Construction Of 22.00 Mtrs. Span R.C.C. T-Beam Bridge Over Digwa Khalaat Rd 7/210 On Link Road Millah Digwakm 0/0 To 7/500 In Distt. Sirmour (H.P.)(Sh:- Construction Of Balance Work Of Bridge Portion Including Wing Wall ) Schemes Under Leftout (Missing) B, Sirmaur-Himachal Pradesh

Public Works Department-PWD has published Construction Of 22.00 Mtrs. Span R.C.C. T-Beam Bridge Over Digwa Khalaat Rd 7/210 On Link Road Millah Digwakm 0/0 To 7/500 In Distt. Sirmour (H.P.)(Sh:- Construction Of Balance Work Of Bridge Portion Including Wing Wall ) Schemes Under Leftout (Missing) B. Submission Date for this Tender is 23-09-2023. Road Work Tenders in Sirmaur Himachal Pradesh. Bidders can get complete Tender details and download the document.




Tender Notice

39621173
Construction Of 22.00 Mtrs. Span R.C.C. T-Beam Bridge Over Digwa Khalaat Rd 7/210 On Link Road Millah Digwakm 0/0 To 7/500 In Distt. Sirmour (H.P.)(Sh:- Construction Of Balance Work Of Bridge Portion Including Wing Wall ) Schemes Under Leftout (Missing) B
National Competitive Bid
Indian
Himachal Pradesh
Sirmaur
23-09-2023

Tender Details

Construction Of 22.00 Mtrs. Span R.C.C. T-Beam Bridge Over Digwa Khalaat Rd 7 / 210 On Link Road Millah Digwakm 0 / 0 To 7 / 500 In Distt. Sirmour ( H.P. ) ( Sh:- Construction Of Balance Work Of Bridge Portion Including Wing Wall ) Schemes Under Leftout ( Missing ) Bridges Under Pmgsy Package No. Hp-10-178

Key Value

Document Fees
INR 5000 /-
EMD
INR 145000.0 /-
Tender Value
INR 72.31 Lakhs /-

BOQ Items

Name of Work:C/O 22.00 mtrs. span R.C.C. T-Beam Bridge over Digwa Khalaat RD 7/210 on link roadMillah DigwaKm 0/0 to 7/500 in Distt. Sirmour (H.P.)(SH:- C/O balance work of Bridge portion including wing wall ) Schemes under leftout (Missing) Bridges under PMGSY Package No. HP-10-178
Sl. No. Item Description
1Excavation for Structures in all depths (Earth work in excavation of foundation of structures as per drawing and technical specification,including setting out, construction of shoring and bracing, removalof stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material.)All work of rock cutting by blasting shallbecarried out by taking all necessary precautionsagainstsoil erosion damage to hill side water pollution etc. and to protect stability ofhill side rock shall be excavated with chiseling and wedging out rock (where blasting is prohibited). All earth work in cutting/excavation including rock excavation shall be carried out true to lines grades, side slopes, width, camber super elevation and level as shown on the drawings or as directed by the Engineer-in-Chargehauling and stacking of materials useful for construction at suitable sites and safe disposal of unsuitable cut materials in specified manner filling of unevenness blind age and finishing of the road tospecifieddimensionorasdirectedbythe Enginer-in-Charge.Ifthefoundation ofthe structureisinanareawithstagnantwateror water is met with in the excavation due to spring seepage rain and other causes it shall be remove by suitable diversion bailing out or pumping as directed and the area of the foundation or embankment shall be kept dry. Any loss to the public or private property during the course of excavation shall be the whole responsibility of the contractor which shall have to be duly compensated by him at his own cost in all cases.
2Providing and laying concrete Mechanically mixed and vibrated PCC M-10 ( Ten) grade 1:3:6 (one cement : three sand: six graded stone aggregate40mm(fortymillimeter) nominalsize for plain /reinforced concrete in open foundations andplinths or similar works complete as per drawingsandtechnicalspecification clauses 802, 803, 1202 and 1203 ( Eight hundred two,Eight hundred three, One thousand two hundred two and One thousand two hundred three)and curing complete including the cost of form work and hauling of materials in all leads and lifts as per the entire satisfaction and direction of Engineer-in-Charge.
3Providing concrete for plain/reinforced cement concrete( M30 (Thirty) - grade ) in Sub-structure as per drawing and Technical Specification including hauling of material in all leads, lifts as per the entire satisfaction and direction of Engineer-in-charge.
4Supplying, fitting and placing HYSD bar reinforcement in sub-structure/super structure complete as per drawing and Technical specification including carriage of material within all leads, lifts and other incidental charges and as per direction of Engineer-In-Charge.
5Providing weep holesin Brickmasonry/Plain/R einforced concrete abutment, wing wall/return wallwith 100 mm ( One hundred milimetre) dia PVC/AC pipe, extending through the full width of the structure with slope of 1V(One Vertical) :20H (Twenty Horigintial) towards drawing foce. Complete as per drawing and T echnicalspecificationsincluding hauling of material within all leads and lifts and other incidental charges and as per direction of Engineer-In-Charge.
6Providing and laying of Filtermedia with granular materials/stone crushed aggregates satisfying the requirements laid down in clause 2504.2.2. ( Two thousand five hundred four point Two point Two) of MORTH specifications to a thickness of not less than 600 mm (Six hundred milimeter) with smaller size towards the soil and bigger size towards the wall and provided over the entire surface behind abutment,wingwall and return wall to the full height compacted to a firm condition complete as per drawing and technical specification.including hauling of material within all leads and lifts and other incidental charges and as per direction of Engineer-In-Charge.
7Furnishing and Placing Reinforced/Prestressed cement concrete ( M-35(Thirty five) grade ) in Sub-structure as per drawing and Technical Specification including hauling of material in all leads, lifts as per the entire satisfaction and direction of Engineer-in-charge.
8Supplying,fitting and fixing in position true to line and levelPOT-PTFEconsisting of a metal piston supported by a disc or unreinforced elastomer confined within a metal cylinder, sealing rings, dust seals PTFE surface sliding against stainless steel mating surface, complete assembly to be of cast steel / fabricated structural steel, metal and elastomer elements to be as per IRC:83 ( Eigthy three) part-I and part - II respectively and other parts conforming to BS:5400,( Five thousand four hundred) section 9.1 and 9.2 ( Nine point one and nine point two) and clause 2006 ( Two thousand six) of MORTH Specifications complete as per drawing and approvedtechnical specifications complete in all respect .includingall leads andlifts and carriage of materials as perentire satisfaction and direction of Engineer-in-charge.
9Construction of RCC railing of M 30 ( Thirty) Grade in-situ with 20 mm (Twenty milimeter) nominal size aggregate, true to line and grade, to lurence of vertical RCC post not to exceed1 (One)in 500 (Five hundred),centre to centre spacing between vertical post not to exceed 2000 mm (Two Thousand milimeter),leaving adequate space between vertical post for expansion, complete as per approved drawing sand technical specifications.including hauling/carriage of all labour equipment and materials to various locations through all modes of transportations in all leads and lifts to the entire satisfaction of the Engineer-in-Charge.
10Providing and fixing Drainage Spouts complete as per drawing and T echnical specifications, including hauling/carriage of all labour equipment and materials to various locations through all modes of transportations in all leads and lifts to the entire satisfaction of the Engineer-in-Charge.
11Providing and laying concrete Mechanically mixed and vibrated PCC M15( Fifteen)Grade leveling course below approach slab complete as per drawing and Technical specification and curing complete including the cost of form work and hauling of materials in all leads and lifts as per the entire satisfaction and direction of Engineer-in-Charge.
12Providing and filling joint sealing compound as per drawings and technical specifications with coarse sand and 6 (Six) per cent bitumen by weight including the cost of form work and hauling of materials in all leads and lifts as per the entire satisfaction and direction of Engineer-in-Charge.
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail