Increasing Capacity Of Kulhui Sub Station And Construction Of 33 Kv Line In District Mahrajganj
Tender Overview
Project Description
Increasing Capacity Of Kulhui Sub Station And Construction Of 33 Kv Line In District Mahrajganj- 1 Work No. 01Part-A- Providing Following Materials By The Contractor. 2 33 Kv ‘Xlpe’ C / J Kit 3X300mm² Outdoor 3 33 Kv ‘V’ Type Cross Arm 100X50x6mm, Ms Channel ( 7.9 Kg / M ) 4 33 Kv Polymer Pin Insulator 5 Number Plate 6 Danger Board With Clamp 7 Barbed Wire 8 Bolts, Nuts, & Washers 9 X-Armclamp With Nut Bolt For St Pole 11 Mtr With Nut Bolt By 50X8 Mm Msflat Iron Make 10 X-Arm Clamp With Nut Bolt For Pcc Pole 9 Mtr With Nut Bolt By 50X8 Mm Msflat Iron Make 11 Stay Set With Clamp For St Pole 11Mtr. With Nut And Bolt By 50X8 Mm Ms Flat Iron Make. 12 Stay Set With Clamp For Pcc Pole 9 Mtrwith Nut And Bolt By 50X8 Mm Ms Flat Iron Make. 13 Stay Rod 20X1800 Mm 14 Stay Wire 7 / 8 Swg 15 Ms Earthing Rod 20X2500 Mm 16 33 Kv Polymer Disc Insulator 70 Kn B&S Type 17 Disc Fitting 70 Knb&S Type For Dog 18 P.G. Clamp For Dog 19 ‘E’ Bracket For 33 Kv 20 M.S. Angle Iron 65X65x6mm Bracing With Clamps 21 33 Kv. Top Channel ( 125X65mmx3200 Mm ( 10.7 Kg / M ) With Clamps 22 33 Kv Guarding Angle 23 Gi Wire 5 Mm 24 33 Kv Guarding Angle Clamp With Nut Bolt For St Pole 11Mtr. With Nut And Bolt By 50X8 Mm Ms Flat Iron Make. 25 33 Kv Guarding Angle Clamp With Nut Bolt For Pcc Pole 9 Mtr. With Nut And Bolt By 50X8 Mm Ms Flat Iron Make. 26 F-Bracket With Nut Bolt For St Pole 11 Mtr & Pcc Pole 9 Mtr With Nut Bolt By 50X8 Mm Msflat Iron Make 27 Part-B Workshifting, Loading And Carriageof Following Materials On Private Truck At Store Centre Maharajganj & Un-Loading Of The Same With Proper Stacking At Work Site . 28 P.C.C.Pole9 M Long 29 S.T. Pole – 11 Mtr. Long 30 33 Kv ‘Xlpe’ Cable 3X300mm² 31 Acsr ‘Dog’ Conductor 32 Laying Of 33 Kv 3X300 Mm² ‘Xlpe’ Cable Of Double Circuit ( 220X2 Mtr ) Cable By Digging Pit & Making Trench In Proper Size ( 1.2M Depth X1m Wide ) Below Ground Level By Fixing Bricks ( 4½? ) On Both Side Of Trench Wall And 9? Brick Work At The Centre Of The Trench Along The Cable.Fixing Brick Slab On Top After Filling Sand Around Both The Cable Including Cost Of Bricks / Hdd Method By Drillingmachine As Per Site Requirement. 33 Laying Of 33Kv ‘Xlpe’ Cable In Air After Providing 6” Dia. M.S Pipe 3 M Long Complete Work. ( Rs 1475 / Mtr ) 34 Providing & Cable Jointing Charges Of 33 Kv Xlpe Cable Outdoor. 35 Gi Pipeearthing Complete Forcable Jointing Kit With Materials 36 Fabrication Of 13 M Long S.T. Pole By Welding 3.0 M Long 5 Dia M.S. Pipe & Flat Iron 50X6 Mm 12 Long By Providing M.S. Pipe And All Other Materials By The Contractor And Only S.T. Poles 11 Mtr. Long Will Be Provided By The Department. 37 Erection Of Single Pole Structure On 9 Mtr Pcc Pole Including All Works Of Evocation Of Pit, Pole Erection, Making Plinth For Poles 30 Cm Above , Grouting In The Ratio 1:4:8 ( Cement, Sand, 40Mm Brick Ballast ) , Back Filling Of Earth , Proper Ramming & Fitting Of All Accessories For Double Circuit ( V Type Cross Arm 100 X 50 X 6 Mm, M.S. Channel ( 7.9 Kg. / M ) Clamps With Bolt And Nut, Composite Polymer Pin Insulator, Danger Board With Clamp, Barbed Wire Earthing, Etc. Complete As Per Resspo ) . 38 Extension Of 9 Mtr Pcc Pole For Proper Clearence For Existing Lines By 33 Kv Top Channel With Clamp With Complete Work As Per Proper Specification. 39 Erection Of Double Pole Structure On 9 Mtr Pcc Poleincluding All Works Of Evocation Of Pit, Pole Erection, Making Plinth For Poles 30 Cm Above , Grouting In The Ratio 1:4:8 ( Cement, Sand, 40 Mm Brick Ballast ) , Back Filling Of Earth , Proper Ramming & Fitting Of All Accessories ( M.S. Angle Iron 65 X 65 X 6 Mm Bracing With Clamps, Top Channel 125 X 65 X 3200 Mm With Clamps, Danger Board With Clamp, Barbed Wire Earthing, Etc. Complete As Per Resspo ) . 40 Erection Of Four Pole Structure On 9 Mtr Pcc Poleincluding All Works Of Evocation Of Pit, Pole Erection, Making Plinth For Poles 30 Cm Above , Grouting In The Ratio 1:4:8 ( Cement, Sand, 40 Mm Brick Ballast ) , Back Filling Of Earth , Proper Ramming & Fitting Of All Accessories ( M.S. Angle Iron 65 X 65 X 6 Mm Bracing With Clamps, Top Channel 125 X 65 X 3200 Mm With Clamps, Danger Board With Clamp, Barbed Wire Earthing, Etc. Complete As Per Resspo ) . 