Purvanchal Vidyut Vitaran Nigam Limited has published Tender For Supply Of Material And Works Against System Strengthening Works In Muncipal Area On Semi Turn Key Basis In Eudd-Mayohall, Bamrauli And Tagore Town Under Eudc-Ii, Prayagraj.. Submission Date for this Tender is 25-09-2023. Cleaning Rags and Cloths Tenders in prayagraj Uttar Pradesh. Bidders can get complete Tender details and download the document.
Sl. No. | Item Description |
1 | SUPPLY OF MATERIALS (Part-A) |
2 | Trip Coil OCB/VCB 24 V |
3 | Multi Meter (100 Amp & 750V) |
4 | Digital Earth Tester |
5 | Volt Meter |
6 | Clamp Meter |
7 | Relly for 11 KV Pannel |
8 | PLA Relly 24 V DC/240 V AC |
9 | Closing Coil 24 V |
10 | Breather |
11 | WTI |
12 | OTI |
13 | Remote Switch |
14 | Amp Meter |
15 | LED Indicator Bulb |
16 | 33 KV Braker Moter |
17 | 33 KV Really ABB Make |
18 | 11 KV SLR 140 C Really |
19 | 11 KV Pannel Charging Motar |
20 | 11 KV Really P 122 micon |
21 | 11 KV Really P 127 micon |
22 | 33 KV REF 615 Really |
23 | Busbar Spout (test) |
24 | T/f Bushing HV/LV (Test) |
25 | Structure for 33 KV VCB (Test) |
26 | Structure for CT(Test) |
27 | Structure for Linghting Arrester(Test) |
28 | Control Cable 4x2.5 sqmm sizes (test) |
29 | Control Cable 6x2.5 sqmm sizes (Test) |
30 | Control Cable 4x1.5 sqmm sizes (Test) |
31 | Holding Clamp for ST Pole-Cross Arm |
32 | Holding Clamp for Top Chanel (STP/PCC) |
33 | Suspension Clamp for ABC Cable |
34 | Dead End Clamp for ABC Cable |
35 | Stone Pad (300x300x75 MM) |
36 | Danger Board with clamp for 11KV & 33 KV |
37 | GI Barbed wire |
38 | Aluminium Binding wire 6 SWG |
39 | Aluminium Paint |
40 | Chemical Earthing Complete |
41 | Red Oxide Paint |
42 | Bolts, Nut & Washer All size |
43 | Aluminium Crimping Lug 70sqmm |
44 | Aluminium Crimping Lug 240 sqmm |
45 | Aluminium Crimping Lug 400 sqmm |
46 | LT Shackle Insulator |
47 | Copper Z Clamp |
48 | I- Hook |
49 | PRC 120 Sqmm |
50 | PRC 90 Sqmm |
51 | DD Wire PVC 70 Sqmm |
52 | LT Cubical Box For Tailness Unit |
53 | Tailness Unit 500 Amp |
54 | Copper Strip 50x6sqmm |
55 | GI Strip 50x6 |
56 | Service Clamp for ST Pole |
57 | PVC Cable 1x35 Sqmm |
58 | MS Angle 50x50x6 MM 18" |
59 | U-Bolt with Nuts |
60 | MOUNTING, FITTING & ERECTION OF WORK AS PER RESPO NORM. (Part-B) |
61 | Eerection, grouting, plinthing & painting of 11 mtr single supportwith disconnent from old pole,tapping on new pole of 11 KV line ,1 no "v" cross armincluding fixing of necessary clamps, other accessories likeguarding angle ,disc insulator with fitting, pin insulator, L.T arm, shackle insulatoretc. grouting ratio 1:4:8, cement, stone grit & coarse sand, plinthing of support of size 0.4x0.45x0.3 Mtr.with cement sand& bricks blast in ratio 1:4:8 and 12 mm thick plastring around the plingth in ration 1:2:4 with 12 mm thickness curing of plingth should be done properly (Grouting , plinthing and all required material will be arranged by the contractor as per Resspo and Electrical Safety rule,only S.T.Pole provided by Deptt.) |
62 | Fixing & grouting of stay rod with cement, sand and bricks ballast in ratio !:4:8 and fasteniong the stay wire with pole and stay rod nozzling.(Grouting material will be arranged by the contractorasper Resspo and Electrical safety rules.) |
63 | Earthing of support complete with the help of M.S. rod 16 mm dia and 2.5 mtr. long, fastening of G.I. wire with clamps/X-arm/support to M.S. earth rodas per Resspo and Electrical Safety rule |
64 | Spreading and stringing of 1 stay wire continuous conductor for hanging 11 KV cable including binding of insulator complete in all respect. The work includes jumpering/connecting of conductor at sectional poleas per Resspo and Electrical Safety rule |
