Tender For Providing, Installation, Testing And Commissioning Of Electro-Mechanical Machinery Alongwith Allied Works At Wss Channi Mansar, udhampur-Jammu And Kashmir

Public Health Engineering Department-PHED has published Tender For Providing, Installation, Testing And Commissioning Of Electro-Mechanical Machinery Alongwith Allied Works At Wss Channi Mansar. Submission Date for this Tender is 29-09-2023. Electromechanical Machinery Tenders in udhampur Jammu And Kashmir. Bidders can get complete Tender details and download the document.




Tender Notice

39633801
Corrigendum : Tender For Providing, Installation, Testing And Commissioning Of Electro-Mechanical Machinery Alongwith Allied Works At Wss Channi Mansar
Open Tender
Indian
Jammu And Kashmir
udhampur
29-09-2023

Tender Details

Providing, Installation, Testing And Commissioning Of Electro-Mechanical Machinery Alongwith Allied Works At Wss Channi Mansar- 1 STAGE-0 MAJALTA TO KAKRAI 2 Providing, installation, testing and commissioning of 5000 GPH x 300 meter head HC pump set withsuitable rating prime mover in compliance with the technical conditions andallied works by way of surveying of site, designing of pump machinery and prime mover in conformity with site conditions. Laying of M-20 grade RCC foundation block for each pump of size 6’x3’x4’ by using reinforcement steel of 10mm dia. The foundation block as per size of pump set should have additional margin of 6” on all sides. The foundation block may be combined for all the pumps which must includes space on all sides of pump set and space between the pump sets. Providing, fabrication and laying of 80mm dia MS suction pipe line to the pump set of length as per site conditions condition and upto maximum of approximately 6 meters each including 80mm dia MS bends, MS flanges, expanders/reducers / dismantling joints / saddles/ pipe extension pieces, 80mm dia Cast Iron sluice valve-1no.,gaskets, nuts, bolts, washers as per site requirement.Providing, fabrication and laying of 80mm dia MS delivery pipe as per site conditions including MS bends, MS flange, expanders/reducers / dismantling joints/ saddles/ pipe extension pieces, Cast steel Sluice valve 80mm dia and NRV 80mm dia alongwith by pass arrangement (class 300 accompanied with manufacturer’s in house test certificate)gaskets, nuts, bolts, washers. Job includes greasing work, P/F of graphited gland packing and thereafter testing on no load and then on full load and commissioning thereof. Job includes providing / fitting and laying of copper cable 35mm2from motor to panelin six leads approximately 36 meters for each motor, then p/f and laying 50mm2 copper cable upto MCCB-bus bar-voltage stabilizerin three leads approximately 30 meters in length alongwith neutral wire conforming to ISI standards with proper thimbling and insulation material. Job covers providing and fitting of 250 ampere MCCB of 50KA breaking strength. Proper chemical earthing of the equipment should be done for safety of machinery. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handing equipments etc. 3 Making connection of delivery lines with rising main through 100mm dia MS pipe manifold. Job includes providing and fitting of bus bar arrangement complete with frame and insulation work on the wall of the pump room.Job includes providing, laying and fixing of insulation rubber mats around electro mechanical machinery on the floor of the pump house Job includes providing and fitting of overhead MS girder of required size so as to sustain the load of material / equipment / machinery while lifting / shifting of the material / equipments / machinery alongwith chain pulley block (1no.) 3 ton. Job includes providing of maintenance tool kit as per enclosed annexure. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handling equipment etc. 4 Design, fabrication, installation, testing and commissioning of 110 ampere rating, 3 phase, LT control panel cum protection panel cum automatic star delta starter alongwith allied works by way of fabrication of panel with 3 pole Main and delta power contactors of 110A rating 01 no. each and star power contactor of 70A rating-1no., complete with all protection, safety and control devices / mechanismcompatible with the design / rating of the prime mover, of reputed make, conforming to ISI standards. The system should be provided with fault analyzer cum controller unit or equivalent of standard and reputed make. The complete system should be enclosed in MS steel enclosure box of suitable dimensions. The enclosure should be finished with powder coated painting from inside as well as from outer surface of approved colour. Providing / laying of copper conductors of proper rating alongwith insulation material as per site requirement. The enclosure should be front shutter mounted with key locking system having glass window. Digital electronic voltmeter & ampere meter should be provided along with the required current transformer and selector switches. The internal control wiring should be done with flexible PVC LT cable with proper thimbling at each end. The system should trip the motor on power failure and on appearance of an electrical fault mentioned below which may otherwise damage the motor field coils and should not restart automatically until unless the system is reset manually, thus providing automation to the system and protection to the motor .The system / star delta auto starter should not fall into delta if it does not fall into star mode first and should remain de-energised to avoid damage to the motor / machinery and also to the power source / transformer. The system / star delta auto starter should trip off if it does not fall into delta & remains in star mode for more than 10-20 seconds. The system shall provide protection against:-Low voltage below 350 V, High Voltage above 450 V, Single phasing, Reverse phasing, Un Balanced phasing, Dry running, Overloading.In addition the system should have the following audio & visual features for a quick and accurate diagnosis of the appeared fault / status for a speedy rectification of the system-- Separate LED fault / status indicators, LED phase indicators. Isolation by pass system, for fault analysis of system, with a blinking indicator. An audio warning system/Siren which activates only on starter failure to trip the motor on appearance of any electrical fault mentioned above, to warn the operator to switch off the motor manually.3 LED, contactor ‘COIL OK’, indicators, one for each of the contactors / coils. LED star & delta indicators to access the star to delta timing. A tamper proof starting system to avoid manipulations by the motor operator to keep the system in a permanently ON position Testing of panel after making all incoming / outgoing connections on no load and then on full load. Proper chemical earthing of equipment should be done. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc, 5 Providing, carriage, installation, testing and commissioning of 3 phase, 100 KVA voltage stabilizer copper wound, first quality CRGO silicon steel core, naturally- oil cooled, manually operated, 14 gaugecontainer chamber alongwith allied works. Job includes providing of 100 KVA voltage stabilizer complete with mineral insulating oil, MCCB, change over switch complete with safety and protection devices etc. Job includes providing and fitting of single core armoured Al. cable of 150mm2 from electric pole to main switch in four leads approximately 50 meters length of each lead and further Providing and fitting of 50mm2 copper cable from main switch to voltage stabilizer approximately 20 meters in length complete with insulation and thimbling.The voltage stabilizer should have 5 upwards steps and 2 downwards steps (or as per the specified voltage range) from the line voltage i.e. it should work from 180V to 400+5%. Proper chemical earthing of the equipment shall be done. Complete Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc. 6 STAGE-KAKRAI MAHAMAYA MANDIR 7 Providing, installation, testing and commissioning of 5000 GPH x 175 meter head HC pump set withsuitable rating prime mover in compliance with the technical conditions andallied works by way of surveying of site, designing of pump machinery and prime mover in conformity with site conditions. Laying of M-20 grade RCC foundation block for each pump of size 6’x3’x4’ by using reinforcement steel of 10mm dia. The foundation block as per size of pump set should have additional margin of 6” on all sides. The foundation block may be combined for all the pumps which must includes space on all sides of pump set and space between the pump sets. Providing, fabrication and laying of 80mm dia MS suction pipe line to the pump set of length as per site conditions condition and upto maximum of approximately 6 meters each including 80mm dia MS bends, MS flanges, expanders/reducers / dismantling joints / saddles/ pipe extension pieces, 80mm dia Cast Iron sluice valve-1no.,gaskets, nuts, bolts, washers as per site requirement.Providing, fabrication and laying of 80 dia MS delivery pipe as per site conditions including MS bends, MS flange, expanders/reducers / dismantling joints/ saddles/ pipe extension pieces, Cast steel Sluice valve 80mm dia and NRV 80mm alongwith by pass arrangement (class 300 accompanied with manufacturer’s in house test certificate)gaskets, nuts, bolts, washers. Job includes greasing work, P/F of graphited gland packing and thereafter testing on no load and then on full load and commissioning thereof. Job includes providing / fitting and laying of copper cable 16mm2from motor to panelin six leads approximately 36 meters for each motor, then p/f and laying 25mm2 copper cable upto MCCB-bus bar-voltage stabilizerin three leads approximately 30 meters in length alongwith neutral wire conforming to ISI standards with proper thimbling and insulation material. Job covers providing and fitting of 100 ampere MCCB of 50KA breaking strength. Proper chemical earthing of the equipment should be done for safety of machinery. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handing equipments etc. 8 Making connection of delivery lines with rising main through 100 mm dia MS pipe manifold. Job includes providing and fitting of bus bar arrangement complete with frame and insulation work on the wall of the pump room. Job includes providing, laying and fixing of insulation rubber mats around electro mechanical machinery on the floor of the pump house Job includes providing and fitting of overhead MS girder of required size so as to sustain the load of material / equipment / machinery while lifting / shifting of the material / equipments / machinery alongwith chain pulley block (1no.) 3 ton. Job includes providing of maintenance tool kit as per enclosed annexure. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handling equipment etc. 9 Design, fabrication, installation, testing and commissioning of 70 ampere rating, 3 phase, LT control panel cum protection panel cum automatic star delta starter alongwith allied works by way of fabrication of panel with 3 pole Main and delta power contactors of 70A rating 01 no. each and star power contactor 50 rating-1no., complete with all protection, safety and control devices / mechanism compatible with the design / rating of the prime mover, of reputed make, conforming to ISI standards. The system should be provided with fault analyzer cum controller unit or equivalent of standard and reputed make. The complete system should be enclosed in MS steel enclosure box of suitable dimensions. The enclosure should be finished with powder coated painting from inside as well as from outer surface of approved colour. Providing / laying of copper conductors of proper rating alongwith insulation material as per site requirement. The enclosure should be front shutter mounted with key locking system having glass window. Digital electronic voltmeter & ampere meter should be provided along with the required current transformer and selector switches. The internal control wiring should be done with flexible PVC LT cable with proper thimbling at each end. The system should trip the motor on power failure and on appearance of an electrical fault mentioned below which may otherwise damage the motor field coils and should not restart automatically until unless the system is reset manually, thus providing automation to the system and protection to the motor .The system / star delta auto starter should not fall into delta if it does not fall into star mode first and should remain de-energised to avoid damage to the motor / machinery and also to the power source / transformer. The system / star delta auto starter should trip off if it does not fall into delta & remains in star mode for more than 10-20 seconds. The system shall provide protection against:-Low voltage below 350 V, High Voltage above 450 V, Single phasing, Reverse phasing, Un Balanced phasing, Dry running, Overloading.In addition the system should have the following audio & visual features for a quick and accurate diagnosis of the appeared fault / status for a speedy rectification of the system-- Separate LED fault / status indicators, LED phase indicators. Isolation by pass system, for fault analysis of system, with a blinking indicator. An audio warning system/Siren which activates only on starter failure to trip the motor on appearance of any electrical fault mentioned above, to warn the operator to switch off the motor manually.3 LED, contactor ‘COIL OK’, indicators, one for each of the contactors / coils. LED star & delta indicators to access the star to delta timing. A tamper proof starting system to avoid manipulations by the motor operator to keep the system in a permanently ON position Testing of panel after making all incoming / outgoing connections on no load and then on full load. Proper chemical earthing of equipment should be done. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc, 10 Providing, carriage, installation, testing and commissioning of 3 phase, 63 KVA voltage stabilizer copper wound, first quality CRGO silicon steel core, naturally- oil cooled, manually operated, 14 gaugecontainer chamber alongwith allied works. Job includes providing of 63 KVA voltage stabilizer complete with mineral insulating oil, MCCB, change over switch complete with safety and protection devices etc. Job includes providing and fitting of single core armoured Al. cable of 70mm2 from electric pole to main switch in four leads approximately 50 meters length of each lead and further Providing and fitting of 25mm2 copper cable from main switch to voltage stabilizer approximately 20 meters in length complete with insulation and thimbling. The voltage stabilizer should have 5 upwards steps and 2 downwards steps (or as per the specified voltage range) from the line voltage i.e. it should work from 180V to 400+5%. Proper chemical earthing of the equipment shall be done. Complete Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc. 11 STAGE-0 KAKRAI TO CHADWA 12 Providing, installation, testing and commissioning of 4000 GPH x 150 meter head HC pump set withsuitable rating prime mover in compliance with the technical conditions andallied works by way of surveying of site, designing of pump machinery and prime mover in conformity with site conditions. Laying of M-20 grade RCC foundation block for each pump of size 6’x3’x4’ by using reinforcement steel of 10mm dia. The foundation block as per size of pump set should have additional margin of 6” on all sides. The foundation block may be combined for all the pumps which must includes space on all sides of pump set and space between the pump sets. Providing, fabrication and laying of 80mm dia MS suction pipe line to the pump set of length as per site conditions condition and upto maximum of approximately 6 meters each including 80mm dia MS bends, MS flanges, expanders/reducers / dismantling joints / saddles/ pipe extension pieces, 80mm dia Cast Iron sluice valve-1no.,gaskets, nuts, bolts, washers as per site requirement.Providing, fabrication and laying of 80mm dia MS delivery pipe as per site conditions including MS bends, MS flange, expanders/reducers / dismantling joints/ saddles/ pipe extension pieces, Cast steel Sluice valve 80mm dia and NRV 80mm alongwith by pass arrangement (class 300 accompanied with manufacturer’s in house test certificate)gaskets, nuts, bolts, washers. Job includes greasing work, P/F of graphited gland packing and thereafter testing on no load and then on full load and commissioning thereof. Job includes providing / fitting and laying of copper cable 25mm2from motor to panelin six leads approximately 36 meters for each motor, then p/f and laying 35mm2 copper cable upto MCCB-bus bar-voltage stabilizerin three leads approximately 30 meters in length alongwith neutral wire conforming to ISI standards with proper thimbling and insulation material. Job covers providing and fitting of 100 ampere MCCB of 50KA breaking strength. Proper chemical earthing of the equipment should be done for safety of machinery. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handing equipments etc. 13 Making connection of delivery lines with rising main through 100mm dia MS pipe manifold. Job includes providing and fitting of bus bar arrangement complete with frame and insulation work on the wall of the pump room. Job includes providing, laying and fixing of insulation rubber mats around electro mechanical machinery on the floor of the pump house Job includes providing and fitting of overhead MS girder of required size so as to sustain the load of material / equipment / machinery while lifting / shifting of the material / equipments / machinery alongwith chain pulley block (1no.) 3 ton. Job includes providing of maintenance tool kit as per enclosed annexure. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handling equipment etc. 14 Design, fabrication, installation, testing and commissioning of 70 ampere rating, 3 phase, LT control panel cum protection panel cum automatic star delta starter alongwith allied works by way of fabrication of panel with 3 pole Main and delta power contactors of 70A rating 01 no. each and star power contactor of 50A rating-1no., complete with all protection, safety and control devices / mechanismcompatible with the design / rating of the prime mover, of reputed make, conforming to ISI standards. The system should be provided with fault analyzer cum controller unit or equivalent of standard and reputed make. The complete system should be enclosed in MS steel enclosure box of suitable dimensions. The enclosure should be finished with powder coated painting from inside as well as from outer surface of approved colour. Providing / laying of copper conductors of proper rating alongwith insulation material as per site requirement. The enclosure should be front shutter mounted with key locking system having glass window. Digital electronic voltmeter & ampere meter should be provided along with the required current transformer and selector switches. The internal control wiring should be done with flexible PVC LT cable with proper thimbling at each end. The system should trip the motor on power failure and on appearance of an electrical fault mentioned below which may otherwise damage the motor field coils and should not restart automatically until unless the system is reset manually, thus providing automation to the system and protection to the motor .The system / star delta auto starter should not fall into delta if it does not fall into star mode first and should remain de-energised to avoid damage to the motor / machinery and also to the power source / transformer. The system / star delta auto starter should trip off if it does not fall into delta & remains in star mode for more than 10-20 seconds. The system shall provide protection against:-Low voltage below 350 V, High Voltage above 450 V, Single phasing, Reverse phasing, Un Balanced phasing, Dry running, Overloading.In addition the system should have the following audio & visual features for a quick and accurate diagnosis of the appeared fault / status for a speedy rectification of the system-- Separate LED fault / status indicators, LED phase indicators. Isolation by pass system, for fault analysis of system, with a blinking indicator. An audio warning system/Siren which activates only on starter failure to trip the motor on appearance of any electrical fault mentioned above, to warn the operator to switch off the motor manually.3 LED, contactor ‘COIL OK’, indicators, one for each of the contactors / coils. LED star & delta indicators to access the star to delta timing. A tamper proof starting system to avoid manipulations by the motor operator to keep the system in a permanently ON position Testing of panel after making all incoming / outgoing connections on no load and then on full load. Proper chemical earthing of equipment should be done. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc, 15 Providing, carriage, installation, testing and commissioning of 3 phase, 63 KVA voltage stabilizer copper wound, first quality CRGO silicon steel core, naturally- oil cooled, manually operated, 14 gaugecontainer chamber alongwith allied works. Job includes providing of 63 KVA voltage stabilizer complete with mineral insulating oil, MCCB, change over switch complete with safety and protection devices etc. Job includes providing and fitting of single core armoured Al. cable of 70mm2 from electric pole to main switch in four leads approximately 50 meters length of each lead and further Providing and fitting of 35mm2 copper cable from main switch to voltage stabilizer approximately 20 meters in length complete with insulation and thimbling. The voltage stabilizer should have 5 upwards steps and 2 downwards steps (or as per the specified voltage range) from the line voltage i.e. it should work from 180V to 400+5%. Proper chemical earthing of the equipment shall be done. Complete Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc. 16 PUMP ROOM MANSAR TO MOHDIAN 17 Providing, installation, testing and commissioning of 2000 GPH x 85 meter head HC pump set withsuitable rating prime mover in compliance with the technical conditions andallied works by way of surveying of site, designing of pump machinery and prime mover in conformity with site conditions. Laying of M-20 grade RCC foundation block for each pump of size 6’x3’x4’ by using reinforcement steel of 10mm dia. The foundation block as per size of pump set should have additional margin of 6” on all sides. The foundation block may be combined for all the pumps which must includes space on all sides of pump set and space between the pump sets. Providing, fabrication and laying of 65mm dia MS suction pipe line to the pump set of length as per site conditions condition and upto maximum of approximately 6 meters each including 65mm dia MS bends, MS flanges, expanders/reducers / dismantling joints / saddles/ pipe extension pieces, 65mm dia Cast Iron sluice valve-1no.,gaskets, nuts, bolts, washers as per site requirement.Providing, fabrication and laying of 65mm dia MS delivery pipe as per site conditions including MS bends, MS flange, expanders/reducers / dismantling joints/ saddles/ pipe extension pieces, Cast steel Sluice valve 65mm dia and NRV 65mm alongwith by pass arrangement (class 150 accompanied with manufacturer’s in house test certificate)gaskets, nuts, bolts, washers. Job includes greasing work, P/F of graphited gland packing and thereafter testing on no load and then on full load and commissioning thereof. Job includes providing / fitting and laying of copper cable 10mm2from motor to panelin six leads approximately 36 meters for each motor, then p/f and laying 16mm2 copper cable upto MCCB-bus bar-voltage stabilizerin three leads approximately 30 meters in length alongwith neutral wire conforming to ISI standards with proper thimbling and insulation material. Job covers providing and fitting of 63 ampere MCCB of 50KA breaking strength. Proper chemical earthing of the equipment should be done for safety of machinery. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handing equipments etc. 18 Making connection of delivery lines with rising main through 80 mm dia MS pipe manifold. Job includes providing and fitting of bus bar arrangement complete with frame and insulation work on the wall of the pump room. Job includes providing, laying and fixing of insulation rubber mats around electro mechanical machinery on the floor of the pump house Job includes providing and fitting of overhead MS girder of required size so as to sustain the load of material / equipment / machinery while lifting / shifting of the material / equipments / machinery alongwith chain pulley block (1no.) 3 ton. Job includes providing of maintenance tool kit as per enclosed annexure. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handling equipment etc. 19 Design, fabrication, installation, testing and commissioning of 50 ampere rating, 3 phase, LT control panel cum protection panel cum automatic star delta starter alongwith allied works by way of fabrication of panel with 3 pole Main and delta power contactors of 50A rating 01 no. each and star power contactor 50 rating-1no., complete with all protection, safety and control devices / mechanism compatible with the design / rating of the prime mover, of reputed make, conforming to ISI standards. The system should be provided with fault analyzer cum controller unit or equivalent of standard and reputed make. The complete system should be enclosed in MS steel enclosure box of suitable dimensions. The enclosure should be finished with powder coated painting from inside as well as from outer surface of approved colour. Providing / laying of copper conductors of proper rating alongwith insulation material as per site requirement. The enclosure should be front shutter mounted with key locking system having glass window. Digital electronic voltmeter & ampere meter should be provided along with the required current transformer and selector switches. The internal control wiring should be done with flexible PVC LT cable with proper thimbling at each end. The system should trip the motor on power failure and on appearance of an electrical fault mentioned below which may otherwise damage the motor field coils and should not restart automatically until unless the system is reset manually, thus providing automation to the system and protection to the motor .The system / star delta auto starter should not fall into delta if it does not fall into star mode first and should remain de-energised to avoid damage to the motor / machinery and also to the power source / transformer. The system / star delta auto starter should trip off if it does not fall into delta & remains in star mode for more than 10-20 seconds. The system shall provide protection against:-Low voltage below 350 V, High Voltage above 450 V, Single phasing, Reverse phasing, Un Balanced phasing, Dry running, Overloading.In addition the system should have the following audio & visual features for a quick and accurate diagnosis of the appeared fault / status for a speedy rectification of the system-- Separate LED fault / status indicators, LED phase indicators. Isolation by pass system, for fault analysis of system, with a blinking indicator. An audio warning system/Siren which activates only on starter failure to trip the motor on appearance of any electrical fault mentioned above, to warn the operator to switch off the motor manually.3 LED, contactor ‘COIL OK’, indicators, one for each of the contactors / coils. LED star & delta indicators to access the star to delta timing. A tamper proof starting system to avoid manipulations by the motor operator to keep the system in a permanently ON position Testing of panel after making all incoming / outgoing connections on no load and then on full load. Proper chemical earthing of equipment should be done. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc, 20 Providing, carriage, installation, testing and commissioning of 3 phase, 63 KVA voltage stabilizer copper wound, first quality CRGO silicon steel core, naturally- oil cooled, manually operated, 14 gaugecontainer chamber alongwith allied works. Job includes providing of 63 KVA voltage stabilizer complete with mineral insulating oil, MCCB, change over switch complete with safety and protection devices etc. Job includes providing and fitting of single core armoured Al. cable of 70mm2 from electric pole to main switch in four leads approximately 50 meters length of each lead and further Providing and fitting of 25mm2 copper cable from main switch to voltage stabilizer approximately 20 meters in length complete with insulation and thimbling. The voltage stabilizer should have 5 upwards steps and 2 downwards steps (or as per the specified voltage range) from the line voltage i.e. it should work from 180V to 400+5%. Proper chemical earthing of the equipment shall be done. Complete Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc. 21 PUMP ROOM MANSAR TO KATTAL 22 Providing, installation, testing and commissioning of 3000 GPH x 200 meter head HC pump set withsuitable rating prime mover in compliance with the technical conditions andallied works by way of surveying of site, designing of pump machinery and prime mover in conformity with site conditions. Laying of M-20 grade RCC foundation block for each pump of size 6’x3’x4’ by using reinforcement steel of 10mm dia. The foundation block as per size of pump set should have additional margin of 6” on all sides. The foundation block may be combined for all the pumps which must includes space on all sides of pump set and space between the pump sets. Providing, fabrication and laying of 65mm dia MS suction pipe line to the pump set of length as per site conditions condition and upto maximum of approximately 6 meters each including 65mm dia MS bends, MS flanges, expanders/reducers / dismantling joints / saddles/ pipe extension pieces, 65mm dia Cast Iron sluice valve-1no.,gaskets, nuts, bolts, washers as per site requirement.Providing, fabrication and laying of 65mm dia MS delivery pipe as per site conditions including MS bends, MS flange, expanders/reducers / dismantling joints/ saddles/ pipe extension pieces, Cast steel Sluice valve 65mm dia and NRV 65mm alongwith by pass arrangement (class 300 accompanied with manufacturer’s in house test certificate)gaskets, nuts, bolts, washers. Job includes greasing work, P/F of graphited gland packing and thereafter testing on no load and then on full load and commissioning thereof. Job includes providing / fitting and laying of copper cable 16mm2from motor to panelin six leads approximately 36 meters for each motor, then p/f and laying 25mm2 copper cable upto MCCB-bus bar-voltage stabilizerin three leads approximately 30 meters in length alongwith neutral wire conforming to ISI standards with proper thimbling and insulation material. Job covers providing and fitting of 63 ampere MCCB of 50KA breaking strength. Proper chemical earthing of the equipment should be done for safety of machinery. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handing equipments etc. 23 Making connection of delivery lines with rising main through 80 mm dia MS pipe manifold. Job includes providing and fitting of bus bar arrangement complete with frame and insulation work on the wall of the pump room. Job includes providing, laying and fixing of insulation rubber mats around electro mechanical machinery on the floor of the pump house Job includes providing and fitting of overhead MS girder of required size so as to sustain the load of material / equipment / machinery while lifting / shifting of the material / equipments / machinery alongwith chain pulley block (1no.) 3 ton. Job includes providing of maintenance tool kit as per enclosed annexure. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handling equipment etc. 24 Design, fabrication, installation, testing and commissioning of 70 ampere rating, 3 phase, LT control panel cum protection panel cum automatic star delta starter alongwith allied works by way of fabrication of panel with 3 pole Main and delta power contactors of 70A rating 01 no. each and star power contactor 50 rating-1no., complete with all protection, safety and control devices / mechanism compatible with the design / rating of the prime mover, of reputed make, conforming to ISI standards. The system should be provided with fault analyzer cum controller unit or equivalent of standard and reputed make. The complete system should be enclosed in MS steel enclosure box of suitable dimensions. The enclosure should be finished with powder coated painting from inside as well as from outer surface of approved colour. Providing / laying of copper conductors of proper rating alongwith insulation material as per site requirement. The enclosure should be front shutter mounted with key locking system having glass window. Digital electronic voltmeter & ampere meter should be provided along with the required current transformer and selector switches. The internal control wiring should be done with flexible PVC LT cable with proper thimbling at each end. The system should trip the motor on power failure and on appearance of an electrical fault mentioned below which may otherwise damage the motor field coils and should not restart automatically until unless the system is reset manually, thus providing automation to the system and protection to the motor .The system / star delta auto starter should not fall into delta if it does not fall into star mode first and should remain de-energised to avoid damage to the motor / machinery and also to the power source / transformer. The system / star delta auto starter should trip off if it does not fall into delta & remains in star mode for more than 10-20 seconds. The system shall provide protection against:-Low voltage below 350 V, High Voltage above 450 V, Single phasing, Reverse phasing, Un Balanced phasing, Dry running, Overloading.In addition the system should have the following audio & visual features for a quick and accurate diagnosis of the appeared fault / status for a speedy rectification of the system-- Separate LED fault / status indicators, LED phase indicators. Isolation by pass system, for fault analysis of system, with a blinking indicator. An audio warning system/Siren which activates only on starter failure to trip the motor on appearance of any electrical fault mentioned above, to warn the operator to switch off the motor manually.3 LED, contactor ‘COIL OK’, indicators, one for each of the contactors / coils. LED star & delta indicators to access the star to delta timing. A tamper proof starting system to avoid manipulations by the motor operator to keep the system in a permanently ON position Testing of panel after making all incoming / outgoing connections on no load and then on full load. Proper chemical earthing of equipment should be done. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc, 25 Providing, carriage, installation, testing and commissioning of 3 phase, 63 KVA voltage stabilizer copper wound, first quality CRGO silicon steel core, naturally- oil cooled, manually operated, 14 gaugecontainer chamber alongwith allied works. Job includes providing of 63 KVA voltage stabilizer complete with mineral insulating oil, MCCB, change over switch complete with safety and protection devices etc. Job includes providing and fitting of single core armoured Al. cable of 70mm2 from electric pole to main switch in four leads approximately 50 meters length of each lead and further Providing and fitting of 25mm2 copper cable from main switch to voltage stabilizer approximately 20 meters in length complete with insulation and thimbling. The voltage stabilizer should have 5 upwards steps and 2 downwards steps (or as per the specified voltage range) from the line voltage i.e. it should work from 180V to 400+5%. Proper chemical earthing of the equipment shall be done. Complete Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc. 26 PUMP ROOM SARAL CHOWA TO CHANED 27 Providing, installation, testing and commissioning of 2000 GPH x 90 meter head HC pump set withsuitable rating prime mover in compliance with the technical conditions andallied works by way of surveying of site, designing of pump machinery and prime mover in conformity with site conditions. Laying of M-20 grade RCC foundation block for each pump of size 6’x3’x4’ by using reinforcement steel of 10mm dia. The foundation block as per size of pump set should have additional margin of 6” on all sides. The foundation block may be combined for all the pumps which must includes space on all sides of pump set and space between the pump sets. Providing, fabrication and laying of 65mm dia MS suction pipe line to the pump set of length as per site conditions condition and upto maximum of approximately 6 meters each including 65mm dia MS bends, MS flanges, expanders/reducers / dismantling joints / saddles/ pipe extension pieces, 65mm dia Cast Iron sluice valve-1no.,gaskets, nuts, bolts, washers as per site requirement.Providing, fabrication and laying of 65mm dia MS delivery pipe as per site conditions including MS bends, MS flange, expanders/reducers / dismantling joints/ saddles/ pipe extension pieces, Cast steel Sluice valve 65mm dia and NRV 65mm alongwith by pass arrangement (class 150 accompanied with manufacturer’s in house test certificate) gaskets, nuts, bolts, washers. Job includes greasing work, P/F of graphited gland packing and thereafter testing on no load and then on full load and commissioning thereof. Job includes providing / fitting and laying of copper cable 10mm2from motor to panelin six leads approximately 36 meters for each motor, then p/f and laying 16mm2 copper cable upto MCCB-bus bar-voltage stabilizerin three leads approximately 30 meters in length alongwith neutral wire conforming to ISI standards with proper thimbling and insulation material. Job covers providing and fitting of 63 ampere MCCB of 50KA breaking strength. Proper chemical earthing of the equipment should be done for safety of machinery. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handing equipments etc. 28 Making connection of delivery lines with rising main through 80 mm dia MS pipe manifold. Job includes providing and fitting of bus bar arrangement complete with frame and insulation work on the wall of the pump room. Job includes providing, laying and fixing of insulation rubber mats around electro mechanical machinery on the floor of the pump house Job includes providing and fitting of overhead MS girder of required size so as to sustain the load of material / equipment / machinery while lifting / shifting of the material / equipments / machinery alongwith chain pulley block (1no.) 3 ton. Job includes providing of maintenance tool kit as per enclosed annexure. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handling equipment etc. 29 Design, fabrication, installation, testing and commissioning of 50 ampere rating, 3 phase, LT control panel cum protection panel cum automatic star delta starter alongwith allied works by way of fabrication of panel with 3 pole Main and delta power contactors of 50 A rating 01 no. each and star power contactor 50 rating-1no., complete with all protection, safety and control devices / mechanism compatible with the design / rating of the prime mover, of reputed make, conforming to ISI standards. The system should be provided with fault analyzer cum controller unit or equivalent of standard and reputed make. The complete system should be enclosed in MS steel enclosure box of suitable dimensions. The enclosure should be finished with powder coated painting from inside as well as from outer surface of approved colour. Providing / laying of copper conductors of proper rating alongwith insulation material as per site requirement. The enclosure should be front shutter mounted with key locking system having glass window. Digital electronic voltmeter & ampere meter should be provided along with the required current transformer and selector switches. The internal control wiring should be done with flexible PVC LT cable with proper thimbling at each end. The system should trip the motor on power failure and on appearance of an electrical fault mentioned below which may otherwise damage the motor field coils and should not restart automatically until unless the system is reset manually, thus providing automation to the system and protection to the motor .The system / star delta auto starter should not fall into delta if it does not fall into star mode first and should remain de-energised to avoid damage to the motor / machinery and also to the power source / transformer. The system / star delta auto starter should trip off if it does not fall into delta & remains in star mode for more than 10-20 seconds. The system shall provide protection against:-Low voltage below 350 V, High Voltage above 450 V, Single phasing, Reverse phasing, Un Balanced phasing, Dry running, Overloading.In addition the system should have the following audio & visual features for a quick and accurate diagnosis of the appeared fault / status for a speedy rectification of the system-- Separate LED fault / status indicators, LED phase indicators. Isolation by pass system, for fault analysis of system, with a blinking indicator. An audio warning system/Siren which activates only on starter failure to trip the motor on appearance of any electrical fault mentioned above, to warn the operator to switch off the motor manually.3 LED, contactor ‘COIL OK’, indicators, one for each of the contactors / coils. LED star & delta indicators to access the star to delta timing. A tamper proof starting system to avoid manipulations by the motor operator to keep the system in a permanently ON position Testing of panel after making all incoming / outgoing connections on no load and then on full load. Proper chemical earthing of equipment should be done. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc, 30 Providing, carriage, installation, testing and commissioning of 3 phase, 63 KVA voltage stabilizer copper wound, first quality CRGO silicon steel core, naturally- oil cooled, manually operated, 14 gaugecontainer chamber alongwith allied works. Job includes providing of 63 KVA voltage stabilizer complete with mineral insulating oil, MCCB, change over switch complete with safety and protection devices etc. Job includes providing and fitting of single core armoured Al. cable of 50mm2 from electric pole to main switch in four leads approximately 50 meters length of each lead and further Providing and fitting of 16mm2 copper cable from main switch to voltage stabilizer approximately 20 meters in length complete with insulation and thimbling. The voltage stabilizer should have 5 upwards steps and 2 downwards steps (or as per the specified voltage range) from the line voltage i.e. it should work from 180V to 400+5%. Proper chemical earthing of the equipment shall be done. Complete Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc. 31 RETROFITTING 32 Providing, installation, testing and commissioning of 20000 GPH x 10-13 meter head mono submersible pump set,4mm2 flat submersible copper cable 3 core approximately 90 meters in length , 10 HP MUG starter alongwith fabrication and fitting of MS pipe, flanges etc. including allied works at pumping station Mansar. Complete Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles and material handling equipment etc. 33 Providing, installation, testing and commissioning of 6000 GPH x 10-13 meter head mono submersible pump set,2.5mm2 flat submersible copper cable 3 core approximately 90 meters in length , 7.5 HP MUG starter alongwith fabrication and fitting of MS pipe, flanges etc. including allied works at pumping station Badigarh. Complete Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles and material handling equipment etc. 34 Providing, installation, testing and commissioning of 20000 GPH x 90 meter head HC pump set withsuitable rating prime mover in compliance with the technical conditions andallied works by way of surveying of site, designing of pump machinery and prime mover in conformity with site conditions. Laying of M-20 grade RCC foundation block for each pump of size 6’x3’x4’ by using reinforcement steel of 10mm dia. The foundation block as per size of pump set should have additional margin of 6” on all sides. The foundation block may be combined for all the pumps which must includes space on all sides of pump set and space between the pump sets. Providing, fabrication and laying of 150mm dia MS suction pipe line to the pump set of length as per site conditions condition and upto maximum of approximately 6 meters each including 150mm dia MS bends, MS flanges, expanders/reducers / dismantling joints / saddles/ pipe extension pieces, 150mm dia Cast Iron sluice valve-1no.,gaskets, nuts, bolts, washers as per site requirement.Providing, fabrication and laying of 100mm dia MS delivery pipe as per site conditions including MS bends, MS flange, expanders/reducers / dismantling joints/ saddles/ pipe extension pieces, Cast steel Sluice valve 100mm dia and NRV 100mm alongwith by pass arrangement (class 150 accompanied with manufacturer’s in house test certificate) gaskets, nuts, bolts, washers. Job includes greasing work, P/F of graphited gland packing and thereafter testing on no load and then on full load and commissioning thereof. Job includes providing / fitting and laying of copper cable 25mm2from motor to panelin six leads approximately 36 meters for each motor, then p/f and laying 35mm2 copper cable upto MCCB-bus bar-voltage stabilizerin three leads approximately 30 meters in length alongwith neutral wire conforming to ISI standards with proper thimbling and insulation material. Job covers providing and fitting of 160 ampere MCCB of 50KA breaking strength. Proper chemical earthing of the equipment should be done for safety of machinery. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handing equipments etc. 35 Design, fabrication, installation, testing and commissioning of 110 ampere rating, 3 phase, LT control panel cum protection panel cum automatic star delta starter alongwith allied works by way of fabrication of panel with 3 pole Main and delta power contactors of 110 A rating 01 no. each and star power contactor 70 rating-1no., complete with all protection, safety and control devices / mechanism compatible with the design / rating of the prime mover, of reputed make, conforming to ISI standards. The system should be provided with fault analyzer cum controller unit or equivalent of standard and reputed make. The complete system should be enclosed in MS steel enclosure box of suitable dimensions. The enclosure should be finished with powder coated painting from inside as well as from outer surface of approved colour. Providing / laying of copper conductors of proper rating alongwith insulation material as per site requirement. The enclosure should be front shutter mounted with key locking system having glass window. Digital electronic voltmeter & ampere meter should be provided along with the required current transformer and selector switches. The internal control wiring should be done with flexible PVC LT cable with proper thimbling at each end. The system should trip the motor on power failure and on appearance of an electrical fault mentioned below which may otherwise damage the motor field coils and should not restart automatically until unless the system is reset manually, thus providing automation to the system and protection to the motor .The system / star delta auto starter should not fall into delta if it does not fall into star mode first and should remain de-energised to avoid damage to the motor / machinery and also to the power source / transformer. The system / star delta auto starter should trip off if it does not fall into delta & remains in star mode for more than 10-20 seconds. The system shall provide protection against:-Low voltage below 350 V, High Voltage above 450 V, Single phasing, Reverse phasing, Un Balanced phasing, Dry running, Overloading.In addition the system should have the following audio & visual features for a quick and accurate diagnosis of the appeared fault / status for a speedy rectification of the system-- Separate LED fault / status indicators, LED phase indicators. Isolation by pass system, for fault analysis of system, with a blinking indicator. An audio warning system/Siren which activates only on starter failure to trip the motor on appearance of any electrical fault mentioned above, to warn the operator to switch off the motor manually.3 LED, contactor ‘COIL OK’, indicators, one for each of the contactors / coils. LED star & delta indicators to access the star to delta timing. A tamper proof starting system to avoid manipulations by the motor operator to keep the system in a permanently ON position Testing of panel after making all incoming / outgoing connections on no load and then on full load. Proper chemical earthing of equipment should be done. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc, 36 Providing, installation, testing and commissioning of 10000 GPH x 250 meter head HC pump set withsuitable rating prime mover in compliance with the technical conditions andallied works by way of surveying of site, designing of pump machinery and prime mover in conformity with site conditions. Laying of M-20 grade RCC foundation block for each pump of size 6’x3’x4’ by using reinforcement steel of 10mm dia. The foundation block as per size of pump set should have additional margin of 6” on all sides. The foundation block may be combined for all the pumps which must includes space on all sides of pump set and space between the pump sets. Providing, fabrication and laying of 100mm dia MS suction pipe line to the pump set of length as per site conditions condition and upto maximum of approximately 6 meters each including 100mm dia MS bends, MS flanges, expanders/reducers / dismantling joints / saddles/ pipe extension pieces, 100mm dia Cast Iron sluice valve-1no.,gaskets, nuts, bolts, washers as per site requirement.Providing, fabrication and laying of 100mm dia MS delivery pipe as per site conditions including MS bends, MS flange, expanders/reducers / dismantling joints/ saddles/ pipe extension pieces, Cast steel Sluice valve 100mm dia and NRV 100mm alongwith by pass arrangement (class 300 accompanied with manufacturer’s in house test certificate) gaskets, nuts, bolts, washers. Job includes greasing work, P/F of graphited gland packing and thereafter testing on no load and then on full load and commissioning thereof. Job includes providing / fitting and laying of copper cable 50mm2from motor to panelin six leads approximately 36 meters for each motor, then p/f and laying 70mm2 copper cable upto MCCB-bus bar-voltage stabilizerin three leads approximately 30 meters in length alongwith neutral wire conforming to ISI standards with proper thimbling and insulation material. Job covers providing and fitting of 250 ampere MCCB of 50KA breaking strength. Proper chemical earthing of the equipment should be done for safety of machinery. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handing equipments etc. 37 Design, fabrication, installation, testing and commissioning of 185 ampere rating, 3 phase, LT control panel cum protection panel cum automatic star delta starter alongwith allied works by way of fabrication of panel with 3 pole Main and delta power contactors of 185 A rating 01 no. each and star power contactor 140 rating-1no., complete with all protection, safety and control devices / mechanism compatible with the design / rating of the prime mover, of reputed make, conforming to ISI standards. The system should be provided with fault analyzer cum controller unit or equivalent of standard and reputed make. The complete system should be enclosed in MS steel enclosure box of suitable dimensions. The enclosure should be finished with powder coated painting from inside as well as from outer surface of approved colour. Providing / laying of copper conductors of proper rating alongwith insulation material as per site requirement. The enclosure should be front shutter mounted with key locking system having glass window. Digital electronic voltmeter & ampere meter should be provided along with the required current transformer and selector switches. The internal control wiring should be done with flexible PVC LT cable with proper thimbling at each end. The system should trip the motor on power failure and on appearance of an electrical fault mentioned below which may otherwise damage the motor field coils and should not restart automatically until unless the system is reset manually, thus providing automation to the system and protection to the motor .The system / star delta auto starter should not fall into delta if it does not fall into star mode first and should remain de-energised to avoid damage to the motor / machinery and also to the power source / transformer. The system / star delta auto starter should trip off if it does not fall into delta & remains in star mode for more than 10-20 seconds. The system shall provide protection against:-Low voltage below 350 V, High Voltage above 450 V, Single phasing, Reverse phasing, Un Balanced phasing, Dry running, Overloading.In addition the system should have the following audio & visual features for a quick and accurate diagnosis of the appeared fault / status for a speedy rectification of the system-- Separate LED fault / status indicators, LED phase indicators. Isolation by pass system, for fault analysis of system, with a blinking indicator. An audio warning system/Siren which activates only on starter failure to trip the motor on appearance of any electrical fault mentioned above, to warn the operator to switch off the motor manually.3 LED, contactor ‘COIL OK’, indicators, one for each of the contactors / coils. LED star & delta indicators to access the star to delta timing. A tamper proof starting system to avoid manipulations by the motor operator to keep the system in a permanently ON position Testing of panel after making all incoming / outgoing connections on no load and then on full load. Proper chemical earthing of equipment should be done. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc,

Corrigendum Details

Sr No CorrigendumDate Corrignedum CorrigendumType NewSubmissionDate
1 23-Sep-2023 NNN Date 29-09-2023

Key Value

Document Fees
INR 500 /-
EMD
INR 386900.0 /-
Tender Value
Refer document

BOQ Items

Name of Work:-Providing, installation, testing and commissioning of electro-mechanical machinery alongwith allied works atCHANNI MANSAR(Udhampur District ) under JJM
Sl. No. Item Description
1STAGE-0 MAJALTA TO KAKRAI
2Providing, installation, testing and commissioning of 5000 GPH x 300 meter head HC pump set withsuitable rating prime mover in compliance with the technical conditions andallied works by way of surveying of site, designing of pump machinery and prime mover in conformity with site conditions. Laying of M-20 grade RCC foundation block for each pump of size 6’x3’x4’ by using reinforcement steel of 10mm dia. The foundation block as per size of pump set should have additional margin of 6” on all sides. The foundation block may be combined for all the pumps which must includes space on all sides of pump set and space between the pump sets. Providing, fabrication and laying of 80mm dia MS suction pipe line to the pump set of length as per site conditions condition and upto maximum of approximately 6 meters each including 80mm dia MS bends, MS flanges, expanders/reducers / dismantling joints / saddles/ pipe extension pieces, 80mm dia Cast Iron sluice valve-1no.,gaskets, nuts, bolts, washers as per site requirement.Providing, fabrication and laying of 80mm dia MS delivery pipe as per site conditions including MS bends, MS flange, expanders/reducers / dismantling joints/ saddles/ pipe extension pieces, Cast steel Sluice valve 80mm dia and NRV 80mm dia alongwith by pass arrangement (class 300 accompanied with manufacturer’s in house test certificate)gaskets, nuts, bolts, washers. Job includes greasing work, P/F of graphited gland packing and thereafter testing on no load and then on full load and commissioning thereof. Job includes providing / fitting and laying of copper cable 35mm2from motor to panelin six leads approximately 36 meters for each motor, then p/f and laying 50mm2 copper cable upto MCCB-bus bar-voltage stabilizerin three leads approximately 30 meters in length alongwith neutral wire conforming to ISI standards with proper thimbling and insulation material. Job covers providing and fitting of 250 ampere MCCB of 50KA breaking strength. Proper chemical earthing of the equipment should be done for safety of machinery. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handing equipments etc.
3Making connection of delivery lines with rising main through 100mm dia MS pipe manifold. Job includes providing and fitting of bus bar arrangement complete with frame and insulation work on the wall of the pump room.Job includes providing, laying and fixing of insulation rubber mats around electro mechanical machinery on the floor of the pump house Job includes providing and fitting of overhead MS girder of required size so as to sustain the load of material / equipment / machinery while lifting / shifting of the material / equipments / machinery alongwith chain pulley block (1no.) 3 ton. Job includes providing of maintenance tool kit as per enclosed annexure. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handling equipment etc.
4Design, fabrication, installation, testing and commissioning of 110 ampere rating, 3 phase, LT control panel cum protection panel cum automatic star delta starter alongwith allied works by way of fabrication of panel with 3 pole Main and delta power contactors of 110A rating 01 no. each and star power contactor of 70A rating-1no., complete with all protection, safety and control devices / mechanismcompatible with the design / rating of the prime mover, of reputed make, conforming to ISI standards. The system should be provided with fault analyzer cum controller unit or equivalent of standard and reputed make. The complete system should be enclosed in MS steel enclosure box of suitable dimensions. The enclosure should be finished with powder coated painting from inside as well as from outer surface of approved colour. Providing / laying of copper conductors of proper rating alongwith insulation material as per site requirement. The enclosure should be front shutter mounted with key locking system having glass window. Digital electronic voltmeter & ampere meter should be provided along with the required current transformer and selector switches. The internal control wiring should be done with flexible PVC LT cable with proper thimbling at each end. The system should trip the motor on power failure and on appearance of an electrical fault mentioned below which may otherwise damage the motor field coils and should not restart automatically until unless the system is reset manually, thus providing automation to the system and protection to the motor .The system / star delta auto starter should not fall into delta if it does not fall into star mode first and should remain de-energised to avoid damage to the motor / machinery and also to the power source / transformer. The system / star delta auto starter should trip off if it does not fall into delta & remains in star mode for more than 10-20 seconds. The system shall provide protection against:-Low voltage below 350 V, High Voltage above 450 V, Single phasing, Reverse phasing, Un Balanced phasing, Dry running, Overloading.In addition the system should have the following audio & visual features for a quick and accurate diagnosis of the appeared fault / status for a speedy rectification of the system-- Separate LED fault / status indicators, LED phase indicators. Isolation by pass system, for fault analysis of system, with a blinking indicator. An audio warning system/Siren which activates only on starter failure to trip the motor on appearance of any electrical fault mentioned above, to warn the operator to switch off the motor manually.3 LED, contactor ‘COIL OK’, indicators, one for each of the contactors / coils. LED star & delta indicators to access the star to delta timing. A tamper proof starting system to avoid manipulations by the motor operator to keep the system in a permanently ON position Testing of panel after making all incoming / outgoing connections on no load and then on full load. Proper chemical earthing of equipment should be done. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc,
5Providing, carriage, installation, testing and commissioning of 3 phase, 100 KVA voltage stabilizer copper wound, first quality CRGO silicon steel core, naturally- oil cooled, manually operated, 14 gaugecontainer chamber alongwith allied works. Job includes providing of 100 KVA voltage stabilizer complete with mineral insulating oil, MCCB, change over switch complete with safety and protection devices etc. Job includes providing and fitting of single core armoured Al. cable of 150mm2 from electric pole to main switch in four leads approximately 50 meters length of each lead and further Providing and fitting of 50mm2 copper cable from main switch to voltage stabilizer approximately 20 meters in length complete with insulation and thimbling.The voltage stabilizer should have 5 upwards steps and 2 downwards steps (or as per the specified voltage range) from the line voltage i.e. it should work from 180V to 400+5%. Proper chemical earthing of the equipment shall be done. Complete Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc.
6STAGE-KAKRAI MAHAMAYA MANDIR
7Providing, installation, testing and commissioning of 5000 GPH x 175 meter head HC pump set withsuitable rating prime mover in compliance with the technical conditions andallied works by way of surveying of site, designing of pump machinery and prime mover in conformity with site conditions. Laying of M-20 grade RCC foundation block for each pump of size 6’x3’x4’ by using reinforcement steel of 10mm dia. The foundation block as per size of pump set should have additional margin of 6” on all sides. The foundation block may be combined for all the pumps which must includes space on all sides of pump set and space between the pump sets. Providing, fabrication and laying of 80mm dia MS suction pipe line to the pump set of length as per site conditions condition and upto maximum of approximately 6 meters each including 80mm dia MS bends, MS flanges, expanders/reducers / dismantling joints / saddles/ pipe extension pieces, 80mm dia Cast Iron sluice valve-1no.,gaskets, nuts, bolts, washers as per site requirement.Providing, fabrication and laying of 80 dia MS delivery pipe as per site conditions including MS bends, MS flange, expanders/reducers / dismantling joints/ saddles/ pipe extension pieces, Cast steel Sluice valve 80mm dia and NRV 80mm alongwith by pass arrangement (class 300 accompanied with manufacturer’s in house test certificate)gaskets, nuts, bolts, washers. Job includes greasing work, P/F of graphited gland packing and thereafter testing on no load and then on full load and commissioning thereof. Job includes providing / fitting and laying of copper cable 16mm2from motor to panelin six leads approximately 36 meters for each motor, then p/f and laying 25mm2 copper cable upto MCCB-bus bar-voltage stabilizerin three leads approximately 30 meters in length alongwith neutral wire conforming to ISI standards with proper thimbling and insulation material. Job covers providing and fitting of 100 ampere MCCB of 50KA breaking strength. Proper chemical earthing of the equipment should be done for safety of machinery. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handing equipments etc.
8Making connection of delivery lines with rising main through 100 mm dia MS pipe manifold. Job includes providing and fitting of bus bar arrangement complete with frame and insulation work on the wall of the pump room. Job includes providing, laying and fixing of insulation rubber mats around electro mechanical machinery on the floor of the pump house Job includes providing and fitting of overhead MS girder of required size so as to sustain the load of material / equipment / machinery while lifting / shifting of the material / equipments / machinery alongwith chain pulley block (1no.) 3 ton. Job includes providing of maintenance tool kit as per enclosed annexure. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handling equipment etc.
9Design, fabrication, installation, testing and commissioning of 70 ampere rating, 3 phase, LT control panel cum protection panel cum automatic star delta starter alongwith allied works by way of fabrication of panel with 3 pole Main and delta power contactors of 70A rating 01 no. each and star power contactor 50 rating-1no., complete with all protection, safety and control devices / mechanism compatible with the design / rating of the prime mover, of reputed make, conforming to ISI standards. The system should be provided with fault analyzer cum controller unit or equivalent of standard and reputed make. The complete system should be enclosed in MS steel enclosure box of suitable dimensions. The enclosure should be finished with powder coated painting from inside as well as from outer surface of approved colour. Providing / laying of copper conductors of proper rating alongwith insulation material as per site requirement. The enclosure should be front shutter mounted with key locking system having glass window. Digital electronic voltmeter & ampere meter should be provided along with the required current transformer and selector switches. The internal control wiring should be done with flexible PVC LT cable with proper thimbling at each end. The system should trip the motor on power failure and on appearance of an electrical fault mentioned below which may otherwise damage the motor field coils and should not restart automatically until unless the system is reset manually, thus providing automation to the system and protection to the motor .The system / star delta auto starter should not fall into delta if it does not fall into star mode first and should remain de-energised to avoid damage to the motor / machinery and also to the power source / transformer. The system / star delta auto starter should trip off if it does not fall into delta & remains in star mode for more than 10-20 seconds. The system shall provide protection against:-Low voltage below 350 V, High Voltage above 450 V, Single phasing, Reverse phasing, Un Balanced phasing, Dry running, Overloading.In addition the system should have the following audio & visual features for a quick and accurate diagnosis of the appeared fault / status for a speedy rectification of the system-- Separate LED fault / status indicators, LED phase indicators. Isolation by pass system, for fault analysis of system, with a blinking indicator. An audio warning system/Siren which activates only on starter failure to trip the motor on appearance of any electrical fault mentioned above, to warn the operator to switch off the motor manually.3 LED, contactor ‘COIL OK’, indicators, one for each of the contactors / coils. LED star & delta indicators to access the star to delta timing. A tamper proof starting system to avoid manipulations by the motor operator to keep the system in a permanently ON position Testing of panel after making all incoming / outgoing connections on no load and then on full load. Proper chemical earthing of equipment should be done. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc,
10Providing, carriage, installation, testing and commissioning of 3 phase, 63 KVA voltage stabilizer copper wound, first quality CRGO silicon steel core, naturally- oil cooled, manually operated, 14 gaugecontainer chamber alongwith allied works. Job includes providing of 63 KVA voltage stabilizer complete with mineral insulating oil, MCCB, change over switch complete with safety and protection devices etc. Job includes providing and fitting of single core armoured Al. cable of 70mm2 from electric pole to main switch in four leads approximately 50 meters length of each lead and further Providing and fitting of 25mm2 copper cable from main switch to voltage stabilizer approximately 20 meters in length complete with insulation and thimbling. The voltage stabilizer should have 5 upwards steps and 2 downwards steps (or as per the specified voltage range) from the line voltage i.e. it should work from 180V to 400+5%. Proper chemical earthing of the equipment shall be done. Complete Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc.