41 Erection Of Single Pole Structure On 11Mtr St. ( Sp-55 ) Pole Including All Works Of Evocation Of Pit, Pole Erection, Making Plinth For Poles 30 Cm Above , Grouting In The Ratio 1:4:8 ( Cement, Sand, 40Mm Brick Ballast ) , Back Filling Of Earth , Proper Ramming & Fitting Of All Accessories For Double Circuit ( V Type Cross Arm 100 X 50 X 6 Mm, M.S. Channel ( 7.9 Kg. / M ) Clamps With Bolt And Nut, Composite Polymer Pin, Insulator, Danger Board With Clamp, Alluminium Paint, Red Oxide Paint, Barbed Wire Earthing, Etc. Complete As Per Resspo. 42 Erection Of Double Pole Structure On 11 Mtr St Pole Including All Works Of Evocation Of Pit, Pole Erection, Making Plinth For Poles 30 Cm Above , Grouting In The Ratio 1:4:8 ( Cement, Sand, 40 Mm Brick Ballast ) , Back Filling Of Earth , Proper Ramming & Fitting Of All Accessories ( M.S. Angle Iron 65 X 65 X 6 Mm Bracing With Clamps, Top Channel 125 X 65 X 3200 Mm With Clamps, Danger Board With Clamp, Alluminium Paint, Red Oxide Paint, Barbed Wire Earthing, Etc. Complete As Per Resspo ) . 43 Erection Of Four Pole Structure On 11 Mtr St Pole Including All Works Of Evocation Of Pit, Pole Erection, Making Plinth For Poles 30 Cm Above , Grouting In The Ratio 1:4:8 ( Cement, Sand, 40 Mm Brick Ballast ) , Back Filling Of Earth , Proper Ramming & Fitting Of All Accessories ( M.S. Angle Iron 65 X 65 X 6 Mm Bracing With Clamps, Top Channel 125 X 65 X 3200 Mm With Clamps, Danger Board With Clamp, Alluminium Paint, Red Oxide Paint, Barbed Wire Earthing, Etc. Complete As Per Resspo ) . 44 Laying, Spreading, Lifting And Final Sagging Of 3 Phases Of Acsr Dog Conductorin Accordance With Profile And Sag Chart Including Binding, Jumpering And Fixing Of P.G. Clamp As Per Requirement In 03 Nos. Conductor In Parallel. 45 Grouting Of Stay Rods ( 20 X 1800 ) Mm Including All Work Of Excavation, Cement Concrete In Size ( 0.60 X 0.60 X 0.30 ) M In Ratio 1:4:8 Cement, Sand, 40Mm Brick Ballast ) As Per Drg Including Back Filling, Proper Ramming Etc. Fixing Tightening & Nozzling Of Stay Wire With Stay Rod With The Poles Of Required Tension As Per Drawing. 46 Painting Of S.T Pole 11 Mtr. Long With Alluminium Paint And Red Oxide Paint Etc. 47 Chopping Of Branches Of Trees Of Eucalyptus, Neem, Keekar And Other Kind Of Trees Along The Route Of The Line And Disposal Of The Same At Suitable Place. 48 Guarding Between Two Poles Like Single Poles, Double Poles, Four Poles, Densearea Etc. To Guard Lt, 11 Kv Line Telephone And River Crossing, Road Crossing Etc. With G.I. Wire No. 6 Swg And G.I. Wire No. 8 Swg, Cutting, Fabrication And Fixing Of Guarding Channel 75 X 40 X 3010 Mm With Clamps Nut & Bolts Etc. As Per Drawing. 49 Work No. 02Part-A- Providing Following Materials By The Contractor. 50 33Kv ‘Xlpe’ C / J Kit 3X300mm² Outdoor 51 33Kv ‘V’ Type Cross Arm 100X50x6mm, Ms Channel ( 7.9 Kg / M ) 52 33 Kv Polymer Pin Insulator 53 Number Plate 54 Danger Board With Clamp 55 Barbed Wire 56 Bolts, Nuts, & Washers 57 X-Armclamp With Nut Bolt For St Pole 11 Mtr With Nut Bolt By 50X8 Mm Msflat Iron Make 58 X-Arm Clamp With Nut Bolt For Pcc Pole 9 Mtr With Nut Bolt By 50X8 Mm Msflat Iron Make 59 Stay Set With Clamp For St Pole 11Mtr. With Nut And Bolt By 50X8 Mm Ms Flat Iron Make. 60 Stay Set With Clamp For Pcc Pole 9 Mtrwith Nut And Bolt By 50X8 Mm Ms Flat Iron Make. 61 Stay Rod 20X1800 Mm 62 Stay Wire 7 / 8 Swg 63 Ms Earthing Rod 20X2500 Mm 64 33 Kv Polymer Disc Insulator 70 Kn B&S Type 65 Disc Fitting 70 Knb&S Type For Dog 66 P.G. Clamp For Dog 67 ‘E’ Bracket For 33 Kv 68 M.S. Angle Iron 65X65x6mm Bracing With Clamps 69 33 Kv. Top Channel ( 125X65mmx3200 Mm ( 10.7 Kg / M ) With Clamps 70 33 Kv Guarding Angle 71 Gi Wire 5 Mm 72 33 Kv Guarding Angle Clamp With Nut Bolt For St Pole 11Mtr. With Nut And Bolt By 50X8 Mm Ms Flat Iron Make. 73 33 Kv Guarding Angle Clamp With Nut Bolt For Pcc Pole 9 Mtr. With Nut And Bolt By 50X8 Mm Ms Flat Iron Make. 74 F-Bracket With Nut Bolt For St Pole 11 Mtr & Pcc Pole 9 Mtr With Nut Bolt By 50X8 Mm Msflat Iron Make 75 Part B Work Shifting, Loading And Carriageof Following Materials On Private Truck At Store Centre Maharajganj & Un-Loading Of The Same With Proper Stacking At Work Site . 76 P.C.C.Pole9 M Long 77 S.T. Pole – 11 Mtr. Long 78 33 Kv ‘Xlpe’ Cable 3X300mm² 79 Acsr ‘Dog’ Conductor 80 Laying Of 33 Kv 3X300 Mm² ‘Xlpe’ Cable Of Double Circuit By Digging Pit & Making Trench In Proper Size ( 1.2M Depth X1m Wide ) Below Ground Level By Fixing Bricks ( 4½? ) On Both Side Of Trench Wall And 9? Brick Work At The Centre Of The Trench Along The Cable.Fixing Brick Slab On Top After Filling Sand Around Both The Cable Including Cost Of Bricks / Hdd Method By Drillingmachine As Per Site Requirement. 