65 | Laying of single 11 KV, 3x185 sq mm XLPE cable Hanging with the help of stay wire/normal soil by digging of trench 900 mm deep, 600 mm wide including supply of required material like first class brick, stone pad and sand etc. The enter axial spacing between two cable( in case of any other cable is also running in parallel) should be in between o.25 mtr. to .40 mtr. The cable shall be laid between two continous rows of bricks, river sand packing on all side of cable shall be done. After laying down of the cable the stone slab shall be laid in such a manner so that cable channel is completely covered from top. The cable shall be laid strictly in compliance to RESSPO Norms and Electrical safety rules (All material required for laying will be supplied by the contractor. 11 KV cable provided by Deptt.) |
66 | Laying of single 11 KV, 3x120 sq mm XLPE cable Hanging with the help of stay wire/normal soil by digging of trench 900 mm deep, 600 mm wide including supply of required material like first class brick, stone pad and sand etc. The enter axial spacing between two cable( in case of any other cable is also running in parallel) should be in between o.25 mtr. to .40 mtr. The cable shall be laid between two continous rows of bricks, river sand packing on all side of cable shall be done. After laying down of the cable the stone slab shall be laid in such a manner so that cable channel is completely covered from top. The cable shall be laid strictly in compliance to RESSPO Norms and Electrical safety rules (All material required for laying will be supplied by the contractor. 11 KV cable provided by Deptt.) |
67 | Fixing ofHeat Shrink cable type end Terminations suitable for 11 KV, 3x185/3x120 sq mm XLPE cable and 11 KV 3x185/3x120 sq mmasper Resspo and Electrical safety rules. |
68 | Outdoor/indoor jointing kit |
69 | Straight through jointing kit |
70 | Erection & commissioning of 11 KV VCB incoming in the switch gear room, by grouting base channel 100 x 50 x 6 x 1000mm. Fixing of 11 KV switchgears rag bolt with proper connection & earthing with GI Strip 50x6mm , control cable & Earthing Materials provided by contractor. 11 KV VCB provided by Deptt. |
71 | Erection & commissioning of 11 KV VCBoutgoing in the switch gear room, by grouting base channel 100 x 50 x 6 x 1000mm. Fixing of 11 KV switchgears rag bolt with proper connection, & earthing with GI Strip 50x6mm , control cable & Earthing Materialsby contractor. 11 KV VCB provided by Deptt. |
72 | Erection, grouting, plinthing, earthing & painting of 11 mtr long sub station type D/P formounting of T/Fs with all accessories like 11 kv fuse set, TPMO, top channel, grouting in ratio1:4:8, cement, stone grit & coarse sand, plinthing of support of size 0.4x0.45x0.3 Mtr.with cement sand& bricks blast in ratio 1:4:8 and 12 mm thick plastring around the plingth in ration 1:2:4 with 12 mm thickness curing of plingth should be done properly as per Resspo and Electrical Safety rule |
73 | Fixing & grouting of stay rod with cement, sand and bricks ballast in ratio !:4:8 and fasteniong the stay wire with pole and stay rod nozzling.(Grouting material will be arranged by the contractorasper Resspo and Electrical safety rules.) |
74 | Earthing of support complete with the help of M.S. rod 16 mm dia and 2.5 mtr. long, fastening of G.I. wire with clamps/X-arm/ support to M.S. earth rodas per Resspo and Electrical Safety rule |
75 | Construction of 11/0.4 KV Transformer plinth in size 1.5x1.5x 1.8 mtr. Height, including 0.6 mtr. below G.l. in bottom 1:4:8 cement sand and brick ballast; concreting upto 15 cm. thickness after ramming should be done. Thickness of 1st class brick work should be 0.35 mtr. below G.L. and above G.L. It should be 0.23 mtr. brick work bill be done with 1:4 cement, sand mortar, The space between the four walls should be filled with sand by ramming and watering keeping a space of 0.15 mtr on lop for 1:2:4 cement stone ballast and sand concreting. The two channels should be grouted as per direction of site in charge. All the sides of wall above G, L. should be plastered by 1:6 cement sand mortar having 12 mm thickness. |
76 | Providing and fixing of welded wire mesh fencing, around transformer plinth having one locking arrangements, Fencing should be provided by grouting MS angle 40x40x5 mm. length of 1.5 m. on all the sides as per standard practice and design. The painting of fencing should be done by good quality green paint with two coats after rubbing and cleaning and providing one coat red oxide primer. The fencing should be 2 M. above ground level. The rates should be inclusive of all materials required for completion of above work. (Plinthing and all required material will be arranged by the contractor per Resspo and Electrical Safety rule) |
77 | Erection & commissioningof T/F 250 KVA on plinth. along with HT/LT connections with copper L-piece. Complete in all respect,as per Resspo and Electrical Safety rule |
78 | Earthing of transformer body and neutral by lowering of chemical pipe/Rod (earthing)connecting with GI Strip of size 50x6 mm with clamps, as per Resspo and Electrical Safety rule |
79 | Spreading and stringing of 1 stay wire continuous conductor for hanging 11 KV cable including binding of insulator complete in all respect. The work includes jumpering/connecting of conductor at sectional poleas per Resspo and Electrical Safety rule |
80 | Laying of single 11 KV, 3x70 sq mm XLPE cable by Hanging with the help of stay wireThe cable shall be laid strictly in compliance to RESSPO Norms and Electrical safety rules (All material required for laying will be supplied by the contractor. 11 KV cable provided by Deptt.) |
81 | Fixing ofHeat Shrink cable type end Terminations suitable for 11 KV, 3x70 sq mm XLPE cable and 11 KV 3x70 sq mmasper Resspo and Electrical safety rules. Outdoor jointing kit |
82 | Laying of single 11 KV, 1x70 sq mm XLPE cable Hanging from HT line to T/F HT bhushing including Tapping from HT Line,crimping lug both sides and all Related HT,LT connection etc (All material required for laying will be supplied by the contractor. 11 KV cable provided by Deptt.) |
83 | Erection and grouting of LT Cubical Box, Making platform for stepping, plastering the same with cement sand in raio 1:6 Fising the tailless unit 500 Amp making LT Bus Bar and its taping. |
84 | Errection andFixing the tailless unit 500 Amp in existing LT cubical Box/Double pole making Copper LT Bus Bar and its taping. |
85 | Laying/hanging of following LT cable of different sizes for main/distribution/connecting the main cable from T/F to tailless unit and for distribution, from tailless unit to LT section Pole, crimping the both ends of cable if required and tapping be made inside distribution box making channel of first class brick and filling with soil. |
86 | 1x400 sq. mm. |
87 | 3 ½x240 sq. mm. |
88 | Errection & Commissioning of (3x120+1x195+1x16) sq.mm ABC,necessary clamps, I-Hook, dead end clamp, suspension clamp,pierising connecter 1x35 sq.mm. & 1x16 sq.mm. PVC cable as per RESSPO norms will be arranged by the contractor exept AB cable as per Resspo and Electrical Safety rule |
89 | Errection & Commissioning of distribution boxes/kiosk on the LT poles including all clamps & materials required, connections & sealing its connection in between Distribution Box & ABC 1x35 sq. mm LT PVC cable (all required Local materialsarranged by the contractor as per Resspo and Electrical Safety rule) |
90 | Construction of 11/0.4 KV Transformer plinth in size 1.5x1.5x 1.8 mtr. Height, including 0.6 mtr. below G.l. in bottom 1:4:8 cement sand and brick ballast; concreting upto 15 cm. thickness after ramming should be done. Thickness of 1st class brick work should be 0.35 mtr. below G.L. and above G.L. It should be 0.23 mtr. brick work bill be done with 1:4 cement, sand mortar, The space between the four walls should be filled with sand by ramming and watering keeping a space of 0.15 mtr on lop for 1:2:4 cement stone ballast and sand concreting. The two channels should be grouted as per direction of site in charge. All the sides of wall above G, L. should be plastered by 1:6 cement sand mortar having 12 mm thickness. |
91 | Erection & commissioningof T/F 400 KVA on New/Existing plinth. along with HT/LT connections with copper L-piece. Complete in all respect,as per Resspo and Electrical Safety rule |
92 | Earthing of transformer body and neutral by lowering of chemical pipe/Rod (earthing)connecting with GI Strip of size 50x6 mm with clamps, as per Resspo and Electrical Safety rule |
93 | Erection and grouting of LT Cubical Box, Making platform for stepping, plastering the same with cement sand in raio 1:6 Fising the tailless nit 500/300 Amp making LT Bus Bar and its taping. |
94 | Errection andFixing the 500 Amp. tailless unit in existing LT cubical Box/Double pole making LT Bus Bar and its taping. |
95 | Laying/hanging of following LT cable of different sizes for main/distribution/connecting the main cable from T/F to tailless unit and for distribution, from tailless unit to LT section Pole, crimping the both ends of cable if required and tapping be made inside distribution box making channel of first class brick and filling with soil. |
96 | 1x400 sq. mm. |
97 | 3 ½ x240 sq. mm. |
98 | Errection & Commissioning of (3x120+1x195+1x16)/ (3x95+1x70+1x16) sq.mm ABC,necessary clamps, I-Hook, dead end clamp, suspension clamp,pierising connecter 1x35 sq.mm. & 1x16 sq.mm. PVC cable as per RESSPO norms will be arranged by the contractor exept AB cable as per Resspo and Electrical Safety rule |
99 | Errection & Commissioning of distribution boxes/kiosk on the LT poles including all clamps & materials required, connections & sealing its connection in between Distribution Box & ABC 1x35 sq. mm LT PVC cable (all required Local materialsarranged by the contractor as per Resspo and Electrical Safety rule) |
100 | Dismantling of all the HT/LT line, connections & earthing of old 11/.4 kV, 250 KVA transformer along with LT cubical box, cable GO set, DO set & T/F, safe loading carrage and unloading of dismentled item from site of work to center store Naini/Power House store/New site. |
101 | Erection, grouting, plinthing,& painting of single support pole 9 mtr long STPfor LT line, including fixing of necessary clamps grouting in ratio1:4:8, cement, stone grit & coarse sand,plinthing of support of size 0.4x0.45x0.3 Mtr.with cement sand& bricks blast in ratio 1:4:8 and 12 mm thick plastring around the plingth in ratio 1:2:4 with 12 mm thickness curing of plingth should be done properly (Grouting & plinthing related all required material will be arranged by the contractor except 9 mtr long STPas per Resspo and Electrical Safety rule) |
102 | Errection & Commissioning of (3x120+1x195+1x16) sq.mm ABC,necessary clamps, I-Hook, dead end clamp, suspension clamp,pierising connecter 1x35 sq.mm. & 1x16 sq.mm. PVC cable as per RESSPO norms will be arranged by the contractor exept AB cable as per Resspo and Electrical Safety rule |
103 | Errection & Commissioning of ACSR Weasl for neutral conductor in LT AB line with fixing of LT X-arm, LT shackle insulator, clamps etc. at existing LT pole Weasel Conductor provided by Deptt. |
104 | Errection andFixing the tailless unit 500 Amp.in existing LT cubical Box/Double pole making LT Bus Bar and its taping. |
105 | Opeing from old line & Reconnection with New LT Line of Consumers service cable of three phase /single phase |
106 | Single Phase |
107 | Three Phase |
108 | Laying/hanging of following LT cable of different sizes for main/distribution/connecting the main cable from T/F to tailless unit and for distribution, from tailless unit to LT section Pole, crimping the both ends of cable if required and tapping be made inside distribution box making channel of first class brick and filling with soil. |
109 | 3 ½ x/240 sq. mm. |
110 | Errection & Commissioning of distribution boxes/kiosk on the LT poles including all clamps & materials required, connections & sealing its connection in between Distribution Box & ABC 1x35 sq. mm LT PVC cable (all required Local materialsarranged by the contractor as per Resspo and Electrical Safety rule) |
111 | Erection, grouting, plinthing,& painting of single support pole 9 mtr long STPfor LT line, including fixing of necessary clamps grouting in ratio1:4:8, cement, stone grit & coarse sand,plinthing of support of size 0.4x0.45x0.3 Mtr.with cement sand& bricks blast in ratio 1:4:8 and 12 mm thick plastring around the plingth in ratio 1:2:4 with 12 mm thickness curing of plingth should be done properly (Grouting & plinthing related all required material will be arranged by the contractor except 9 mtr long STPas per Resspo and Electrical Safety rule) |
112 | Earthing of support complete with the help of M.S. rod 16 mm dia and 2.5 mtr. long, fastening of G.I. wire with clamps/X-arm/ support to M.S. earth rodas per Resspo and Electrical Safety rule |
113 | Opeing from old line & Reconnection with New LT Line of Consumers service cable of three phase /single phase |
114 | Single Phase |
115 | Three Phase |
116 | Dismantling of old LT/HT supports along with all accessories on pole. |
117 | 9 Mtr STP. |
118 | Loading cariedge and unloading of dismentaled item from site of work to centre store Naini/power house store. |
119 | 9 Mtr STP |
120 | Other petty materials as conductor, cross arms, channels, angles, D.O. fuse set, TPMO, LT cubical box, clamps etc. |
121 | Eerection, grouting, plinthing & painting of 11 mtr single supportwith disconnent from old pole,tapping on new pole of 11 KV line ,1 no "v" cross armincluding fixing of necessary clamps, other accessories likeguarding angle ,disc insulator with fitting, pin insulator, L.T arm, shackle insulatoretc. grouting ratio 1:4:8, cement, stone grit & coarse sand, plinthing of support of size 0.4x0.45x0.3 Mtr.with cement sand& bricks blast in ratio 1:4:8 and 12 mm thick plastring around the plingth in ration 1:2:4 with 12 mm thickness curing of plingth should be done properly (Grouting , plinthing and all required material will be arranged by the contractor as per Resspo and Electrical Safety rule,only S.T.Pole provided by Deptt.) |
122 | Earthing of support complete with the help of M.S. rod 16 mm dia and 2.5 mtr. long, fastening of G.I. wire with clamps/X-arm/ support to M.S. earth rodas per Resspo and Electrical Safety rule |
123 | Opeing from old line & Reconnection with New LT Line of Consumers service cable of three phase /single phase |
124 | Single Phase |
125 | Three Phase |
126 | Dismantling of old LT/HT supports along with all accessories on pole. |
127 | 9/11/13 Mtr STP. |
128 | Loading cariedge and unloading of dismentaled item from site of work to centre store Naini/power house store. |
129 | 9/11 Mtr STP |
130 | Other petty materials as conductor, cross arms, channels, angles, D.O. fuse set, TPMO, LT cubical box, clamps etc. |
131 | Earthing of transformer body and neutral by lowering of chemical pipe (earthing)connecting with GI Strip of size 25x6 mm with clamps, as per Resspo and Electrical Safety rule |
132 | Cartage of 11/9 Mtr STP from Store to dump store/work Site Including loading and unloading |
133 | Cartage of 400/250 kva Transformer from Store to dump store/work Site Including loading and unloading |
134 | Cartage of LT 1x400, 1x240, 3.5x400, 3.5x240 sqmm from Store to dump store/work Site Including loading and unloading |
135 | Cartage of 3X185, 3x120, 3x70 SQ MM xlpe 11 KV XPLE CABLE from Store to dump store/work Site Including loading and unloading |
136 | Cartage of LT ABC from Store to dump store/work Site Including loading and unloading |
137 | Cartage of ACSR Weasel conductor from Store to dump store/work Site Including loading and unloading |
138 | Other petty materials as conductor, cross arms, channels, angles, D.O. fuse set, TPMO, LT cubical box, clamps etc. |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy