| 1 | Earth work in excavation in foundation trenches in hard soil(Vide classification of soil item-B) and disposal of excaveted earth as obtained to a distance upto 50M including all lifts levelling, ramming the foundation trenches, removing roots of trees,shrubs all complete as per approved design,building specification and direction of E/I. |
| 2 | By mix in place method (Construction of granular sub- base by providing close graded material spreding in uniform layers with motor graded in prepared surface , mixing by mix in place method with rotavator at OMC , compacting with vibratory roller to achieve the desired density , complete as per clause 401). |
| 3 | Plain cement concrete in open foundation complete as per drawing and technical specification . (A) PCC grade M20(1:1.5:3), |
| 4 | Filling in foundation trenches and plinth in layer not exceeding 150 mm thick well watered rammed fully compact -- do --do- complete job |
| 5 | Centering and shuttering including strutting , proping etc and removal of form for foundations etc |
| 6 | CARRAIGE OF MATERIALSCEMENT |
| 7 | SAND |
| 8 | STONE CHIPS |
| 9 | STONE DUST |
| 10 | E/W in ecavation of foundation of structures as per drawing and technical specification, including setting out , construction of shoring and bracing, removal of stumps and other deleterious matter,dressing of sides and bottom and backfilling with approved material.(upto 3.00 m depth)RCD 12.01(A) ii |
| 11 | Providing and laying boulder apron on river bed for protection against scour with stone boulders weighing not less 40 kg each complete as per drawing and technical specification .(A) Boulder laid dry without wire crates.) RCD 16.01 |
| 12 | Plain/Reinforcedcementconcreteinopenfoundationcompleteasper drawing and Technical Specifications |
| 13 | Stone masonary work in cement mortar 1:3 in foundation complete as per drawing and technical specification .. |
| 14 | Stone masonry work in cement mortar in sub-structure complete as per drawing and technical specifications Clauses 702, 704, 1202 & 1203. |
| 15 | Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications |
| 16 | Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications |
| 17 | Furnishing and placing reinforced cement concrete in super structure as per drawing and technical specification. |
| 18 | ProvidingandlayingCementconcretewearingcoatM-30gradeincluding reinforcement complete as per drawing and Technical Specifications |
| 19 | Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per drawing and technical specifications |
| 20 | Providing 12 mm thick cement plaster (1:4) with clean course sand of f.m. 1.5 including screening curing with all leads and lifts of water do… doas per E/i. & 1204 |
| 21 | Providing weep holes with day grades stone filter of 53 mm to 22.4 mm size in abutment and wing wall all complete job as per specification and direction of E/I. |
| 22 | Backfillingbehindabutment,wingwallandreturnwallwithSandyMaterial complete as per drawings & technical specification Clause 1204.3.8 |
| 23 | Centerin and shuttering including strutting , proping etc and removal of form for roofs.S.O.R 5.3.17.3 |
| 24 | Carraige of materials(a) Cement |
| 25 | (b) Sand |
| 26 | © stone Chips |
| 27 | (d) Boulder |
| 28 | (e) Steel |
| 29 | E/W in ecavation of foundation of structures as per drawing and technical specification, including setting out , construction of shoring and bracing, removal of stumps and other deleterious matter,dressing of sides and bottom and backfilling with approved material.(upto 3.00 m depth)RCD 12.01 A(ii) |
| 30 | Providing and laying boulder apron on river bed for protection against scour with stone boulders weighing not less 40 kg each complete as per drawing and technical specification .(A) Boulder laid dry without wire crates.) RCD 16.01 |
| 31 | Plain/Reinforcedcementconcreteinopenfoundationcompleteasper drawing and Technical Specifications |
| 32 | Stone masonary work in cement mortar 1:3 in foundation complete as per drawing and technical specification .. |
| 33 | Stone masonry work in cement mortar in sub-structure complete as per drawing and technical specifications Clauses 702, 704, 1202 & 1203. |
| 34 | Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications |
| 35 | Providing 12 mm thick cement plaster (1:4) with clean course sand of f.m. 1.5 including screening curing with all leads and lifts of water do… doas per E/i. & 1204 |
| 36 | Providing weep holes with day grades stone filter of 53 mm to 22.4 mm size in abutment and wing wall all complete job as per specification and direction of E/I. |
| 37 | Backfillingbehindabutment,wingwallandreturnwallwithSandyMaterial complete as per drawings & technical specification Clause 1204.3.8 |
| 38 | Carraige of materials(a) Cement |
| 39 | (b) Sand |
| 40 | © stone Chips |
| 41 | (d) Boulder |
| 42 | Add Gst 18% |
| 43 | Add Gst1% |