81 Laying Of 33Kv ‘Xlpe’ Cable In Air After Providing 6” Dia. M.S Pipe 3 M Long Complete Work. ( Rs 1475 / Mtr ) 82 Providing & Cable Jointing Charges Of 33 Kv Xlpe Cable Outdoor. 83 Gi Pipeearthing Complete Forcable Jointing Kit With Materials 84 Fabrication Of 13 M Long S.T. Pole By Welding 3.0 M Long 5 Dia M.S. Pipe & Flat Iron 50X6 Mm 12 Long By Providing M.S. Pipe And All Other Materials By The Contractor And Only S.T. Poles 11 Mtr. Long Will Be Provided By The Department. 85 Erection Of Single Pole Structure On 9 Mtr Pcc Pole Including All Works Of Evocation Of Pit, Pole Erection, Making Plinth For Poles 30 Cm Above , Grouting In The Ratio 1:4:8 ( Cement, Sand, 40Mm Brick Ballast ) , Back Filling Of Earth , Proper Ramming & Fitting Of All Accessories For Double Circuit ( V Type Cross Arm 100 X 50 X 6 Mm, M.S. Channel ( 7.9 Kg. / M ) Clamps With Bolt And Nut, Composite Polymer Pin Insulator, Danger Board With Clamp, Barbed Wire Earthing, Etc. Complete As Per Resspo ) . 86 Extension Of 9 Mtr Pcc Pole For Proper Clearence For Existing Lines By 33 Kv Top Channel With Clamp With Complete Work As Per Proper Specification. 87 Erection Of Double Pole Structure On 9 Mtr Pcc Poleincluding All Works Of Evocation Of Pit, Pole Erection, Making Plinth For Poles 30 Cm Above , Grouting In The Ratio 1:4:8 ( Cement, Sand, 40 Mm Brick Ballast ) , Back Filling Of Earth , Proper Ramming & Fitting Of All Accessories ( M.S. Angle Iron 65 X 65 X 6 Mm Bracing With Clamps, Top Channel 125 X 65 X 3200 Mm With Clamps, Danger Board With Clamp, Barbed Wire Earthing, Etc. Complete As Per Resspo ) . 88 Erection Of Four Pole Structure On 9 Mtr Pcc Poleincluding All Works Of Evocation Of Pit, Pole Erection, Making Plinth For Poles 30 Cm Above , Grouting In The Ratio 1:4:8 ( Cement, Sand, 40 Mm Brick Ballast ) , Back Filling Of Earth , Proper Ramming & Fitting Of All Accessories ( M.S. Angle Iron 65 X 65 X 6 Mm Bracing With Clamps, Top Channel 125 X 65 X 3200 Mm With Clamps, Danger Board With Clamp, Barbed Wire Earthing, Etc. Complete As Per Resspo ) . 89 Erection Of Single Pole Structure On 11Mtr St. ( Sp-55 ) Pole Including All Works Of Evocation Of Pit, Pole Erection, Making Plinth For Poles 30 Cm Above , Grouting In The Ratio 1:4:8 ( Cement, Sand, 40Mm Brick Ballast ) , Back Filling Of Earth , Proper Ramming & Fitting Of All Accessories For Double Circuit ( V Type Cross Arm 100 X 50 X 6 Mm, M.S. Channel ( 7.9 Kg. / M ) Clamps With Bolt And Nut, Composite Polymer Pin, Insulator, Danger Board With Clamp, Alluminium Paint, Red Oxide Paint, Barbed Wire Earthing, Etc. Complete As Per Resspo. 90 Erection Of Double Pole Structure On 11 Mtr St Pole Including All Works Of Evocation Of Pit, Pole Erection, Making Plinth For Poles 30 Cm Above , Grouting In The Ratio 1:4:8 ( Cement, Sand, 40 Mm Brick Ballast ) , Back Filling Of Earth , Proper Ramming & Fitting Of All Accessories ( M.S. Angle Iron 65 X 65 X 6 Mm Bracing With Clamps, Top Channel 125 X 65 X 3200 Mm With Clamps, Danger Board With Clamp, Alluminium Paint, Red Oxide Paint, Barbed Wire Earthing, Etc. Complete As Per Resspo ) . 91 Erection Of Four Pole Structure On 11 Mtr St Pole Including All Works Of Evocation Of Pit, Pole Erection, Making Plinth For Poles 30 Cm Above , Grouting In The Ratio 1:4:8 ( Cement, Sand, 40 Mm Brick Ballast ) , Back Filling Of Earth , Proper Ramming & Fitting Of All Accessories ( M.S. Angle Iron 65 X 65 X 6 Mm Bracing With Clamps, Top Channel 125 X 65 X 3200 Mm With Clamps, Danger Board With Clamp, Alluminium Paint, Red Oxide Paint, Barbed Wire Earthing, Etc. Complete As Per Resspo ) . 92 Laying, Spreading, Lifting And Final Sagging Of 3 Phases Of Acsr Dog Conductorin Accordance With Profile And Sag Chart Including Binding, Jumpering And Fixing Of P.G. Clamp As Per Requirement In 03 Nos. Conductor In Parallel. 93 Grouting Of Stay Rods ( 20 X 1800 ) Mm Including All Work Of Excavation, Cement Concrete In Size ( 0.60 X 0.60 X 0.30 ) M In Ratio 1:4:8 Cement, Sand, 40Mm Brick Ballast ) As Per Drg Including Back Filling, Proper Ramming Etc. Fixing Tightening & Nozzling Of Stay Wire With Stay Rod With The Poles Of Required Tension As Per Drawing. 94 Painting Of S.T Pole 11 Mtr. Long With Alluminium Paint And Red Oxide Paint Etc. 95 Chopping Of Branches Of Trees Of Eucalyptus, Neem, Keekar And Other Kind Of Trees Along The Route Of The Line And Disposal Of The Same At Suitable Place. 96 Guarding Between Two Poles Like Single Poles, Double Poles, Four Poles, Etc. To Guard Lt, 11 Kv Line Telephone And River Crossing, Road Crossing Etc. With G.I. Wire No. 6 Swg And G.I. Wire No. 8 Swg, Cutting, Fabrication And Fixing Of Guarding Channel 75 X 40 X 3010 Mm With Clamps Nut & Bolts Etc. As Per Drawing. 97 Work No. 03Shifting & Loading Of Following Materials On Private Truck At Store Centre Maharajganj& Carriage Up To 33 / 11 Kv Sub-Station Koluhi, Distt- Maharajganj & Un-Loading Of The Same With Proper Stacking ( Distance About0 To 55 Km ) 98 11 Kv ‘Xlpe’ Power Cable. 99 33 Kv ‘Vcb’ Complete With All Structure. 100 33 Kv. C.T. 101 33 Kv C.T.Structure 102 33 Kv Fuse Set 103 33 Line Type Isolator 104 33 Bus Type Isolator 105 33 Kv Post Insulator 106 Structure For Above 107 33 Kv Single T / F Control Pannel 108 33 Kv Lightening Arrester 109 33 Kv La Structure. 110 Repairing Of Plinth And Foundation For 10 Mva Transformer As Per Required Specification. Dismantling Of T / F All Connection. 111 Dismentling Of Existing 2 No Body And 1 No Neutral Earthing Safely Of Existing 5 Mva Power Transformer Earthing For Installation Of New 10 Mva T / F And Re-Earthing Of New 10 Mva T / F By Old Earth Strip Including Providing Required Length Of Gi Earth Strip .The Earthing Of 10 Mva T / F Included All Work Completed As Per Required Specification Of Resspo Norms. 112 Providing33 Kv. Top Channel For Cable Stand & Neutral Earthing 113 Dismentling Of Ht Jumpers, 11 Kv C / J Kit And Different Earthing Of 5 Mva T / F Drain Out T / F Oil After Closing Valve And Opening Of Radiator For Shifting Of Existing 5 Mva T / F From Plinth About 30 Mtr. Distance & Resetting Of All Accessories Etc. Complete Work. 114 Digging Of Pit For Taking Out Of Old & Used Running Condition 11 Kv Cable Safely. 115 Grouting Of M.S. Channel 3.2 Mtr Long For Cable Stand And Welding Of M.S. Flat At Equal Distance For Fastening Cable By Clamp With Nuts And Bolts Mounting Of Cable At Cable Stand And Connection Of Jumpers. 116 Providing & Jointing Charges Of 11 Kv “Xlpe” C / J Kit 3 X 300 Mm2 Indoor / Outdoor Type 117 Laying Of 11 Kv “Xlpe” Power Cable 3 X 300 / 185 Mm2including Digging Of Pits Of Size 0.5 X 0.5 Mtr. Covering Of Cable With Sand And 1St Class Brick Around The Cable. 118 Laying Of 11Kv ‘Xlpe’ Cable In Air After Providing 6” Dia. M.S Pipe 3 M Long Complete Work. 119 Gi Pipeearthing Complete Forcable Jointing Kit With Materials 120 Neutral Earthing Of 10 Mva T / F Complete Including Cost Of Gi Strip, Gi Pipe 1.5 Dia And 30 Long And Other Earthing Materials ( Delta Type ) . 121 Providing And Making Connection Of 24 Volt Battery And Battery Charger With Cabinet. 122 Jumpring From 33 Kv Bus Bar To Post Insulator, Bus Isolator, Vcb, Ct And La To 10 Mva Transformer Etc. ( Providing Alluminium Lug And Pg Clamp ) 123 Installation Of 33 Kv Control Panel For “Vcb” With Complete Earthing With Installation Of Battery And Battery Charger In Control Room And Making Connection. 124 Erection, Installation And Grouting Of “Vcb” Structure Mounting And Fitting Of “Vcb” On Erected Structure With Complete Earthing. 125 Erection, Installation And Grouting Of “Ct” Structure Mounting And Fitting Of “Ct” On Erected Structure With Complete Earthing. 126 Erection, Installation And Grounting Of Fuse Set Structure. Mounting And Fitting Of Fuse Set On Erected Structure With Complete Earthing. 127 Erection, Installation And Grounting Of La Structure. Mounting And Fitting Of La On Erected Structure With Complete Earthing. 128 Mounting And Fitting Of Equipment On Erected Structures. 129 33 Kv Line Isolator 400 Amp 130 33 Kv Bus – Isolator 400 Amp. 131 33 Kv Post Insulator 132 33 Kv La 133 Painting Of Erected Structure In Switchyard ( Applying On Coat Of Good Quality Red Oxide Primer Then Two Coat Of Good Quality Of High Class Luxol Aluminium Paint ) 134 Providing Following Control Cable And Its Laying From Switchyard To Control Room 33 Kv Panel By Digging Trench In Switchyard Including Cost Of Sand And 1St Class Bricks With Covering And Making Connection Complete And Including Cost Of Laying. 135 Size 2 X 2.5 Mm2 136 Size 4 X 2.5 Mm2 137 Dismantling Of Existing Pale Fencing And Resetting After Completion Of Transformer Work. 138 Carriage Of Old And Used 11 Kv ‘Xlpe’ Power Cable From 33 / 11 Kv Sub-Station Koluhi, Distt-Maharajganjto Store Center Maharajganj
BOQ
| Sl. No. | Item Description |
| 1 | Work No. 01Part-A- Providing following materials by the Contractor. |
| 2 | 33 KV ‘XLPE’ C/J Kit 3x300mm² Outdoor |
| 3 | 33 KV ‘V’ Type Cross Arm 100x50x6mm, MS Channel ( 7.9 Kg/m) |
| 4 | 33 KV Polymer Pin Insulator |
| 5 | Number Plate |
| 6 | Danger Board with Clamp |
| 7 | Barbed wire |
| 8 | Bolts, Nuts, & Washers |
| 9 | X-armclamp with nut bolt for ST Pole 11 mtr with nut bolt by 50x8 mm MSflat Iron make |
| 10 | X-arm clamp with nut bolt for PCC Pole 9 mtr with nut bolt by 50x8 mm MSflat Iron make |
| 11 | Stay set with Clamp for ST Pole 11mtr. with Nut and Bolt by 50x8 mm MS Flat Iron make. |
| 12 | Stay set with Clamp for PCC Pole 9 mtrwith Nut and Bolt by 50x8 mm MS Flat Iron make. |
| 13 | Stay Rod 20x1800 mm |
| 14 | Stay wire 7/8 SWG |
| 15 | MS Earthing Rod 20x2500 mm |
| 16 | 33 KV Polymer Disc Insulator 70 KN B&S Type |
| 17 | Disc fitting 70 KNB&S Type for DOG |
| 18 | P.G. Clamp for DOG |
| 19 | ‘E’ Bracket for 33 KV |
| 20 | M.S. Angle Iron 65x65x6mm bracing with clamps |
| 21 | 33 KV. Top channel ( 125x65mmX3200 mm ( 10.7 Kg/m) with clamps |
| 22 | 33 KV Guarding angle |
| 23 | GI Wire 5 mm |
| 24 | 33 KV Guarding angle Clamp with nut bolt for ST Pole 11mtr. with Nut and Bolt by 50x8 mm MS Flat Iron make. |
| 25 | 33 KV Guarding angle Clamp with nut bolt for PCC Pole 9 mtr. with Nut and Bolt by 50x8 mm MS Flat Iron make. |
| 26 | F-bracket with nut bolt for ST Pole 11 mtr & PCC Pole 9 mtr with nut bolt by 50x8 mm MSflat Iron make |
| 27 | Part-B WorkShifting,loading and carriageof following materials on private truck at store centre Maharajganj & Un-loading of the same with proper stacking at work site . |
| 28 | P.C.C.Pole9 M long |
| 29 | S.T. Pole – 11 Mtr. Long |
| 30 | 33 KV ‘XLPE’ Cable 3x300mm² |
| 31 | ACSR ‘Dog’ Conductor |
| 32 | Laying of 33 KV 3x300 mm² ‘XLPE’ cable of double circuit (220X2 Mtr)cable by digging pit & making trench in Proper size(1.2M depth x1M wide) below ground level by fixing bricks(4½?)on both side of trench wall and 9? brick work at the centre of the trench along the cable.Fixing brick slab on top after filling sand around both the cable including cost of bricks/ HDD Method by drillingmachine as per site requirement. |
| 33 | Laying of 33KV ‘XLPE’ cable in air after providing 6” dia. M.S pipe 3 m long Complete work.(Rs 1475/mtr) |
| 34 | Providing & Cable jointing charges of 33 KV XLPE Cable Outdoor. |
| 35 | GI PipeEarthing Complete forCable jointing Kit with materials |
| 36 | Fabrication of 13 M long S.T. pole by welding 3.0 M long 5\" dia M.S. pipe & Flat Iron 50x6 mm 12\" long by providing M.S. pipe and all other materials by the contractor and only S.T. poles 11 Mtr. Long will be provided by the department. |
| 37 | Erection of Single pole structure on 9 Mtr PCC Pole including all works of evocation of pit, pole erection, making plinth for poles 30 cm above , grouting in the ratio 1:4:8 (cement, sand, 40mm brick ballast),back filling of earth ,proper ramming & fitting of all accessories for double circuit ( \"V\" type cross arm 100 x 50 x 6 mm, M.S. Channel (7.9 Kg./M) clamps with bolt and nut, composite polymer pin insulator, danger board with clamp,barbed wire earthing, etc. complete as per RESSPO). |
| 38 | Extension of 9 mtr PCC Pole for proper clearence for existing lines by 33 KV Top channel with clamp with complete work as per proper specification. |
| 39 | Erection of Double pole structure on 9 Mtr PCC Poleincluding all works of evocation of pit, pole erection, making plinth for poles 30 cm above , grouting in the ratio 1:4:8 (cement, sand, 40 mm brick ballast),back filling of earth ,proper ramming & fitting of all accessories (M.S. angle iron 65 x 65 x 6 mm bracing with clamps, top channel 125 x 65 x 3200 mm with clamps, danger board with clamp,barbed wire earthing, etc. complete as per RESSPO) . |
| 40 | Erection of Four pole structure on 9 Mtr PCC Poleincluding all works of evocation of pit, pole erection, making plinth for poles 30 cm above , grouting in the ratio 1:4:8 (cement, sand, 40 mm brick ballast),back filling of earth ,proper ramming & fitting of all accessories (M.S. angle iron 65 x 65 x 6 mm bracing with clamps, top channel 125 x 65 x 3200 mm with clamps, danger board with clamp,barbed wire earthing, etc. complete as per RESSPO) . |
| 41 | Erection of Single pole structure on 11mtr ST. (SP-55) Pole including all works of evocation of pit, pole erection, making plinth for poles 30 cm above , grouting in the ratio 1:4:8 (cement, sand, 40mm brick ballast),back filling of earth ,proper ramming & fitting of all accessories for double circuit ( \"V\" type cross arm 100 x 50 x 6 mm, M.S. Channel (7.9 Kg./M) clamps with bolt and nut, composite polymer pin, insulator, danger board with clamp, Alluminium paint, red oxide paint, barbed wire earthing, etc. complete as per RESSPO. |
| 42 | Erection of Double pole structure on 11 mtr ST Pole including all works of evocation of pit, pole erection, making plinth for poles 30 cm above , grouting in the ratio 1:4:8 (cement, sand, 40 mm brick ballast),back filling of earth ,proper ramming & fitting of all accessories (M.S. angle iron 65 x 65 x 6 mm bracing with clamps, top channel 125 x 65 x 3200 mm with clamps, danger board with clamp, Alluminium paint, red oxide paint, barbed wire earthing, etc. complete as per RESSPO) . |
| 43 | Erection of four pole structure on 11 mtr ST Pole including all works of evocation of pit, pole erection, making plinth for poles 30 cm above , grouting in the ratio 1:4:8 (cement, sand, 40 mm brick ballast),back filling of earth ,proper ramming & fitting of all accessories (M.S. angle iron 65 x 65 x 6 mm bracing with clamps, top channel 125 x 65 x 3200 mm with clamps, danger board with clamp, Alluminium paint, red oxide paint, barbed wire earthing, etc. complete as per RESSPO) . |
| 44 | Laying, spreading, lifting and final sagging of 3 phases of ACSR Dog conductorin accordance with profile and sag chart including binding, Jumpering and fixing of P.G. Clamp as per requirement in 03 Nos. conductor in parallel. |
| 45 | Grouting of stay rods (20 x 1800) mm including all work of excavation, cement concrete in size (0.60 x 0.60 x 0.30) m in ratio 1:4:8 cement, sand, 40mm brick ballast) as per drg including back filling, proper ramming etc. Fixing tightening & nozzling of stay wire with stay rod with the poles of required tension as per drawing. |
| 46 | Painting of S.T Pole 11 mtr. Long with Alluminium paint and red oxide paint etc. |
| 47 | Chopping of branches of trees of eucalyptus, Neem, Keekar and other kind of trees along the route of the line and disposal of the same at suitable place. |
| 48 | Guarding between two poles like single poles, double poles, four poles, densearea etc. to guard LT, 11 KV Line telephone and river crossing, road crossing etc. with G.I. wire no. 6 SWG and G.I. wire no. 8 SWG, cutting, fabrication and fixing of guarding channel 75 x 40 x 3010 mm with clamps nut & bolts etc. as per drawing. |
| 49 | Work No. 02Part-A- Providing following materials by the Contractor. |
| 50 | 33KV ‘XLPE’ C/J Kit 3x300mm² Outdoor |
| 51 | 33KV ‘V’ Type Cross Arm 100x50x6mm, MS Channel ( 7.9 Kg/m) |
| 52 | 33 KV Polymer Pin Insulator |
| 53 | Number Plate |
| 54 | Danger Board with Clamp |
| 55 | Barbed wire |
| 56 | Bolts, Nuts, & Washers |
| 57 | X-armclamp with nut bolt for ST Pole 11 mtr with nut bolt by 50x8 mm MSflat Iron make |
| 58 | X-arm clamp with nut bolt for PCC Pole 9 mtr with nut bolt by 50x8 mm MSflat Iron make |
| 59 | Stay set with Clamp for ST Pole 11mtr. with Nut and Bolt by 50x8 mm MS Flat Iron make. |
| 60 | Stay set with Clamp for PCC Pole 9 mtrwith Nut and Bolt by 50x8 mm MS Flat Iron make. |
| 61 | Stay Rod 20x1800 mm |
| 62 | Stay wire 7/8 SWG |
| 63 | MS Earthing Rod 20x2500 mm |
| 64 | 33 KV Polymer Disc Insulator 70 KN B&S Type |
| 65 | Disc fitting 70 KNB&S Type for DOG |
| 66 | P.G. Clamp for DOG |
| 67 | ‘E’ Bracket for 33 KV |
| 68 | M.S. Angle Iron 65x65x6mm bracing with clamps |
| 69 | 33 KV. Top channel ( 125x65mmX3200 mm ( 10.7 Kg/m) with clamps |
| 70 | 33 KV Guarding angle |
| 71 | GI Wire 5 mm |
| 72 | 33 KV Guarding angle Clamp with nut bolt for ST Pole 11mtr. with Nut and Bolt by 50x8 mm MS Flat Iron make. |
| 73 | 33 KV Guarding angle Clamp with nut bolt for PCC Pole 9 mtr. with Nut and Bolt by 50x8 mm MS Flat Iron make. |
| 74 | F-bracket with nut bolt for ST Pole 11 mtr & PCC Pole 9 mtr with nut bolt by 50x8 mm MSflat Iron make |
| 75 | Part B Work Shifting,loading and carriageof following materials on private truck at store centre Maharajganj & Un-loading of the same with proper stacking at work site . |
| 76 | P.C.C.Pole9 M long |
| 77 | S.T. Pole – 11 Mtr. Long |
| 78 | 33 KV ‘XLPE’ Cable 3x300mm² |
| 79 | ACSR ‘Dog’ Conductor |
| 80 | Laying of 33 KV 3x300 mm² ‘XLPE’ cable of double circuit by digging pit & making trench in Proper size(1.2M depth x1M wide) below ground level by fixing bricks(4½?)on both side of trench wall and 9? brick work at the centre of the trench along the cable.Fixing brick slab on top after filling sand around both the cable including cost of bricks/ HDD Method by drillingmachine as per site requirement. |
| 81 | Laying of 33KV ‘XLPE’ cable in air after providing 6” dia. M.S pipe 3 m long Complete work.(Rs 1475/mtr) |
| 82 | Providing & Cable jointing charges of 33 KV XLPE Cable Outdoor. |
| 83 | GI PipeEarthing Complete forCable jointing Kit with materials |
| 84 | Fabrication of 13 M long S.T. pole by welding 3.0 M long 5\" dia M.S. pipe & Flat Iron 50x6 mm 12\" long by providing M.S. pipe and all other materials by the contractor and only S.T. poles 11 Mtr. Long will be provided by the department. |
| 85 | Erection of Single pole structure on 9 Mtr PCC Pole including all works of evocation of pit, pole erection, making plinth for poles 30 cm above , grouting in the ratio 1:4:8 (cement, sand, 40mm brick ballast),back filling of earth ,proper ramming & fitting of all accessories for double circuit ( \"V\" type cross arm 100 x 50 x 6 mm, M.S. Channel (7.9 Kg./M) clamps with bolt and nut, composite polymer pin insulator, danger board with clamp,barbed wire earthing, etc. complete as per RESSPO). |
| 86 | Extension of 9 mtr PCC Pole for proper clearence for existing lines by 33 KV Top channel with clamp with complete work as per proper specification. |
| 87 | Erection of Double pole structure on 9 Mtr PCC Poleincluding all works of evocation of pit, pole erection, making plinth for poles 30 cm above , grouting in the ratio 1:4:8 (cement, sand, 40 mm brick ballast),back filling of earth ,proper ramming & fitting of all accessories (M.S. angle iron 65 x 65 x 6 mm bracing with clamps, top channel 125 x 65 x 3200 mm with clamps, danger board with clamp,barbed wire earthing, etc. complete as per RESSPO) . |
| 88 | Erection of Four pole structure on 9 Mtr PCC Poleincluding all works of evocation of pit, pole erection, making plinth for poles 30 cm above , grouting in the ratio 1:4:8 (cement, sand, 40 mm brick ballast),back filling of earth ,proper ramming & fitting of all accessories (M.S. angle iron 65 x 65 x 6 mm bracing with clamps, top channel 125 x 65 x 3200 mm with clamps, danger board with clamp,barbed wire earthing, etc. complete as per RESSPO) . |
| 89 | Erection of Single pole structure on 11mtr ST. (SP-55) Pole including all works of evocation of pit, pole erection, making plinth for poles 30 cm above , grouting in the ratio 1:4:8 (cement, sand, 40mm brick ballast),back filling of earth ,proper ramming & fitting of all accessories for double circuit ( \"V\" type cross arm 100 x 50 x 6 mm, M.S. Channel (7.9 Kg./M) clamps with bolt and nut, composite polymer pin, insulator, danger board with clamp, Alluminium paint, red oxide paint, barbed wire earthing, etc. complete as per RESSPO. |
| 90 | Erection of Double pole structure on 11 mtr ST Pole including all works of evocation of pit, pole erection, making plinth for poles 30 cm above , grouting in the ratio 1:4:8 (cement, sand, 40 mm brick ballast),back filling of earth ,proper ramming & fitting of all accessories (M.S. angle iron 65 x 65 x 6 mm bracing with clamps, top channel 125 x 65 x 3200 mm with clamps, danger board with clamp, Alluminium paint, red oxide paint, barbed wire earthing, etc. complete as per RESSPO) . |
| 91 | Erection of four pole structure on 11 mtr ST Pole including all works of evocation of pit, pole erection, making plinth for poles 30 cm above , grouting in the ratio 1:4:8 (cement, sand, 40 mm brick ballast),back filling of earth ,proper ramming & fitting of all accessories (M.S. angle iron 65 x 65 x 6 mm bracing with clamps, top channel 125 x 65 x 3200 mm with clamps, danger board with clamp, Alluminium paint, red oxide paint, barbed wire earthing, etc. complete as per RESSPO) . |
| 92 | Laying, spreading, lifting and final sagging of 3 phases of ACSR Dog conductorin accordance with profile and sag chart including binding, Jumpering and fixing of P.G. Clamp as per requirement in 03 Nos. conductor in parallel. |
| 93 | Grouting of stay rods (20 x 1800) mm including all work of excavation, cement concrete in size (0.60 x 0.60 x 0.30) m in ratio 1:4:8 cement, sand, 40mm brick ballast) as per drg including back filling, proper ramming etc. Fixing tightening & nozzling of stay wire with stay rod with the poles of required tension as per drawing. |
| 94 | Painting of S.T Pole 11 mtr. Long with Alluminium paint and red oxide paint etc. |
| 95 | Chopping of branches of trees of eucalyptus, Neem, Keekar and other kind of trees along the route of the line and disposal of the same at suitable place. |
| 96 | Guarding between two poles like single poles, double poles, four poles, etc. to guard LT, 11 KV Line telephone and river crossing, road crossing etc. with G.I. wire no. 6 SWG and G.I. wire no. 8 SWG, cutting, fabrication and fixing of guarding channel 75 x 40 x 3010 mm with clamps nut & bolts etc. as per drawing. |
| 97 | Work No. 03Shifting & loading of following materials on private truck at store centre Maharajganj& carriage up to 33/11 KV Sub-Station Koluhi,Distt- Maharajganj & Un-loading of the same with proper stacking (Distance about0 to 55 km) |
| 98 | 11 KV ‘XLPE’ power cable. |
| 99 | 33 KV ‘VCB’ complete with all structure. |
| 100 | 33 KV. C.T. |
| 101 | 33 KV C.T.Structure |
| 102 | 33 KV Fuse Set |
| 103 | 33 Line Type Isolator |
| 104 | 33 Bus Type Isolator |
| 105 | 33 KV Post Insulator |
| 106 | Structure for Above |
| 107 | 33 KV Single T/F Control pannel |
| 108 | 33 KV lightening arrester |
| 109 | 33 KV LA Structure. |
| 110 | Repairing of plinth and foundation for 10 MVA transformer as per required specification. Dismantling of T/F all connection. |
| 111 | Dismentling of existing 2 no body and 1 no Neutral earthing safely of existing 5 MVA power transformer earthing for installation of new 10 MVA T/F and re-earthing of new 10 MVA T/F by old earth strip including providing required length of GI Earth strip .The earthing of 10 MVA T/F Included all work completed as per required specification of RESSPO norms. |
| 112 | Providing33 KV. Top channel for cable stand & neutral earthing |
| 113 | Dismentling of HT jumpers, 11 KV C/J kit and different earthing of 5 MVA T/F drain out T/F oil after closing valve and opening of radiator for shifting of existing 5 MVA T/F from plinth about 30 mtr. Distance & resetting of All accessories etc. complete work. |
| 114 | Digging of pit for taking out of old & used running condition 11 KV cable safely. |
| 115 | Grouting of M.S. channel 3.2 mtr long for cable stand and welding of M.S. flat at equal distance for fastening cable by clamp with nuts and bolts mounting of cable at cable stand and connection of jumpers. |
| 116 | Providing & Jointing charges of 11 KV “XLPE” C/J kit 3 x 300 mm2 Indoor/Outdoor type |
| 117 | Laying of 11 KV “XLPE” power cable 3 x 300/185 mm2including digging of pits of size 0.5 x 0.5 mtr. covering of cable with sand and 1st class brick around the cable. |
| 118 | Laying of 11KV ‘XLPE’ cable in air after providing 6” dia. M.S pipe 3 m long Complete work. |
| 119 | GI PipeEarthing Complete forCable jointing Kit with materials |
| 120 | Neutral earthing of 10 MVA T/F Complete including cost of GI Strip, GI Pipe 1.5\" dia and 30\" long and other earthing materials(Delta type). |
| 121 | Providing and Making connection of 24 Volt battery and battery charger with cabinet. |
| 122 | Jumpring from 33 KV Bus bar to post insulator, bus isolator, VCB, CT and LA to 10 MVA transformer etc.( Providing alluminium Lug and PG Clamp) |
| 123 | Installation of 33 KV control panel for “VCB” with complete earthing with installation of battery and battery charger in control room and making connection. |
| 124 | Erection,Installation and grouting of “VCB” Structure mounting and fitting of “VCB” on erected structure with complete earthing. |
| 125 | Erection,Installation and grouting of “CT” Structure mounting and fitting of “CT” on erected structure with complete earthing. |
| 126 | Erection,Installation and grounting of Fuse Set structure. mounting and fitting of Fuse Set on erected structure with complete earthing. |
| 127 | Erection,Installation and grounting of LA structure. mounting and fitting of LA on erected structure with complete earthing. |
| 128 | Mounting and fitting of equipment on erected structures. |
| 129 | 33 KV line isolator 400 Amp |
| 130 | 33 KV Bus – Isolator 400 Amp. |
| 131 | 33 KV Post Insulator |
| 132 | 33 KV LA |
| 133 | Painting of erected structure in switchyard (Applying on coat of good quality red oxide primer then two coat of good quality of high class luxol aluminium paint) |
| 134 | Providing following control cable and its laying from switchyard to control room 33 KV panel by digging trench in switchyard including cost of sand and 1st class bricks with covering and making connection complete and including cost of laying. |
| 135 | Size 2 x 2.5 mm2 |
| 136 | Size 4 x 2.5 mm2 |
| 137 | Dismantling of existing pale fencing and resetting after completion of transformer work. |
| 138 | Carriage of old and used 11 KV ‘XLPE’ power cable from 33/11 KV Sub-Station Koluhi,Distt-Maharajganjto store center Maharajganj |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender