| 1 | Removing the existing Clean removal of lime plaster from walls as per instruction of departmental officers etc.,complete. |
| 2 | Dismantling the existing Brick stone masnory wall in Lime mortar walls under 3m height as per instruction of departmental officers etc.,complete. |
| 3 | Plastering with Lime mortar 1:1.5,12mm thick (One Lime and One and off sand) including cost and conveyance of all materials and all labour charges,curing etc,complete complying with standard specifications.The lime used should be of highly iron fortified and suitable for structural and masonry works. |
| 4 | Providing Water wash and appropriate methodology to restore the originalities of the existing Granite structures inclusive of necessary scaffolding charges, conveyance and all hire charegs for all tools and plants and clearing the site after completeion of work etc.,complete. |
| 5 | Pointing the cut stone joints with Lime Mortor1:1.5 (one part of lime and one and halfpart of sand) 20 mm deep using red and yellow oxide and including cost of special tools such as brush and watering, curing etc complete, as per standard specifications. |
| 6 | Wall surface |
| 7 | Flooring area |
| 8 | Dismantling the One course of pressed tile roof finish in cement mortaras per instruction of departmental officers etc.,complete |
| 9 | Finishing the top of roof with one course of machine pressed tiles 20cmx 20cmx20mm of approved quality laid in ;LM 1:3,(One Lime and Three Sand) 12mm thick mixed with water proofing compound of conforming to ISS 2% by weight of Lime mortar used and the joints pointed neatly to full depth of tiles with the same lime mortar mixed with red oxide and water proofing compound including curing etc.,complete complying with standard specification and as directed by the departmental officers etc, |
| 10 | Labour Charges forOld Cutstone Removing and Re-fixing theFlooring and all hire charegs for all tools and plants and clearing the site after completeion of work including pointing with lime mortar 1:1.5 and as per instruction of departmental officers etc.,complete. |
| 11 | Scaffolding charges for Vimanams andgopurams with casurina posts coconut or plamtrees wherever necessaryfor main, form work and providing with coconut keeth coverings, providing ladder arrangements, country wood plant for working, inpection etc, complete hire charges only for erection, maintainance and removing the same on completion of the work 1 sq,ft.. |
| 12 | Vimanam /Gopuram upto 15\"-0\" Height |
| 13 | Painting with multicolour (Panchavarnam)good Emulsion paints complete for the Vimanams/Gopurams, inculding costand conveyence of all materials, labour charges inculding Artist painter, working in heights, lifting of material, cost of brushes etc,complete-which including all extra for foldings-100sft, superficial area. |
| 14 | Vimanam /Gopuram upto 15\"-0\" Height |
| 15 | Scraping the old paint and Painting two coat with approved water based Exterior Emulsion over the cement plastered wall surface, ceiling and other new surface including clearing preparing the surface curingin all floors including brushes etc., complete as per specification. |
| 16 | Earth work excavation for foundation with all leads and lifts in all soils and sub-soils and to the required depth as may be directed except hard rock requiring blasting inclusive of shoring, strutting and bailing out water wherever necessary refilling the sides of foundation with excavated earth in layers of 150mm thick well consolidated, depositing the surplus earth in places shown and levelling the site with all leads and lifts etc. complete in all respects. |
| 17 | Supplying and Filling in foundation and basement etc with filling sand in layers of not exceeding more than 15 cm thick well watered, rammed and consolidated complete complying with relevant standard specification and asdirected by the departmental officers. |
| 18 | Cement concrete 1:5:10 (One of cement, five of sand and ten of HBG Jelly for foundation) using 40mm gauge hard broken granite stone jelly for foundation including dewatering if found necessary and laid in layers of not more than 15cm thick, well rammed, watered etc., complete complying with standard specification |
| 19 | Random Rubble masonry work in LM 1:5 ( One of Lime and five of sand) Using selected stones and bond stones in foundation and basement including dewatering wherever necessary proper setting, curing etc., complete in all respectscomplying with relevant standard Specifications. and asdirected by the departmental officers. |
| 20 | Supplying and erecting steel centering including necessary supports for plane surfaces for Reinforced Cement Concrete works such as column footings, column pedestals, plinth beams, grade beams, staircase steps, etc. which require only nominal strutting using mild steel sheets of size 90cm x 60cm and 10 BG stiffened with welded mild steel angles of size 25mm x 25mm x 3 mm for boarding, laid over silver oakjoists of size 10cm x 6.5cm spaced at about 75cm centre to centre or at suitable intervals etc. complete in all floors complying with standard specifcation. (Payment for centering shall be given after the concrete is laid)For Grade Beam, Plinth beams,Column Footings etc. |
| 21 | Providing and laying in position, Standardised Concrete Mix M-20 Grade in accordance with IS:456-2000, using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement content of 325 kg/m? and maximum water cement ratio of 0.55, including admixture (plasticiser / super plasticiser) in recommended proportions as per IS:9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability with about (5 cu.m.) 7730 kg. of 20mm machine crushed stone jelly and with about (3.3 cu.m.) 5156 kg. of 10-12mm machine crushed stone jelly and with about (4.79 cu.m.) 7670 kg. of sand, but excluding cost of reinforcement grill and fabricating charges, centering and shuttering and also including laying, vibrating with mechanical vibrators, finishing, curing, etc. and providing fixtures like fan clamps in the RCC floor/ roof slabs wherever necessary without claiming extra, etc., complete complying with standard specification and as directed by the departmental officers.The coarse and fine aggregates to be used should comply with the requirements of IS Standards.(No separate payment will be made by the Department for the excess usage of materials). |
| 22 | Supplying, fabricating and placing in position Mild steel or Ribbed tor steel in all size for all RCC works as per the design given including cost of steel and binding wire in all floors etc., complete complying with standard specifications.(The contratctor will have to make his own arrangements for the supply of MS plain rod / RTS rod and binding wire) |
| 23 | Brick work in limeMortor 1:2 using country brick of size 83/4\"x41/4\"x23/4\" including cost and conveyance of all materials and labour charges and all other incidental charges etc complete complying with standard specification. |
| 24 | Flooring with cut stone slab of size 600mmX600mm not less than 100mm thick with machine cut edges and top surface dressed as directed by the departmental officers including cost and conveyance of materials to site and labour charges for paving in existing sand bed and Pointing With Lime Mortor1:1.5 etc complete. |
| 25 | Supplying & fixing Teak wood temple type door including all materials, labour charges for manufacturing and fixing in position including all furniture fittings etc complete with std. Specifications |
| 26 | Painting new wood work with two coats of synthetic enamelpaint of approved quality andcolor over one coat of white primer in all floors the rate is to include cost of all materials, brushes scaffolding charges etc, complete complying with standard specifications. |
| 27 | Supplying and fixing in postition of Country wood frames incliding cost and conveyance of materials and matireals as per standard specifications. |
| 28 | Brick on edge Flooring over a bed of con -crete 100mm thick and pointed with LM 1:1.5 (one part of lime and one and halfpart of sand) conveyance of materials and matireals as per standard specifications. |
| 29 | Existing Brick on edge Flooringpointed with LM 1:1.5 (one part of lime and one and halfpart of sand) and conveyance of materials and matireals as per standard specifications. |
| 30 | Providing New sudhai vigrahams in the vimanams and Rajagopurams with galvanised iron rod reinforcement of suitable dia with binding wires wherever necessary, shaping the core with broken bricks set in Lime Mortor 1:3 finishing the same withLime Mortor 1:3 bringing to the correct shape (Lakshana) in conformift with silpa sastra inclusive of special ornaments, wiapons, peedam etc., complete and providing C.M. Nayam theervai wherever necessary. inclusive of cost and conveyance of all materials, such as cement broken bricks, and G.I. rods.binding wire all labour for working in heights, curing lifiting of materials etc., complete including cement painting 2 coats over a primary coat (one vigraham is accountable with one head, 4 hands with weapons, ornamental costumes etc., as per prathima lakshans, Vigraham height is measurable from the crown top to the bottom of foot only If peetam is pt\rovided the rate with peetam may be adopted as datailed hereunder) |
| 31 | Sudhai size above1\" 6\" upto 2\" 6\" |
| 32 | sub total |
| 33 | GST 18% |