With Road Crossing)For 15 mm Service connection |