11STAGE-0 KAKRAI TO CHADWA
12Providing, installation, testing and commissioning of 4000 GPH x 150 meter head HC pump set withsuitable rating prime mover in compliance with the technical conditions andallied works by way of surveying of site, designing of pump machinery and prime mover in conformity with site conditions. Laying of M-20 grade RCC foundation block for each pump of size 6’x3’x4’ by using reinforcement steel of 10mm dia. The foundation block as per size of pump set should have additional margin of 6” on all sides. The foundation block may be combined for all the pumps which must includes space on all sides of pump set and space between the pump sets. Providing, fabrication and laying of 80mm dia MS suction pipe line to the pump set of length as per site conditions condition and upto maximum of approximately 6 meters each including 80mm dia MS bends, MS flanges, expanders/reducers / dismantling joints / saddles/ pipe extension pieces, 80mm dia Cast Iron sluice valve-1no.,gaskets, nuts, bolts, washers as per site requirement.Providing, fabrication and laying of 80mm dia MS delivery pipe as per site conditions including MS bends, MS flange, expanders/reducers / dismantling joints/ saddles/ pipe extension pieces, Cast steel Sluice valve 80mm dia and NRV 80mm alongwith by pass arrangement (class 300 accompanied with manufacturer’s in house test certificate)gaskets, nuts, bolts, washers. Job includes greasing work, P/F of graphited gland packing and thereafter testing on no load and then on full load and commissioning thereof. Job includes providing / fitting and laying of copper cable 25mm2from motor to panelin six leads approximately 36 meters for each motor, then p/f and laying 35mm2 copper cable upto MCCB-bus bar-voltage stabilizerin three leads approximately 30 meters in length alongwith neutral wire conforming to ISI standards with proper thimbling and insulation material. Job covers providing and fitting of 100 ampere MCCB of 50KA breaking strength. Proper chemical earthing of the equipment should be done for safety of machinery. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handing equipments etc.
13Making connection of delivery lines with rising main through 100mm dia MS pipe manifold. Job includes providing and fitting of bus bar arrangement complete with frame and insulation work on the wall of the pump room. Job includes providing, laying and fixing of insulation rubber mats around electro mechanical machinery on the floor of the pump house Job includes providing and fitting of overhead MS girder of required size so as to sustain the load of material / equipment / machinery while lifting / shifting of the material / equipments / machinery alongwith chain pulley block (1no.) 3 ton. Job includes providing of maintenance tool kit as per enclosed annexure. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handling equipment etc.
14Design, fabrication, installation, testing and commissioning of 70 ampere rating, 3 phase, LT control panel cum protection panel cum automatic star delta starter alongwith allied works by way of fabrication of panel with 3 pole Main and delta power contactors of 70A rating 01 no. each and star power contactor of 50A rating-1no., complete with all protection, safety and control devices / mechanismcompatible with the design / rating of the prime mover, of reputed make, conforming to ISI standards. The system should be provided with fault analyzer cum controller unit or equivalent of standard and reputed make. The complete system should be enclosed in MS steel enclosure box of suitable dimensions. The enclosure should be finished with powder coated painting from inside as well as from outer surface of approved colour. Providing / laying of copper conductors of proper rating alongwith insulation material as per site requirement. The enclosure should be front shutter mounted with key locking system having glass window. Digital electronic voltmeter & ampere meter should be provided along with the required current transformer and selector switches. The internal control wiring should be done with flexible PVC LT cable with proper thimbling at each end. The system should trip the motor on power failure and on appearance of an electrical fault mentioned below which may otherwise damage the motor field coils and should not restart automatically until unless the system is reset manually, thus providing automation to the system and protection to the motor .The system / star delta auto starter should not fall into delta if it does not fall into star mode first and should remain de-energised to avoid damage to the motor / machinery and also to the power source / transformer. The system / star delta auto starter should trip off if it does not fall into delta & remains in star mode for more than 10-20 seconds. The system shall provide protection against:-Low voltage below 350 V, High Voltage above 450 V, Single phasing, Reverse phasing, Un Balanced phasing, Dry running, Overloading.In addition the system should have the following audio & visual features for a quick and accurate diagnosis of the appeared fault / status for a speedy rectification of the system-- Separate LED fault / status indicators, LED phase indicators. Isolation by pass system, for fault analysis of system, with a blinking indicator. An audio warning system/Siren which activates only on starter failure to trip the motor on appearance of any electrical fault mentioned above, to warn the operator to switch off the motor manually.3 LED, contactor ‘COIL OK’, indicators, one for each of the contactors / coils. LED star & delta indicators to access the star to delta timing. A tamper proof starting system to avoid manipulations by the motor operator to keep the system in a permanently ON position Testing of panel after making all incoming / outgoing connections on no load and then on full load. Proper chemical earthing of equipment should be done. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc,
15Providing, carriage, installation, testing and commissioning of 3 phase, 63 KVA voltage stabilizer copper wound, first quality CRGO silicon steel core, naturally- oil cooled, manually operated, 14 gaugecontainer chamber alongwith allied works. Job includes providing of 63 KVA voltage stabilizer complete with mineral insulating oil, MCCB, change over switch complete with safety and protection devices etc. Job includes providing and fitting of single core armoured Al. cable of 70mm2 from electric pole to main switch in four leads approximately 50 meters length of each lead and further Providing and fitting of 35mm2 copper cable from main switch to voltage stabilizer approximately 20 meters in length complete with insulation and thimbling. The voltage stabilizer should have 5 upwards steps and 2 downwards steps (or as per the specified voltage range) from the line voltage i.e. it should work from 180V to 400+5%. Proper chemical earthing of the equipment shall be done. Complete Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc.
16PUMP ROOM MANSAR TO MOHDIAN
17Providing, installation, testing and commissioning of 2000 GPH x 85 meter head HC pump set withsuitable rating prime mover in compliance with the technical conditions andallied works by way of surveying of site, designing of pump machinery and prime mover in conformity with site conditions. Laying of M-20 grade RCC foundation block for each pump of size 6’x3’x4’ by using reinforcement steel of 10mm dia. The foundation block as per size of pump set should have additional margin of 6” on all sides. The foundation block may be combined for all the pumps which must includes space on all sides of pump set and space between the pump sets. Providing, fabrication and laying of 65mm dia MS suction pipe line to the pump set of length as per site conditions condition and upto maximum of approximately 6 meters each including 65mm dia MS bends, MS flanges, expanders/reducers / dismantling joints / saddles/ pipe extension pieces, 65mm dia Cast Iron sluice valve-1no.,gaskets, nuts, bolts, washers as per site requirement.Providing, fabrication and laying of 65mm dia MS delivery pipe as per site conditions including MS bends, MS flange, expanders/reducers / dismantling joints/ saddles/ pipe extension pieces, Cast steel Sluice valve 65mm dia and NRV 65mm alongwith by pass arrangement (class 150 accompanied with manufacturer’s in house test certificate)gaskets, nuts, bolts, washers. Job includes greasing work, P/F of graphited gland packing and thereafter testing on no load and then on full load and commissioning thereof. Job includes providing / fitting and laying of copper cable 10mm2from motor to panelin six leads approximately 36 meters for each motor, then p/f and laying 16mm2 copper cable upto MCCB-bus bar-voltage stabilizerin three leads approximately 30 meters in length alongwith neutral wire conforming to ISI standards with proper thimbling and insulation material. Job covers providing and fitting of 63 ampere MCCB of 50KA breaking strength. Proper chemical earthing of the equipment should be done for safety of machinery. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handing equipments etc.
18Making connection of delivery lines with rising main through 80 mm dia MS pipe manifold. Job includes providing and fitting of bus bar arrangement complete with frame and insulation work on the wall of the pump room. Job includes providing, laying and fixing of insulation rubber mats around electro mechanical machinery on the floor of the pump house Job includes providing and fitting of overhead MS girder of required size so as to sustain the load of material / equipment / machinery while lifting / shifting of the material / equipments / machinery alongwith chain pulley block (1no.) 3 ton. Job includes providing of maintenance tool kit as per enclosed annexure. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handling equipment etc.
19Design, fabrication, installation, testing and commissioning of 50 ampere rating, 3 phase, LT control panel cum protection panel cum automatic star delta starter alongwith allied works by way of fabrication of panel with 3 pole Main and delta power contactors of 50A rating 01 no. each and star power contactor 50 rating-1no., complete with all protection, safety and control devices / mechanism compatible with the design / rating of the prime mover, of reputed make, conforming to ISI standards. The system should be provided with fault analyzer cum controller unit or equivalent of standard and reputed make. The complete system should be enclosed in MS steel enclosure box of suitable dimensions. The enclosure should be finished with powder coated painting from inside as well as from outer surface of approved colour. Providing / laying of copper conductors of proper rating alongwith insulation material as per site requirement. The enclosure should be front shutter mounted with key locking system having glass window. Digital electronic voltmeter & ampere meter should be provided along with the required current transformer and selector switches. The internal control wiring should be done with flexible PVC LT cable with proper thimbling at each end. The system should trip the motor on power failure and on appearance of an electrical fault mentioned below which may otherwise damage the motor field coils and should not restart automatically until unless the system is reset manually, thus providing automation to the system and protection to the motor .The system / star delta auto starter should not fall into delta if it does not fall into star mode first and should remain de-energised to avoid damage to the motor / machinery and also to the power source / transformer. The system / star delta auto starter should trip off if it does not fall into delta & remains in star mode for more than 10-20 seconds. The system shall provide protection against:-Low voltage below 350 V, High Voltage above 450 V, Single phasing, Reverse phasing, Un Balanced phasing, Dry running, Overloading.In addition the system should have the following audio & visual features for a quick and accurate diagnosis of the appeared fault / status for a speedy rectification of the system-- Separate LED fault / status indicators, LED phase indicators. Isolation by pass system, for fault analysis of system, with a blinking indicator. An audio warning system/Siren which activates only on starter failure to trip the motor on appearance of any electrical fault mentioned above, to warn the operator to switch off the motor manually.3 LED, contactor ‘COIL OK’, indicators, one for each of the contactors / coils. LED star & delta indicators to access the star to delta timing. A tamper proof starting system to avoid manipulations by the motor operator to keep the system in a permanently ON position Testing of panel after making all incoming / outgoing connections on no load and then on full load. Proper chemical earthing of equipment should be done. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc,
20Providing, carriage, installation, testing and commissioning of 3 phase, 63 KVA voltage stabilizer copper wound, first quality CRGO silicon steel core, naturally- oil cooled, manually operated, 14 gaugecontainer chamber alongwith allied works. Job includes providing of 63 KVA voltage stabilizer complete with mineral insulating oil, MCCB, change over switch complete with safety and protection devices etc. Job includes providing and fitting of single core armoured Al. cable of 70mm2 from electric pole to main switch in four leads approximately 50 meters length of each lead and further Providing and fitting of 25mm2 copper cable from main switch to voltage stabilizer approximately 20 meters in length complete with insulation and thimbling. The voltage stabilizer should have 5 upwards steps and 2 downwards steps (or as per the specified voltage range) from the line voltage i.e. it should work from 180V to 400+5%. Proper chemical earthing of the equipment shall be done. Complete Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc.
21PUMP ROOM MANSAR TO KATTAL
22Providing, installation, testing and commissioning of 3000 GPH x 200 meter head HC pump set withsuitable rating prime mover in compliance with the technical conditions andallied works by way of surveying of site, designing of pump machinery and prime mover in conformity with site conditions. Laying of M-20 grade RCC foundation block for each pump of size 6’x3’x4’ by using reinforcement steel of 10mm dia. The foundation block as per size of pump set should have additional margin of 6” on all sides. The foundation block may be combined for all the pumps which must includes space on all sides of pump set and space between the pump sets. Providing, fabrication and laying of 65mm dia MS suction pipe line to the pump set of length as per site conditions condition and upto maximum of approximately 6 meters each including 65mm dia MS bends, MS flanges, expanders/reducers / dismantling joints / saddles/ pipe extension pieces, 65mm dia Cast Iron sluice valve-1no.,gaskets, nuts, bolts, washers as per site requirement.Providing, fabrication and laying of 65mm dia MS delivery pipe as per site conditions including MS bends, MS flange, expanders/reducers / dismantling joints/ saddles/ pipe extension pieces, Cast steel Sluice valve 65mm dia and NRV 65mm alongwith by pass arrangement (class 300 accompanied with manufacturer’s in house test certificate)gaskets, nuts, bolts, washers. Job includes greasing work, P/F of graphited gland packing and thereafter testing on no load and then on full load and commissioning thereof. Job includes providing / fitting and laying of copper cable 16mm2from motor to panelin six leads approximately 36 meters for each motor, then p/f and laying 25mm2 copper cable upto MCCB-bus bar-voltage stabilizerin three leads approximately 30 meters in length alongwith neutral wire conforming to ISI standards with proper thimbling and insulation material. Job covers providing and fitting of 63 ampere MCCB of 50KA breaking strength. Proper chemical earthing of the equipment should be done for safety of machinery. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handing equipments etc.
23Making connection of delivery lines with rising main through 80 mm dia MS pipe manifold. Job includes providing and fitting of bus bar arrangement complete with frame and insulation work on the wall of the pump room. Job includes providing, laying and fixing of insulation rubber mats around electro mechanical machinery on the floor of the pump house Job includes providing and fitting of overhead MS girder of required size so as to sustain the load of material / equipment / machinery while lifting / shifting of the material / equipments / machinery alongwith chain pulley block (1no.) 3 ton. Job includes providing of maintenance tool kit as per enclosed annexure. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handling equipment etc.
24Design, fabrication, installation, testing and commissioning of 70 ampere rating, 3 phase, LT control panel cum protection panel cum automatic star delta starter alongwith allied works by way of fabrication of panel with 3 pole Main and delta power contactors of 70A rating 01 no. each and star power contactor 50 rating-1no., complete with all protection, safety and control devices / mechanism compatible with the design / rating of the prime mover, of reputed make, conforming to ISI standards. The system should be provided with fault analyzer cum controller unit or equivalent of standard and reputed make. The complete system should be enclosed in MS steel enclosure box of suitable dimensions. The enclosure should be finished with powder coated painting from inside as well as from outer surface of approved colour. Providing / laying of copper conductors of proper rating alongwith insulation material as per site requirement. The enclosure should be front shutter mounted with key locking system having glass window. Digital electronic voltmeter & ampere meter should be provided along with the required current transformer and selector switches. The internal control wiring should be done with flexible PVC LT cable with proper thimbling at each end. The system should trip the motor on power failure and on appearance of an electrical fault mentioned below which may otherwise damage the motor field coils and should not restart automatically until unless the system is reset manually, thus providing automation to the system and protection to the motor .The system / star delta auto starter should not fall into delta if it does not fall into star mode first and should remain de-energised to avoid damage to the motor / machinery and also to the power source / transformer. The system / star delta auto starter should trip off if it does not fall into delta & remains in star mode for more than 10-20 seconds. The system shall provide protection against:-Low voltage below 350 V, High Voltage above 450 V, Single phasing, Reverse phasing, Un Balanced phasing, Dry running, Overloading.In addition the system should have the following audio & visual features for a quick and accurate diagnosis of the appeared fault / status for a speedy rectification of the system-- Separate LED fault / status indicators, LED phase indicators. Isolation by pass system, for fault analysis of system, with a blinking indicator. An audio warning system/Siren which activates only on starter failure to trip the motor on appearance of any electrical fault mentioned above, to warn the operator to switch off the motor manually.3 LED, contactor ‘COIL OK’, indicators, one for each of the contactors / coils. LED star & delta indicators to access the star to delta timing. A tamper proof starting system to avoid manipulations by the motor operator to keep the system in a permanently ON position Testing of panel after making all incoming / outgoing connections on no load and then on full load. Proper chemical earthing of equipment should be done. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc,
25Providing, carriage, installation, testing and commissioning of 3 phase, 63 KVA voltage stabilizer copper wound, first quality CRGO silicon steel core, naturally- oil cooled, manually operated, 14 gaugecontainer chamber alongwith allied works. Job includes providing of 63 KVA voltage stabilizer complete with mineral insulating oil, MCCB, change over switch complete with safety and protection devices etc. Job includes providing and fitting of single core armoured Al. cable of 70mm2 from electric pole to main switch in four leads approximately 50 meters length of each lead and further Providing and fitting of 25mm2 copper cable from main switch to voltage stabilizer approximately 20 meters in length complete with insulation and thimbling. The voltage stabilizer should have 5 upwards steps and 2 downwards steps (or as per the specified voltage range) from the line voltage i.e. it should work from 180V to 400+5%. Proper chemical earthing of the equipment shall be done. Complete Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc.
26PUMP ROOM SARAL CHOWA TO CHANED
27Providing, installation, testing and commissioning of 2000 GPH x 90 meter head HC pump set withsuitable rating prime mover in compliance with the technical conditions andallied works by way of surveying of site, designing of pump machinery and prime mover in conformity with site conditions. Laying of M-20 grade RCC foundation block for each pump of size 6’x3’x4’ by using reinforcement steel of 10mm dia. The foundation block as per size of pump set should have additional margin of 6” on all sides. The foundation block may be combined for all the pumps which must includes space on all sides of pump set and space between the pump sets. Providing, fabrication and laying of 65mm dia MS suction pipe line to the pump set of length as per site conditions condition and upto maximum of approximately 6 meters each including 65mm dia MS bends, MS flanges, expanders/reducers / dismantling joints / saddles/ pipe extension pieces, 65mm dia Cast Iron sluice valve-1no.,gaskets, nuts, bolts, washers as per site requirement.Providing, fabrication and laying of 65mm dia MS delivery pipe as per site conditions including MS bends, MS flange, expanders/reducers / dismantling joints/ saddles/ pipe extension pieces, Cast steel Sluice valve 65mm dia and NRV 65mm alongwith by pass arrangement (class 150 accompanied with manufacturer’s in house test certificate) gaskets, nuts, bolts, washers. Job includes greasing work, P/F of graphited gland packing and thereafter testing on no load and then on full load and commissioning thereof. Job includes providing / fitting and laying of copper cable 10mm2from motor to panelin six leads approximately 36 meters for each motor, then p/f and laying 16mm2 copper cable upto MCCB-bus bar-voltage stabilizerin three leads approximately 30 meters in length alongwith neutral wire conforming to ISI standards with proper thimbling and insulation material. Job covers providing and fitting of 63 ampere MCCB of 50KA breaking strength. Proper chemical earthing of the equipment should be done for safety of machinery. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handing equipments etc.
28Making connection of delivery lines with rising main through 80 mm dia MS pipe manifold. Job includes providing and fitting of bus bar arrangement complete with frame and insulation work on the wall of the pump room. Job includes providing, laying and fixing of insulation rubber mats around electro mechanical machinery on the floor of the pump house Job includes providing and fitting of overhead MS girder of required size so as to sustain the load of material / equipment / machinery while lifting / shifting of the material / equipments / machinery alongwith chain pulley block (1no.) 3 ton. Job includes providing of maintenance tool kit as per enclosed annexure. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handling equipment etc.
29Design, fabrication, installation, testing and commissioning of 50 ampere rating, 3 phase, LT control panel cum protection panel cum automatic star delta starter alongwith allied works by way of fabrication of panel with 3 pole Main and delta power contactors of 50 A rating 01 no. each and star power contactor 50 rating-1no., complete with all protection, safety and control devices / mechanism compatible with the design / rating of the prime mover, of reputed make, conforming to ISI standards. The system should be provided with fault analyzer cum controller unit or equivalent of standard and reputed make. The complete system should be enclosed in MS steel enclosure box of suitable dimensions. The enclosure should be finished with powder coated painting from inside as well as from outer surface of approved colour. Providing / laying of copper conductors of proper rating alongwith insulation material as per site requirement. The enclosure should be front shutter mounted with key locking system having glass window. Digital electronic voltmeter & ampere meter should be provided along with the required current transformer and selector switches. The internal control wiring should be done with flexible PVC LT cable with proper thimbling at each end. The system should trip the motor on power failure and on appearance of an electrical fault mentioned below which may otherwise damage the motor field coils and should not restart automatically until unless the system is reset manually, thus providing automation to the system and protection to the motor .The system / star delta auto starter should not fall into delta if it does not fall into star mode first and should remain de-energised to avoid damage to the motor / machinery and also to the power source / transformer. The system / star delta auto starter should trip off if it does not fall into delta & remains in star mode for more than 10-20 seconds. The system shall provide protection against:-Low voltage below 350 V, High Voltage above 450 V, Single phasing, Reverse phasing, Un Balanced phasing, Dry running, Overloading.In addition the system should have the following audio & visual features for a quick and accurate diagnosis of the appeared fault / status for a speedy rectification of the system-- Separate LED fault / status indicators, LED phase indicators. Isolation by pass system, for fault analysis of system, with a blinking indicator. An audio warning system/Siren which activates only on starter failure to trip the motor on appearance of any electrical fault mentioned above, to warn the operator to switch off the motor manually.3 LED, contactor ‘COIL OK’, indicators, one for each of the contactors / coils. LED star & delta indicators to access the star to delta timing. A tamper proof starting system to avoid manipulations by the motor operator to keep the system in a permanently ON position Testing of panel after making all incoming / outgoing connections on no load and then on full load. Proper chemical earthing of equipment should be done. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc,
30Providing, carriage, installation, testing and commissioning of 3 phase, 63 KVA voltage stabilizer copper wound, first quality CRGO silicon steel core, naturally- oil cooled, manually operated, 14 gaugecontainer chamber alongwith allied works. Job includes providing of 63 KVA voltage stabilizer complete with mineral insulating oil, MCCB, change over switch complete with safety and protection devices etc. Job includes providing and fitting of single core armoured Al. cable of 50mm2 from electric pole to main switch in four leads approximately 50 meters length of each lead and further Providing and fitting of 16mm2 copper cable from main switch to voltage stabilizer approximately 20 meters in length complete with insulation and thimbling. The voltage stabilizer should have 5 upwards steps and 2 downwards steps (or as per the specified voltage range) from the line voltage i.e. it should work from 180V to 400+5%. Proper chemical earthing of the equipment shall be done. Complete Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc.
31RETROFITTING
32Providing, installation, testing and commissioning of 20000 GPH x 10-13 meter head mono submersible pump set,4mm2 flat submersible copper cable 3 core approximately 90 meters in length , 10 HP MUG starter alongwith fabrication and fitting of MS pipe, flanges etc. including allied works at pumping station Mansar. Complete Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles and material handling equipment etc.
33Providing, installation, testing and commissioning of 6000 GPH x 10-13 meter head mono submersible pump set,2.5mm2 flat submersible copper cable 3 core approximately 90 meters in length , 7.5 HP MUG starter alongwith fabrication and fitting of MS pipe, flanges etc. including allied works at pumping station Badigarh. Complete Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles and material handling equipment etc.
34Providing, installation, testing and commissioning of 20000 GPH x 90 meter head HC pump set withsuitable rating prime mover in compliance with the technical conditions andallied works by way of surveying of site, designing of pump machinery and prime mover in conformity with site conditions. Laying of M-20 grade RCC foundation block for each pump of size 6’x3’x4’ by using reinforcement steel of 10mm dia. The foundation block as per size of pump set should have additional margin of 6” on all sides. The foundation block may be combined for all the pumps which must includes space on all sides of pump set and space between the pump sets. Providing, fabrication and laying of 150mm dia MS suction pipe line to the pump set of length as per site conditions condition and upto maximum of approximately 6 meters each including 150mm dia MS bends, MS flanges, expanders/reducers / dismantling joints / saddles/ pipe extension pieces, 150mm dia Cast Iron sluice valve-1no.,gaskets, nuts, bolts, washers as per site requirement.Providing, fabrication and laying of 100mm dia MS delivery pipe as per site conditions including MS bends, MS flange, expanders/reducers / dismantling joints/ saddles/ pipe extension pieces, Cast steel Sluice valve 100mm dia and NRV 100mm alongwith by pass arrangement (class 150 accompanied with manufacturer’s in house test certificate) gaskets, nuts, bolts, washers. Job includes greasing work, P/F of graphited gland packing and thereafter testing on no load and then on full load and commissioning thereof. Job includes providing / fitting and laying of copper cable 25mm2from motor to panelin six leads approximately 36 meters for each motor, then p/f and laying 35mm2 copper cable upto MCCB-bus bar-voltage stabilizerin three leads approximately 30 meters in length alongwith neutral wire conforming to ISI standards with proper thimbling and insulation material. Job covers providing and fitting of 160 ampere MCCB of 50KA breaking strength. Proper chemical earthing of the equipment should be done for safety of machinery. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handing equipments etc.
35Design, fabrication, installation, testing and commissioning of 110 ampere rating, 3 phase, LT control panel cum protection panel cum automatic star delta starter alongwith allied works by way of fabrication of panel with 3 pole Main and delta power contactors of 110 A rating 01 no. each and star power contactor 70 rating-1no., complete with all protection, safety and control devices / mechanism compatible with the design / rating of the prime mover, of reputed make, conforming to ISI standards. The system should be provided with fault analyzer cum controller unit or equivalent of standard and reputed make. The complete system should be enclosed in MS steel enclosure box of suitable dimensions. The enclosure should be finished with powder coated painting from inside as well as from outer surface of approved colour. Providing / laying of copper conductors of proper rating alongwith insulation material as per site requirement. The enclosure should be front shutter mounted with key locking system having glass window. Digital electronic voltmeter & ampere meter should be provided along with the required current transformer and selector switches. The internal control wiring should be done with flexible PVC LT cable with proper thimbling at each end. The system should trip the motor on power failure and on appearance of an electrical fault mentioned below which may otherwise damage the motor field coils and should not restart automatically until unless the system is reset manually, thus providing automation to the system and protection to the motor .The system / star delta auto starter should not fall into delta if it does not fall into star mode first and should remain de-energised to avoid damage to the motor / machinery and also to the power source / transformer. The system / star delta auto starter should trip off if it does not fall into delta & remains in star mode for more than 10-20 seconds. The system shall provide protection against:-Low voltage below 350 V, High Voltage above 450 V, Single phasing, Reverse phasing, Un Balanced phasing, Dry running, Overloading.In addition the system should have the following audio & visual features for a quick and accurate diagnosis of the appeared fault / status for a speedy rectification of the system-- Separate LED fault / status indicators, LED phase indicators. Isolation by pass system, for fault analysis of system, with a blinking indicator. An audio warning system/Siren which activates only on starter failure to trip the motor on appearance of any electrical fault mentioned above, to warn the operator to switch off the motor manually.3 LED, contactor ‘COIL OK’, indicators, one for each of the contactors / coils. LED star & delta indicators to access the star to delta timing. A tamper proof starting system to avoid manipulations by the motor operator to keep the system in a permanently ON position Testing of panel after making all incoming / outgoing connections on no load and then on full load. Proper chemical earthing of equipment should be done. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc,
36Providing, installation, testing and commissioning of 10000 GPH x 250 meter head HC pump set withsuitable rating prime mover in compliance with the technical conditions andallied works by way of surveying of site, designing of pump machinery and prime mover in conformity with site conditions. Laying of M-20 grade RCC foundation block for each pump of size 6’x3’x4’ by using reinforcement steel of 10mm dia. The foundation block as per size of pump set should have additional margin of 6” on all sides. The foundation block may be combined for all the pumps which must includes space on all sides of pump set and space between the pump sets. Providing, fabrication and laying of 100mm dia MS suction pipe line to the pump set of length as per site conditions condition and upto maximum of approximately 6 meters each including 100mm dia MS bends, MS flanges, expanders/reducers / dismantling joints / saddles/ pipe extension pieces, 100mm dia Cast Iron sluice valve-1no.,gaskets, nuts, bolts, washers as per site requirement.Providing, fabrication and laying of 100mm dia MS delivery pipe as per site conditions including MS bends, MS flange, expanders/reducers / dismantling joints/ saddles/ pipe extension pieces, Cast steel Sluice valve 100mm dia and NRV 100mm alongwith by pass arrangement (class 300 accompanied with manufacturer’s in house test certificate) gaskets, nuts, bolts, washers. Job includes greasing work, P/F of graphited gland packing and thereafter testing on no load and then on full load and commissioning thereof. Job includes providing / fitting and laying of copper cable 50mm2from motor to panelin six leads approximately 36 meters for each motor, then p/f and laying 70mm2 copper cable upto MCCB-bus bar-voltage stabilizerin three leads approximately 30 meters in length alongwith neutral wire conforming to ISI standards with proper thimbling and insulation material. Job covers providing and fitting of 250 ampere MCCB of 50KA breaking strength. Proper chemical earthing of the equipment should be done for safety of machinery. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools, tackles, and material handing equipments etc.
37Design, fabrication, installation, testing and commissioning of 185 ampere rating, 3 phase, LT control panel cum protection panel cum automatic star delta starter alongwith allied works by way of fabrication of panel with 3 pole Main and delta power contactors of 185 A rating 01 no. each and star power contactor 140 rating-1no., complete with all protection, safety and control devices / mechanism compatible with the design / rating of the prime mover, of reputed make, conforming to ISI standards. The system should be provided with fault analyzer cum controller unit or equivalent of standard and reputed make. The complete system should be enclosed in MS steel enclosure box of suitable dimensions. The enclosure should be finished with powder coated painting from inside as well as from outer surface of approved colour. Providing / laying of copper conductors of proper rating alongwith insulation material as per site requirement. The enclosure should be front shutter mounted with key locking system having glass window. Digital electronic voltmeter & ampere meter should be provided along with the required current transformer and selector switches. The internal control wiring should be done with flexible PVC LT cable with proper thimbling at each end. The system should trip the motor on power failure and on appearance of an electrical fault mentioned below which may otherwise damage the motor field coils and should not restart automatically until unless the system is reset manually, thus providing automation to the system and protection to the motor .The system / star delta auto starter should not fall into delta if it does not fall into star mode first and should remain de-energised to avoid damage to the motor / machinery and also to the power source / transformer. The system / star delta auto starter should trip off if it does not fall into delta & remains in star mode for more than 10-20 seconds. The system shall provide protection against:-Low voltage below 350 V, High Voltage above 450 V, Single phasing, Reverse phasing, Un Balanced phasing, Dry running, Overloading.In addition the system should have the following audio & visual features for a quick and accurate diagnosis of the appeared fault / status for a speedy rectification of the system-- Separate LED fault / status indicators, LED phase indicators. Isolation by pass system, for fault analysis of system, with a blinking indicator. An audio warning system/Siren which activates only on starter failure to trip the motor on appearance of any electrical fault mentioned above, to warn the operator to switch off the motor manually.3 LED, contactor ‘COIL OK’, indicators, one for each of the contactors / coils. LED star & delta indicators to access the star to delta timing. A tamper proof starting system to avoid manipulations by the motor operator to keep the system in a permanently ON position Testing of panel after making all incoming / outgoing connections on no load and then on full load. Proper chemical earthing of equipment should be done. Job includes cost of machinery, equipments and material, transportation charges, manual carriage charges, labour charges, loading /unloading charges, hire charges of tools and tackles etc,
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail