Annual Rates Contract For Extraction, Loading, Unloading And Lowering Of Submersible Pump Sets, Vt Pump Sets, Pump Sets Of Dug Wells Along With Replacement Of Components Of Submersible Pump Set / Vt Pump Set, Submersible Cables And Allied Works At , urban-Jammu And Kashmir

Public Health Engineering Department-PHED has published Annual Rates Contract For Extraction, Loading, Unloading And Lowering Of Submersible Pump Sets, Vt Pump Sets, Pump Sets Of Dug Wells Along With Replacement Of Components Of Submersible Pump Set / Vt Pump Set, Submersible Cables And Allied Works At . Submission Date for this Tender is 25-09-2023. Loading Work Tenders in urban Jammu And Kashmir. Bidders can get complete Tender details and download the document.




Tender Notice

39496780
Annual Rates Contract For Extraction, Loading, Unloading And Lowering Of Submersible Pump Sets, Vt Pump Sets, Pump Sets Of Dug Wells Along With Replacement Of Components Of Submersible Pump Set / Vt Pump Set, Submersible Cables And Allied Works At
Open Tender
Indian
Jammu And Kashmir
urban
25-09-2023

Tender Details

Annual Rates Contract For Extraction, Loading, Unloading And Lowering Of Submersible Pump Sets, Vt Pump Sets, Pump Sets Of Dug Wells Along With Replacement Of Components Of Submersible Pump Set / Vt Pump Set, Submersible Cables And Allied Works At Various Tube Wells / Pumping Stations / Dug Wells Under The Jurisdiction Of Phe Mechanical Urban Circle Jammu- 1 Submersible Pump V4 2 Dismantling of Submersible Pump set at Workshop and checking for its replacement of damaged parts. 3 Providing and fitting of new Pump Shaft. 4 Reconditioning of Pump Shaft by way of welding, turning and polishing to the actual size, making of key way. 5 Providing and fitting of new impeller. 6 Reconditioning of impeller by way of welding, turning and polishing to the actual size. 7 Providing and fitting of new Neck Ring. 8 Providing and fitting of Shaft Sleeve. 9 Providing and fitting of Coupling with key. 10 Providing and fitting of Bowl Bush. 11 Providing and fitting of NRV Bowl. 12 Providing and fitting of Tee Bolts/per piece. 13 Providing and fitting of Motor Base Bowl. 14 Providing and fitting of Stud fasting ring with studs upper and lower and circlip lock. 15 Providing and fitting of Bowl. 16 Providing and fitting of Diffuser. 17 Reconditioning of rotor shaft by way of welding to ends, turning and polishing to the required size. 18 Providing and fitting of thrust bearing / thrust pad set 19 Providing and fitting of bush for motor bowl 20 Providing and fitting of motor bowl upper/ lower 21 Rebuilding of Broken rotor shaft. 22 Assembling of Pump and then coupling with motor with proper alignment. Testing in test pit at workshop. 23 Submersible Pump V6 24 Dismantling of Submersible Pump set at Workshop and checking for its replacement of damaged parts. 25 Providing and fitting of new Pump Shaft. 26 Reconditioning of Pump Shaft by way of welding, turning and polishing to the actual size, making of key way. 27 Providing and fitting of new impeller. 28 Reconditioning of impeller by way of welding, turning and polishing to the actual size. 29 Providing and fitting of new Neck Ring. 30 Providing and fitting of Shaft Sleeve. 31 Providing and fitting of Coupling with key. 32 Providing and fitting of Bowl Bush. 33 Providing and fitting of NRV Bowl. 34 Providing and fitting of Tee Bolts/per piece. 35 Providing and fitting of Motor Base Bowl. 36 Providing and fitting of Stud fasting ring with studs upper and lower and circlip lock. 37 Providing and fitting of Bowl. 38 Providing and fitting of Diffuser. 39 Reconditioning of rotor shaft by way of welding to ends, turning and polishing to the required size. 40 Providing and fitting of thrust bearing / thrust pad set 41 Providing and fitting of bush for motor bowl 42 Providing and fitting of motor bowl upper/ lower 43 Rebuilding of Broken rotor shaft. 44 Assembling of Pump and then coupling with motor with proper alignment. Testing in test pit at workshop. 45 Submersible Pump V8 46 Dismantling of Submersible Pump set at Workshop and checking for its replacement of damaged parts. 47 Providing and fitting of new Pump Shaft. 48 Reconditioning of Pump Shaft by way of welding, turning and polishing to the actual size, making of key way. 49 Providing and fitting of new impeller. 50 Reconditioning of impeller by way of welding, turning and polishing to the actual size. 51 Providing and fitting of new Neck Ring. 52 Providing and fitting of Shaft Sleeve. 53 Providing and fitting of Coupling with key. 54 Providing and fitting of Bowl Bush. 55 Providing and fitting of NRV Bowl. 56 Providing and fitting of Tee Bolts/per piece. 57 Providing and fitting of Motor Base Bowl. 58 Providing and fitting of Stud fasting ring with studs upper and lower and circlip lock. 59 Providing and fitting of Bowl. 60 Providing and fitting of Diffuser. 61 Reconditioning of rotor shaft by way of welding to ends, turning and polishing to the required size. 62 Providing and fitting of thrust bearing / thrust pad set 63 Providing and fitting of bush for motor bowl 64 Providing and fitting of motor bowl upper/ lower 65 Rebuilding of Broken rotor shaft. 66 Assembling of Pump and then coupling with motor with proper alignment. Testing in test pit at workshop. 67 Submersible Pump V10 68 Dismantling of Submersible Pump set at Workshop and checking for its replacement of damaged parts. 69 Providing and fitting of new Pump Shaft. 70 Reconditioning of Pump Shaft by way of welding, turning and polishing to the actual size, making of key way. 71 Providing and fitting of new impeller. 72 Reconditioning of impeller by way of welding, turning and polishing to the actual size. 73 Providing and fitting of new Neck Ring. 74 Providing and fitting of Shaft Sleeve. 75 Providing and fitting of Coupling with key. 76 Providing and fitting of Bowl Bush. 77 Providing and fitting of NRV Bowl. 78 Providing and fitting of Tee Bolts/per piece. 79 Providing and fitting of Motor Base Bowl. 80 Providing and fitting of Stud fasting ring with studs upper and lower and circlip lock. 81 Providing and fitting of Bowl. 82 Providing and fitting of Diffuser. 83 Reconditioning of rotor shaft by way of welding to ends, turning and polishing to the required size. 84 Providing and fitting of thrust bearing / thrust pad set 85 Providing and fitting of bush for motor bowl 86 Providing and fitting of motor bowl upper/ lower 87 Rebuilding of Broken rotor shaft. 88 Assembling of Pump and then coupling with motor with proper alignment. Testing in test pit at workshop. 89 VT Pump 1.80lac. GPH X 34.5 Mtr. 90 Dismantling of Pump assembly, checking of parts that needs to be reconditioned/replaced including liner assembly. 91 Providing and fitting of new VT Pump shaft. 92 Reconditioning of VT Pump shaft by way of welding, turning, polishing to the required size. Making of key ways for holding impeller and threading at one end as per thread size of the shaft coupler. 93 Reconditioning of bowl body by extracting out the damaged bowl bush, fabrication of new bush and fitting the same to the body including welding, turning and polishing to the required size. 94 Providing and fitting of new stage casing Bowl. 95 Reconditioning of Stage Casing Bowl. 96 Providing and fitting of New Suction Bowl. 97 Providing and fitting of New Discharge Bowl. 98 Providing and fitting of new body bush. 99 Providing and fitting of new impeller. 100 Reconditioning of impeller by re-metalling on damaged portion, turning, finishing and balancing. 101 Fabrication and fitting of neck ring to bowl body. 102 Providing and fitting of guide spider 103 Providing and fitting of guide spider bush 104 Providing and fitting of discharge head bolt 105 Reconditioning of guide spider 106 Providing and fitting of stuffing box 107 Reconditioning ofstuffing box 108 Reconditioning of pump body/ suction 109 Providing and fitting of impeller holding split rings. 110 Providing and fitting of stage casing bush Gun Metal 111 Providing and fitting of top shaft as per sample. 112 Providing and fitting of shaft protection sleeves. 113 Providing and fitting of shaft coupler. 114 Providing and fitting of liner shaft 115 Providing and fitting of shaft enclosing tubes. 116 Reconditioning of top shaft 117 Reconditioning of shaft enclosing tubes by way of cutting the tube from the centre and welding of both the threaded ends with superior quality welding rods and checking of its proper alignment. Then threading the both ends internally as per size of bush. 118 Providing and fitting of gun metal bush for shaft enclosing tubes. 119 Dismantling of ratchet assembly, extraction of damaged ratchet bearings, ratchet pins. Fitting of ratchet assembly after replacement of components. 120 Providing and fitting of bearing 7319. 121 Providing and fitting of bearing 16026. 122 Providing and fitting of ratchet pin 123 Reconditioning of ratchet pin 124 Providing and fitting of Top Ratchet Plate. 125 Providing and fitting of Coupling Pulley Set. 126 Providing and fitting of Coupling Bolt ( 10 mm X 75 mm) and Rubber Bush/ each. 127 Providing and fitting of Nut- Bolt ( ¾ x 3” ) / kg. 128 VT Pump 1.50lac. GPH X 45 Mtr. 129 Dismantling of Pump assembly, checking of parts that needs to be reconditioned/replaced including liner assembly. 130 Providing and fitting of new VT Pump shaft. 131 Reconditioning of VT Pump shaft by way of welding, turning, polishing to the required size. Making of key ways for holding impeller and threading at one end as per thread size of the shaft coupler. 132 Reconditioning of bowl body by extracting out the damaged bowl bush, fabrication of new bush and fitting the same to the body including welding, turning and polishing to the required size. 133 Providing and fitting of new stage casing Bowl. 134 Reconditioning of Stage Casing Bowl. 135 Providing and fitting of New Suction Bowl. 136 Providing and fitting of New Discharge Bowl. 137 Providing and fitting of new body bush. 138 Providing and fitting of new impeller. 139 Reconditioning of impeller by re-metalling on damaged portion, turning, finishing and balancing. 140 Fabrication and fitting of neck ring to bowl body. 141 Providing and fitting of guide spider 142 Providing and fitting of guide spider bush 143 Providing and fitting of discharge head bolt 144 Reconditioning of guide spider 145 Providing and fitting of stuffing box 146 Reconditioning ofstuffing box 147 Reconditioning of pump body/ suction 148 Reconditioning of Stage Casing Bowl. 149 Providing and fitting of New Suction Bowl. 150 Providing and fitting of New Discharge Bowl. 151 Providing and fitting of impeller holding split rings. 152 Providing and fitting of stage casing bush Gun Metal 153 Providing and fitting of Bottle ( cast iron ) 154 Providing and fitting of Bottle Bush G.M. 155 Providing and fitting of top shaft as per sample. 156 Providing and fitting of shaft protection sleeves. 157 Providing and fitting of shaft coupler. 158 Providing and fitting of liner shaft 159 Providing and fitting of shaft enclosing tubes. 160 Reconditioning of top shaft 161 Reconditioning of shaft enclosing tubes by way of cutting the tube from the centre and welding of both the threaded ends with superior quality welding rods and checking of its proper alignment. Then threading the both ends internally as per size of bush. 162 Providing and fitting of gun metal bush for shaft enclosing tubes. 163 Dismantling of ratchet assembly, extraction of damaged ratchet bearings, ratchet pins. Fitting of ratchet assembly after replacement of components. 164 Providing and fitting of bearing 29320M. 165 Providing and fitting of ratchet pin 166 Reconditioning of ratchet pin 167 Providing and fitting of Top Ratchet Plate. 168 Providing and fitting of Coupling Pulley Set. 169 Providing and fitting of Coupling Bolt ( 10 mm X 75 mm) and Rubber Bush/ each. 170 Providing and fitting of Nut- Bolt ( ¾ x 3” ) / kg. 171 VT Pump 0.55 lac. GPH X 30 Mtr. 172 Dismantling of Pump assembly, checking of parts that needs to be reconditioned/replaced including liner assembly. 173 Providing and fitting of new VT Pump shaft. 174 Reconditioning of VT Pump shaft by way of welding, turning, polishing to the required size. Making of key ways for holding impeller and threading at one end as per thread size of the shaft coupler. 175 Reconditioning of bowl body by extracting out the damaged bowl bush, fabrication of new bush and fitting the same to the body including welding, turning and polishing to the required size. 176 Providing and fitting of new stage casing Bowl. 177 Reconditioning of Stage Casing Bowl. 178 Providing and fitting of New Suction Bowl. 179 Providing and fitting of New Discharge Bowl. 180 Providing and fitting of new body bush. 181 Providing and fitting of new impeller. 182 Reconditioning of impeller by re-metalling on damaged portion, turning, finishing and balancing. 183 Fabrication and fitting of neck ring to bowl body. 184 Providing and fitting of guide spider 185 Providing and fitting of guide spider bush 186 Providing and fitting of discharge head bolt 187 Reconditioning of guide spider 188 Providing and fitting of stuffing box 189 Reconditioning ofstuffing box 190 Reconditioning of pump body/ suction 191 Providing and fitting of impeller holding split rings. 192 Providing and fitting of stage casing bush Gun Metal 193 Providing and fitting of Bottle ( cast iron ) 194 Providing and fitting of Bottle Bush G.M. 195 Providing and fitting of top shaft as per sample. 196 Providing and fitting of shaft protection sleeves. 197 Providing and fitting of shaft coupler. 198 Providing and fitting of liner shaft 199 Providing and fitting of shaft enclosing tubes. 200 Reconditioning of top shaft 201 Reconditioning of shaft enclosing tubes by way of cutting the tube from the centre and welding of both the threaded ends with superior quality welding rods and checking of its proper alignment. Then threading the both ends internally as per size of bush. 202 Providing and fitting of gun metal bush for shaft enclosing tubes. 203 Dismantling of ratchet assembly, extraction of damaged ratchet bearings, ratchet pins. Fitting of ratchet assembly after replacement of components. 204 Providing and fitting of bearing 7214. 205 Providing and fitting of ratchet pin 206 Reconditioning of ratchet pin 207 Providing and fitting of Top Ratchet Plate. 208 Providing and fitting of Coupling Pulley Set. 209 Providing and fitting of Coupling Bolt ( 10 mm X 75 mm) and Rubber Bush/ each. 210 Providing and fitting of Nut- Bolt ( ¾ x 3” ) / kg. 211 Column pipes/ Flanges 212 Providing and fitting of G.I column pipes of 3 mtr length having flanges at both ends:- 213 32 mm dia 214 65 mm dia 215 80 mm dia 216 100 mm dia 217 125 mm dia 218 150 mm dia 219 200 mm dia 220 Providing and fitting of M.S column pipes of 3 mtr length having flanges at both ends:- 221 32 mm dia 222 65 mm dia 223 80 mm dia 224 100 mm dia 225 125 mm dia 226 150 mm dia 227 200 mm dia 228 Fabrication and fitting of M.S flange (One end) to G.I/ M.S column pipes of following ID:- 229 32 mm dia 230 65 mm dia 231 80 mm dia 232 100 mm dia 233 125 mm dia 234 150 mm dia 235 200 mm dia 236 Providing and fitting of copper Submersible cable 3core along with Thimbles. 237 2.5 sq. mm /mtr. 238 4 sq.mm /mtr. 239 6 sq. mm /mtr. 240 10 sq. mm/mtr. 241 16 sq. mm/mtr. 242 25 sq. mm/mtr. 243 35 sq. mm/mtr. 244 50 sq. mm/mtr. 245 Providing & filling of lubricating oil (Grade 43) in ratchet per liter 246 For 2.5-inch dia to 4 inch dia column pipes when number of column pipes lies in the range of 0 to 10, Disconnecting of Power connections from starter panel, disengaging from delivery bend and extracting out Submersible Pump Set complete along with column pipes by hoisting chain pulley block at Tube well, stacking of column pipes and Submersible cable properly. 247 For 2.5 inch dia to 4 inch dia column pipes when number of column pipes lies in the range of 11 to 20, Disconnecting of Power connections from starter panel, disengaging from delivery bend and extracting out Submersible Pump Set complete along with column pipes by hoisting chain pulley block at Tube well, stacking of column pipes and Submersible cable properly. 248 For 2.5 inch dia to 4 inch dia column pipes when number of column pipes lies in the range of 21 to 30, Disconnecting of Power connections from starter panel, disengaging from delivery bend and extracting out Submersible Pump Set complete along with column pipes by hoisting chain pulley block at Tube well, stacking of column pipes and Submersible cable properly. 249 For 2.5 inch dia to 4 inch dia column pipes when number of column pipes lies in the range of 31 to 40, Disconnecting of Power connections from starter panel, disengaging from delivery bend and extracting out Submersible Pump Set complete along with column pipes by hoisting chain pulley block at Tube well, stacking of column pipes and Submersible cable properly. 250 For 2.5 inch dia to 4 inch dia column pipes when number of column pipes lies in the range of 41 and above, Disconnecting of Power connections from starter panel, disengaging from delivery bend and extracting out Submersible Pump Set complete along with column pipes by hoisting chain pulley block at Tube well, stacking of column pipes and Submersible cable properly. 251 For 5 inch dia to 8 inch dia column pipes when number of column pipes lies in the range of 0 to 10, Disconnecting of Power connections from starter panel, disengaging from delivery bend and extracting out Submersible Pump Set complete along with column pipes by hoisting chain pulley block at Tubewell, stacking of column pipes and Submersible cable properly. 252 For 5 inch dia to 8 inch dia column pipes when number of column pipes lies in the range of 11 to 20, Disconnecting of Power connections from starter panel, disengaging from delivery bend and extracting out Submersible Pump Set complete along with column pipes by hoisting chain pulley block at Tube well, stacking of column pipes and Submersible cable properly. 253 For 5 inch dia to 8 inch dia column pipes when number of column pipes lies in the range of 21 to 30, Disconnecting of Power connections from starter panel, disengaging from delivery bend and extracting out Submersible Pump Set complete along with column pipes by hoisting chain pulley block at Tube well, stacking of column pipes and Submersible cable properly. 254 For 5 inch dia to 8 inch dia column pipes when number of column pipes lies in the range of 31 to 40, Disconnecting of Power connections from starter panel, disengaging from delivery bend and extracting out Submersible Pump Set complete along with column pipes by hoisting chain pulley block at Tube well, stacking of column pipes and Submersible cable properly. 255 For 5 inch dia to 8 inch dia column pipes when number of column pipes lies in the range of 41 and above, Disconnecting of Power connections from starter panel, disengaging from delivery bend and extracting out Submersible Pump Set complete along with column pipes by hoisting chain pulley block at Tube well, stacking of column pipes and Submersible cable properly. 256 For 2.5 inch dia to 4 inch dia column pipes, Loading of Submersible Pump Set in Mechanical transport, carriage to the Workshop and unloading. In the range of 0 to 10 km. 257 For 2.5 inch dia to 4 inch diacolumn pipes, Loading of Submersible Pump Set in Mechanical transport, carriage to the Workshop and unloading. In the range of 11 Kilometer & above. 258 For 2.5 inch dia to 4 inch diacolumn pipes, Loading in Mechanical transport and carriage back to site of work and unloading at site.in the range of 0 to 10 kilometer. 259 For 2.5 inch dia to 4 inch diacolumn pipes, Loading in Mechanical transport and carriage back to site of work and unloading at site.in the range of 11 Kilometer & above. 260 For2.5 inch diato 4 inch diacolumn pipes, when number of column pipes lies in the range of 0 to 10, Making of cable connection of motor with Submersible cable after dressing cable ends properly. Making of each joint water proof. Lowering of Submersible Pump Set complete along with column pipes and submersible cable with providing & fitting of jointing material and nuts and bolts. Making of connections to the starter panel. 261 For2.5 inch diato 4 inch diacolumn pipes, when number of column pipes lies in the range of 11 to 20, Making of cable connection of motor with Submersible cable after dressing cable ends properly. Making of each joint water proof. Lowering of Submersible Pump Set complete along with column pipes and submersible cable with providing & fitting of jointing material and nuts and bolts. Making of connections to the starter panel. 262 For2.5 inch diato 4 inch diacolumn pipes, when number of column pipes lies in the range of 21 to 30, Making of cable connection of motor with Submersible cable after dressing cable ends properly. Making of each joint water proof. Lowering of Submersible Pump Set complete along with column pipes and submersible cable with providing & fitting of jointing material and nuts and bolts. Making of connections to the starter panel. 263 For2.5 inch diato 4 inch diacolumn pipes, when number of column pipes lies in the range of 31 to 40, Making of cable connection of motor with Submersible cable after dressing cable ends properly. Making of each joint water proof. Lowering of Submersible Pump Set complete along with column pipes and submersible cable with providing & fitting of jointing material and nuts and bolts. Making of connections to the starter panel. 264 For2.5 inch diato 4 inch diacolumn pipes, when number of column pipes lies in the range of 41 and above, Making of cable connection of motor with Submersible cable after dressing cable ends properly. Making of each joint water proof. Lowering of Submersible Pump Set complete along with column pipes and submersible cable with providing & fitting of jointing material and nuts and bolts. Making of connections to the starter panel. 265 For5 inch diato 8 inch dia column pipes, when number of column pipes lies in the range of 0 to 10, Making of cable connection of motor with Submersible cable after dressing cable ends properly. Making of each joint water proof. Lowering of Submersible Pump Set complete along with column pipes and submersible cable with providing & fitting of jointing material and nuts and bolts. Making of connections to the starter panel. 266 For5 inch diato 8 inch dia column pipes, when number of column pipes lies in the range of 11 to 20, Making of cable connection of motor with Submersible cable after dressing cable ends properly. Making of each joint water proof. Lowering of Submersible Pump Set complete along with column pipes and submersible cable with providing & fitting of jointing material and nuts and bolts. Making of connections to the starter panel. 267 For5 inch diato 8 inch dia column pipes, when number of column pipes lies in the range of 21 to 30, Making of cable connection of motor with Submersible cable after dressing cable ends properly. Making of each joint water proof. Lowering of Submersible Pump Set complete along with column pipes and submersible cable with providing & fitting of jointing material and nuts and bolts. Making of connections to the starter panel. 268 For5 inch diato 8 inch dia column pipes, when number of column pipes lies in the range of 31 to 40, Making of cable connection of motor with Submersible cable after dressing cable ends properly. Making of each joint water proof. Lowering of Submersible Pump Set complete along with column pipes and submersible cable with providing & fitting of jointing material and nuts and bolts. Making of connections to the starter panel. 269 For5 inch diato 8 inch dia column pipes, when number of column pipes lies in the range of 40 and above, Making of cable connection of motor with Submersible cable after dressing cable ends properly. Making of each joint water proof. Lowering of Submersible Pump Set complete along with column pipes and submersible cable with providing & fitting of jointing material and nuts and bolts. Making of connections to the starter panel. 270 For VT Pump 1.80 lac. GPH X 34.5 Mtr. Disconnecting of Power connections from starter panel, dismounting of motor using special tools and tackles, skilled man power. 271 For VT Pump 1.80 lac. GPH X 34.5 Mtr. Disengaging from delivery bend and extraction of VT Pump Set complete including liner assembly and pump assembly using special tool and tackles, skilled manpower, stacking of pump parts, cables. 272 For VT Pump 1.80 lac. GPH X 34.5 Mtr. Loading of complete pump set/motor into Mechanical Transport and carriage to workshop and unloading thereof. 273 For VT Pump 1.80 lac. GPH X 34.5 Mtr. Loading of complete pump set/ motor into Mechanical Transport and carriage from workshop and unloading at site. 274 For VT Pump 1.80 lac. GPH X 34.5 Mtr. Lowering of VT Pump Set complete including linear assembly with proper alignment, fitting of discharge head, delivery line, packing box, ratchet assembly, coupling pulley. 275 For VT Pump 1.80 lac. GPH X 34.5 Mtr. Mounting of motor using special tools, tackles and skilled labour. Coupling of motor. Making of connections with starter panel. 276 For VT Pump 1.50 lac. GPH X 45 Mtr. Disconnecting of Power connections from starter panel, dismounting of motor using special tools and tackles, skilled man power 277 For VT Pump 1.50 lac. GPH X 45 Mtr. Disengaging from delivery bend and extraction of VT Pump Set complete including liner assembly and pump assembly using special tool and tackles, skilled manpower, stacking of pump parts,cables. 278 For VT Pump 1.50 lac. GPH X 45 Mtr. Loading of complete pump set/motor into Mechanical Transport and carriage to workshop and unloading thereof. 279 For VT Pump 1.50 lac. GPH X 45 Mtr. Loading of complete pumpset/ motor into Mechanical Transport and carriage from workshop and unloading at site. 280 For VT Pump 1.50 lac. GPH X 45 Mtr. Lowering of VT Pump Set complete including linear assembly with proper alignment, fitting of discharge head, delivery line, packing box, ratchet assembly, coupling pulley. 281 For VT Pump 1.50 lac. GPH X 45 Mtr. Mounting of motor using special tools, tackles and skilled labour. Coupling ofmotor. Making of connections with starter panel. . 282 For VT Pump 0.55 lac. GPH X 30 Mtr. Disconnecting of Power connections from starter panel, dismounting of motor using special tools and tackles, skilled man power 283 For VT Pump 0.55 lac. GPH X 30 Mtr. Disengaging from delivery bend and extraction of VT Pump Set complete including liner assembly and pump assembly using special tool and tackles, skilled manpower, stacking of pump parts,cables. 284 For VT Pump 0.55 lac. GPH X 30 Mtr. Loading of complete pump set/motor into Mechanical Transport and carriage to workshop and unloading thereof. 285 For VT Pump 0.55 lac. GPH X 30 Mtr. Loading of complete pump set/ motor into Mechanical Transport and carriage from workshop and unloading at site. 286 For VT Pump 0.55 lac. GPH X 30 Mtr. Lowering of VT Pump Set complete including linear assembly with proper alignment, fitting of discharge head, delivery line, packing box, ratchet assembly, coupling pulley. 287 For VT Pump 0.55 lac. GPH X 30 Mtr. Mounting of motor using special tools, tackles and skilled labour. Coupling of motor. Making of connections with starter panel. . 288 ForDug wells, Disconnecting of Power connections from starter panel, disengaging from delivery bend and extracting outPump Set complete along with column pipes by hoisting chain pulley block. Stacking of column pipes and cable properly. 289 ForDug wells, Loading of Pump Set in Mechanical transport, carriage to the Workshop and unloading. In the range of 0 to 10 kilometer 290 ForDug wells, Loading of Pump Set in Mechanical transport, carriage to the Workshop and unloading. In the range of 11 kilometers and above. 291 For Dug wells, Loading in Mechanical transport and carriage back to site of work and unloading at site in the range of 0 to 10 kilometers. 292 For Dug wells, Loading in Mechanical transport and carriage back to site of work and unloading at site in the range of 11 kilometers and above. 293 For Dug wells, Making of cable connection of motor with cable after dressing cable ends properly. Making of each joint water proof. Lowering of Pump Set complete along with column pipes and cable with providing & fitting of jointing material and nuts and bolts. Making of connections to the starter panel.

Key Value

Document Fees
INR 2000 /-
EMD
INR 200000.0 /-
Tender Value
Refer document

BOQ Items

Name of the Work: Annual Rates Contract for Extraction, Loading, Unloading and Lowering of Submersible Pump Sets, VT Pump Sets, Pump Sets of Dug Wells along with Replacement of Components of Submersible Pump Set / VT Pump set, Submersible Cables and allied Works at various Tube Wells / PumpingStations / Dug Wells Under the jurisdiction of PHE Mechanical Urban Circle Jammu
Sl. No. Item Description
1Submersible Pump V4
2Dismantling of Submersible Pump set at Workshop and checking for its replacement of damaged parts.
3Providing and fitting of new Pump Shaft.
4Reconditioning of Pump Shaft by way of welding, turning and polishing to the actual size, making of key way.
5Providing and fitting of new impeller.
6Reconditioning of impeller by way of welding, turning and polishing to the actual size.
7Providing and fitting of new Neck Ring.
8Providing and fitting of Shaft Sleeve.
9Providing and fitting of Coupling with key.
10Providing and fitting of Bowl Bush.
11Providing and fitting of NRV Bowl.
12Providing and fitting of Tee Bolts/per piece.
13Providing and fitting of Motor Base Bowl.
14Providing and fitting of Stud fasting ring with studs upper and lower and circlip lock.
15Providing and fitting of Bowl.
16Providing and fitting of Diffuser.
17Reconditioning of rotor shaft by way of welding to ends, turning and polishing to the required size.
18Providing and fitting of thrust bearing / thrust pad set
19Providing and fitting of bush for motor bowl
20Providing and fitting of motor bowl upper/ lower
21Rebuilding of Broken rotor shaft.
22Assembling of Pump and then coupling with motor with proper alignment. Testing in test pit at workshop.
23Submersible Pump V6
24Dismantling of Submersible Pump set at Workshop and checking for its replacement of damaged parts.
25Providing and fitting of new Pump Shaft.
26Reconditioning of Pump Shaft by way of welding, turning and polishing to the actual size, making of key way.
27Providing and fitting of new impeller.
28Reconditioning of impeller by way of welding, turning and polishing to the actual size.
29Providing and fitting of new Neck Ring.
30Providing and fitting of Shaft Sleeve.
31Providing and fitting of Coupling with key.
32Providing and fitting of Bowl Bush.
33Providing and fitting of NRV Bowl.
34Providing and fitting of Tee Bolts/per piece.
35Providing and fitting of Motor Base Bowl.
36Providing and fitting of Stud fasting ring with studs upper and lower and circlip lock.
37Providing and fitting of Bowl.
38Providing and fitting of Diffuser.
39Reconditioning of rotor shaft by way of welding to ends, turning and polishing to the required size.
40Providing and fitting of thrust bearing / thrust pad set
41Providing and fitting of bush for motor bowl
42Providing and fitting of motor bowl upper/ lower
43Rebuilding of Broken rotor shaft.
44Assembling of Pump and then coupling with motor with proper alignment. Testing in test pit at workshop.
45Submersible Pump V8
46Dismantling of Submersible Pump set at Workshop and checking for its replacement of damaged parts.
47Providing and fitting of new Pump Shaft.
48Reconditioning of Pump Shaft by way of welding, turning and polishing to the actual size, making of key way.
49Providing and fitting of new impeller.
50Reconditioning of impeller by way of welding, turning and polishing to the actual size.
51Providing and fitting of new Neck Ring.
52Providing and fitting of Shaft Sleeve.
53Providing and fitting of Coupling with key.
54Providing and fitting of Bowl Bush.
55Providing and fitting of NRV Bowl.
56Providing and fitting of Tee Bolts/per piece.
57Providing and fitting of Motor Base Bowl.
58Providing and fitting of Stud fasting ring with studs upper and lower and circlip lock.
59Providing and fitting of Bowl.
60Providing and fitting of Diffuser.
61Reconditioning of rotor shaft by way of welding to ends, turning and polishing to the required size.
62Providing and fitting of thrust bearing / thrust pad set
63Providing and fitting of bush for motor bowl
64Providing and fitting of motor bowl upper/ lower
65Rebuilding of Broken rotor shaft.
66Assembling of Pump and then coupling with motor with proper alignment. Testing in test pit at workshop.
67Submersible Pump V10
68Dismantling of Submersible Pump set at Workshop and checking for its replacement of damaged parts.
69Providing and fitting of new Pump Shaft.
70Reconditioning of Pump Shaft by way of welding, turning and polishing to the actual size, making of key way.
71Providing and fitting of new impeller.
72Reconditioning of impeller by way of welding, turning and polishing to the actual size.
73Providing and fitting of new Neck Ring.
74Providing and fitting of Shaft Sleeve.
75Providing and fitting of Coupling with key.
76Providing and fitting of Bowl Bush.
77Providing and fitting of NRV Bowl.
78Providing and fitting of Tee Bolts/per piece.
79Providing and fitting of Motor Base Bowl.
80Providing and fitting of Stud fasting ring with studs upper and lower and circlip lock.
81Providing and fitting of Bowl.
82Providing and fitting of Diffuser.
83Reconditioning of rotor shaft by way of welding to ends, turning and polishing to the required size.
84Providing and fitting of thrust bearing / thrust pad set
85Providing and fitting of bush for motor bowl
86Providing and fitting of motor bowl upper/ lower
87Rebuilding of Broken rotor shaft.
88Assembling of Pump and then coupling with motor with proper alignment. Testing in test pit at workshop.
89VT Pump 1.80lac. GPH X 34.5 Mtr.
90Dismantling of Pump assembly, checking of parts that needs to be reconditioned/replaced including liner assembly.
91Providing and fitting of new VT Pump shaft.
92Reconditioning of VT Pump shaft by way of welding, turning, polishing to the required size. Making of key ways for holding impeller and threading at one end as per thread size of the shaft coupler.
93Reconditioning of bowl body by extracting out the damaged bowl bush, fabrication of new bush and fitting the same to the body including welding, turning and polishing to the required size.
94Providing and fitting of new stage casing Bowl.
95Reconditioning of Stage Casing Bowl.
96Providing and fitting of New Suction Bowl.
97Providing and fitting of New Discharge Bowl.
98Providing and fitting of new body bush.
99Providing and fitting of new impeller.
100Reconditioning of impeller by re-metalling on damaged portion, turning, finishing and balancing.
101Fabrication and fitting of neck ring to bowl body.
102Providing and fitting of guide spider
103Providing and fitting of guide spider bush
104Providing and fitting of discharge head bolt
105Reconditioning of guide spider
106Providing and fitting of stuffing box
107Reconditioning ofstuffing box
108Reconditioning of pump body/ suction
109Providing and fitting of impeller holding split rings.
110Providing and fitting of stage casing bush Gun Metal
111Providing and fitting of top shaft as per sample.
112Providing and fitting of shaft protection sleeves.
113Providing and fitting of shaft coupler.
114Providing and fitting of liner shaft
115Providing and fitting of shaft enclosing tubes.
116Reconditioning of top shaft
117Reconditioning of shaft enclosing tubes by way of cutting the tube from the centre and welding of both the threaded ends with superior quality welding rods and checking of its proper alignment. Then threading the both ends internally as per size of bush.
118Providing and fitting of gun metal bush for shaft enclosing tubes.
119Dismantling of ratchet assembly, extraction of damaged ratchet bearings, ratchet pins. Fitting of ratchet assembly after replacement of components.
120Providing and fitting of bearing 7319.
121Providing and fitting of bearing 16026.
122Providing and fitting of ratchet pin
123Reconditioning of ratchet pin
124Providing and fitting of Top Ratchet Plate.
125Providing and fitting of Coupling Pulley Set.
126Providing and fitting of Coupling Bolt ( 10 mm X 75 mm) and Rubber Bush/ each.
127Providing and fitting of Nut- Bolt ( ¾ x 3” ) / kg.
128VT Pump 1.50lac. GPH X 45 Mtr.
129Dismantling of Pump assembly, checking of parts that needs to be reconditioned/replaced including liner assembly.
130Providing and fitting of new VT Pump shaft.
131Reconditioning of VT Pump shaft by way of welding, turning, polishing to the required size. Making of key ways for holding impeller and threading at one end as per thread size of the shaft coupler.
132Reconditioning of bowl body by extracting out the damaged bowl bush, fabrication of new bush and fitting the same to the body including welding, turning and polishing to the required size.
133Providing and fitting of new stage casing Bowl.
134Reconditioning of Stage Casing Bowl.
135Providing and fitting of New Suction Bowl.
136Providing and fitting of New Discharge Bowl.
137Providing and fitting of new body bush.
138Providing and fitting of new impeller.
139Reconditioning of impeller by re-metalling on damaged portion, turning, finishing and balancing.
140Fabrication and fitting of neck ring to bowl body.
141Providing and fitting of guide spider
142Providing and fitting of guide spider bush
143Providing and fitting of discharge head bolt
144Reconditioning of guide spider
145Providing and fitting of stuffing box
146Reconditioning ofstuffing box
147Reconditioning of pump body/ suction
148Reconditioning of Stage Casing Bowl.
149Providing and fitting of New Suction Bowl.
150Providing and fitting of New Discharge Bowl.
151Providing and fitting of impeller holding split rings.
152Providing and fitting of stage casing bush Gun Metal
153Providing and fitting of Bottle ( cast iron )
154Providing and fitting of Bottle Bush G.M.
155Providing and fitting of top shaft as per sample.
156Providing and fitting of shaft protection sleeves.
157Providing and fitting of shaft coupler.
158Providing and fitting of liner shaft
159Providing and fitting of shaft enclosing tubes.
160Reconditioning of top shaft
161Reconditioning of shaft enclosing tubes by way of cutting the tube from the centre and welding of both the threaded ends with superior quality welding rods and checking of its proper alignment. Then threading the both ends internally as per size of bush.
162Providing and fitting of gun metal bush for shaft enclosing tubes.
163Dismantling of ratchet assembly, extraction of damaged ratchet bearings, ratchet pins. Fitting of ratchet assembly after replacement of components.
164Providing and fitting of bearing 29320M.
165Providing and fitting of ratchet pin
166Reconditioning of ratchet pin
167Providing and fitting of Top Ratchet Plate.
168Providing and fitting of Coupling Pulley Set.
169Providing and fitting of Coupling Bolt ( 10 mm X 75 mm) and Rubber Bush/ each.
170Providing and fitting of Nut- Bolt ( ¾ x 3” ) / kg.
171VT Pump 0.55 lac. GPH X 30 Mtr.
172Dismantling of Pump assembly, checking of parts that needs to be reconditioned/replaced including liner assembly.
173Providing and fitting of new VT Pump shaft.
174Reconditioning of VT Pump shaft by way of welding, turning, polishing to the required size. Making of key ways for holding impeller and threading at one end as per thread size of the shaft coupler.
175Reconditioning of bowl body by extracting out the damaged bowl bush, fabrication of new bush and fitting the same to the body including welding, turning and polishing to the required size.
176Providing and fitting of new stage casing Bowl.
177Reconditioning of Stage Casing Bowl.
178Providing and fitting of New Suction Bowl.
179Providing and fitting of New Discharge Bowl.
180Providing and fitting of new body bush.
181Providing and fitting of new impeller.
182Reconditioning of impeller by re-metalling on damaged portion, turning, finishing and balancing.
183Fabrication and fitting of neck ring to bowl body.
184Providing and fitting of guide spider
185Providing and fitting of guide spider bush
186Providing and fitting of discharge head bolt
187Reconditioning of guide spider
188Providing and fitting of stuffing box
189Reconditioning ofstuffing box
190Reconditioning of pump body/ suction
191Providing and fitting of impeller holding split rings.
192Providing and fitting of stage casing bush Gun Metal
193Providing and fitting of Bottle ( cast iron )
194Providing and fitting of Bottle Bush G.M.
195Providing and fitting of top shaft as per sample.
196Providing and fitting of shaft protection sleeves.
197Providing and fitting of shaft coupler.
198Providing and fitting of liner shaft
199Providing and fitting of shaft enclosing tubes.
200Reconditioning of top shaft
201Reconditioning of shaft enclosing tubes by way of cutting the tube from the centre and welding of both the threaded ends with superior quality welding rods and checking of its proper alignment. Then threading the both ends internally as per size of bush.
202Providing and fitting of gun metal bush for shaft enclosing tubes.
203Dismantling of ratchet assembly, extraction of damaged ratchet bearings, ratchet pins. Fitting of ratchet assembly after replacement of components.
204Providing and fitting of bearing 7214.
205Providing and fitting of ratchet pin
206Reconditioning of ratchet pin
207Providing and fitting of Top Ratchet Plate.
208Providing and fitting of Coupling Pulley Set.
209Providing and fitting of Coupling Bolt ( 10 mm X 75 mm) and Rubber Bush/ each.
210Providing and fitting of Nut- Bolt ( ¾ x 3” ) / kg.
211Column pipes/ Flanges
212Providing and fitting of G.I column pipes of 3 mtr length having flanges at both ends:-
21332 mm dia
21465 mm dia
21580 mm dia
216100 mm dia
217125 mm dia
218150 mm dia
219200 mm dia
220Providing and fitting of M.S column pipes of 3 mtr length having flanges at both ends:-
22132 mm dia
22265 mm dia
22380 mm dia
224100 mm dia
225125 mm dia
226150 mm dia
227200 mm dia
228Fabrication and fitting of M.S flange (One end) to G.I/ M.S column pipes of following ID:-
22932 mm dia
23065 mm dia
23180 mm dia
232100 mm dia
233125 mm dia
234150 mm dia
235200 mm dia
236Providing and fitting of copper Submersible cable 3core along with Thimbles.
2372.5 sq. mm /mtr.
2384 sq.mm /mtr.
2396 sq. mm /mtr.
24010 sq. mm/mtr.
24116 sq. mm/mtr.
24225 sq. mm/mtr.
24335 sq. mm/mtr.
24450 sq. mm/mtr.
245Providing & filling of lubricating oil (Grade 43) in ratchet per liter
246For 2.5-inch dia to 4 inch dia column pipes when number of column pipes lies in the range of 0 to 10, Disconnecting of Power connections from starter panel, disengaging from delivery bend and extracting out Submersible Pump Set complete along with column pipes by hoisting chain pulley block at Tube well, stacking of column pipes and Submersible cable properly.
247For 2.5 inch dia to 4 inch dia column pipes when number of column pipes lies in the range of 11 to 20, Disconnecting of Power connections from starter panel, disengaging from delivery bend and extracting out Submersible Pump Set complete along with column pipes by hoisting chain pulley block at Tube well, stacking of column pipes and Submersible cable properly.
248For 2.5 inch dia to 4 inch dia column pipes when number of column pipes lies in the range of 21 to 30, Disconnecting of Power connections from starter panel, disengaging from delivery bend and extracting out Submersible Pump Set complete along with column pipes by hoisting chain pulley block at Tube well, stacking of column pipes and Submersible cable properly.
249For 2.5 inch dia to 4 inch dia column pipes when number of column pipes lies in the range of 31 to 40, Disconnecting of Power connections from starter panel, disengaging from delivery bend and extracting out Submersible Pump Set complete along with column pipes by hoisting chain pulley block at Tube well, stacking of column pipes and Submersible cable properly.
250For 2.5 inch dia to 4 inch dia column pipes when number of column pipes lies in the range of 41 and above, Disconnecting of Power connections from starter panel, disengaging from delivery bend and extracting out Submersible Pump Set complete along with column pipes by hoisting chain pulley block at Tube well, stacking of column pipes and Submersible cable properly.
251For 5 inch dia to 8 inch dia column pipes when number of column pipes lies in the range of 0 to 10, Disconnecting of Power connections from starter panel, disengaging from delivery bend and extracting out Submersible Pump Set complete along with column pipes by hoisting chain pulley block at Tubewell, stacking of column pipes and Submersible cable properly.
252For 5 inch dia to 8 inch dia column pipes when number of column pipes lies in the range of 11 to 20, Disconnecting of Power connections from starter panel, disengaging from delivery bend and extracting out Submersible Pump Set complete along with column pipes by hoisting chain pulley block at Tube well, stacking of column pipes and Submersible cable properly.
253For 5 inch dia to 8 inch dia column pipes when number of column pipes lies in the range of 21 to 30, Disconnecting of Power connections from starter panel, disengaging from delivery bend and extracting out Submersible Pump Set complete along with column pipes by hoisting chain pulley block at Tube well, stacking of column pipes and Submersible cable properly.
254For 5 inch dia to 8 inch dia column pipes when number of column pipes lies in the range of 31 to 40, Disconnecting of Power connections from starter panel, disengaging from delivery bend and extracting out Submersible Pump Set complete along with column pipes by hoisting chain pulley block at Tube well, stacking of column pipes and Submersible cable properly.
255For 5 inch dia to 8 inch dia column pipes when number of column pipes lies in the range of 41 and above, Disconnecting of Power connections from starter panel, disengaging from delivery bend and extracting out Submersible Pump Set complete along with column pipes by hoisting chain pulley block at Tube well, stacking of column pipes and Submersible cable properly.
256For 2.5 inch dia to 4 inch dia column pipes, Loading of Submersible Pump Set in Mechanical transport, carriage to the Workshop and unloading. In the range of 0 to 10 km.
257For 2.5 inch dia to 4 inch diacolumn pipes, Loading of Submersible Pump Set in Mechanical transport, carriage to the Workshop and unloading. In the range of 11 Kilometer & above.
258For 2.5 inch dia to 4 inch diacolumn pipes, Loading in Mechanical transport and carriage back to site of work and unloading at site.in the range of 0 to 10 kilometer.
259For 2.5 inch dia to 4 inch diacolumn pipes, Loading in Mechanical transport and carriage back to site of work and unloading at site.in the range of 11 Kilometer & above.
260For2.5 inch diato 4 inch diacolumn pipes, when number of column pipes lies in the range of 0 to 10, Making of cable connection of motor with Submersible cable after dressing cable ends properly. Making of each joint water proof. Lowering of Submersible Pump Set complete along with column pipes and submersible cable with providing & fitting of jointing material and nuts and bolts. Making of connections to the starter panel.
261For2.5 inch diato 4 inch diacolumn pipes, when number of column pipes lies in the range of 11 to 20, Making of cable connection of motor with Submersible cable after dressing cable ends properly. Making of each joint water proof. Lowering of Submersible Pump Set complete along with column pipes and submersible cable with providing & fitting of jointing material and nuts and bolts. Making of connections to the starter panel.
262For2.5 inch diato 4 inch diacolumn pipes, when number of column pipes lies in the range of 21 to 30, Making of cable connection of motor with Submersible cable after dressing cable ends properly. Making of each joint water proof. Lowering of Submersible Pump Set complete along with column pipes and submersible cable with providing & fitting of jointing material and nuts and bolts. Making of connections to the starter panel.
263For2.5 inch diato 4 inch diacolumn pipes, when number of column pipes lies in the range of 31 to 40, Making of cable connection of motor with Submersible cable after dressing cable ends properly. Making of each joint water proof. Lowering of Submersible Pump Set complete along with column pipes and submersible cable with providing & fitting of jointing material and nuts and bolts. Making of connections to the starter panel.
264For2.5 inch diato 4 inch diacolumn pipes, when number of column pipes lies in the range of 41 and above, Making of cable connection of motor with Submersible cable after dressing cable ends properly. Making of each joint water proof. Lowering of Submersible Pump Set complete along with column pipes and submersible cable with providing & fitting of jointing material and nuts and bolts. Making of connections to the starter panel.
265For5 inch diato 8 inch dia column pipes, when number of column pipes lies in the range of 0 to 10, Making of cable connection of motor with Submersible cable after dressing cable ends properly. Making of each joint water proof. Lowering of Submersible Pump Set complete along with column pipes and submersible cable with providing & fitting of jointing material and nuts and bolts. Making of connections to the starter panel.
266For5 inch diato 8 inch dia column pipes, when number of column pipes lies in the range of 11 to 20, Making of cable connection of motor with Submersible cable after dressing cable ends properly. Making of each joint water proof. Lowering of Submersible Pump Set complete along with column pipes and submersible cable with providing & fitting of jointing material and nuts and bolts. Making of connections to the starter panel.
267For5 inch diato 8 inch dia column pipes, when number of column pipes lies in the range of 21 to 30, Making of cable connection of motor with Submersible cable after dressing cable ends properly. Making of each joint water proof. Lowering of Submersible Pump Set complete along with column pipes and submersible cable with providing & fitting of jointing material and nuts and bolts. Making of connections to the starter panel.
268For5 inch diato 8 inch dia column pipes, when number of column pipes lies in the range of 31 to 40, Making of cable connection of motor with Submersible cable after dressing cable ends properly. Making of each joint water proof. Lowering of Submersible Pump Set complete along with column pipes and submersible cable with providing & fitting of jointing material and nuts and bolts. Making of connections to the starter panel.
269For5 inch diato 8 inch dia column pipes, when number of column pipes lies in the range of 40 and above, Making of cable connection of motor with Submersible cable after dressing cable ends properly. Making of each joint water proof. Lowering of Submersible Pump Set complete along with column pipes and submersible cable with providing & fitting of jointing material and nuts and bolts. Making of connections to the starter panel.
270For VT Pump 1.80 lac. GPH X 34.5 Mtr. Disconnecting of Power connections from starter panel, dismounting of motor using special tools and tackles, skilled man power.
271For VT Pump 1.80 lac. GPH X 34.5 Mtr. Disengaging from delivery bend and extraction of VT Pump Set complete including liner assembly and pump assembly using special tool and tackles, skilled manpower, stacking of pump parts, cables.
272For VT Pump 1.80 lac. GPH X 34.5 Mtr. Loading of complete pump set/motor into Mechanical Transport and carriage to workshop and unloading thereof.
273For VT Pump 1.80 lac. GPH X 34.5 Mtr. Loading of complete pump set/ motor into Mechanical Transport and carriage from workshop and unloading at site.
274For VT Pump 1.80 lac. GPH X 34.5 Mtr. Lowering of VT Pump Set complete including linear assembly with proper alignment, fitting of discharge head, delivery line, packing box, ratchet assembly, coupling pulley.
275For VT Pump 1.80 lac. GPH X 34.5 Mtr. Mounting of motor using special tools, tackles and skilled labour. Coupling of motor. Making of connections with starter panel.
276For VT Pump 1.50 lac. GPH X 45 Mtr. Disconnecting of Power connections from starter panel, dismounting of motor using special tools and tackles, skilled man power
277For VT Pump 1.50 lac. GPH X 45 Mtr. Disengaging from delivery bend and extraction of VT Pump Set complete including liner assembly and pump assembly using special tool and tackles, skilled manpower, stacking of pump parts,cables.
278For VT Pump 1.50 lac. GPH X 45 Mtr. Loading of complete pump set/motor into Mechanical Transport and carriage to workshop and unloading thereof.
279For VT Pump 1.50 lac. GPH X 45 Mtr. Loading of complete pumpset/ motor into Mechanical Transport and carriage from workshop and unloading at site.
280For VT Pump 1.50 lac. GPH X 45 Mtr. Lowering of VT Pump Set complete including linear assembly with proper alignment, fitting of discharge head, delivery line, packing box, ratchet assembly, coupling pulley.
281For VT Pump 1.50 lac. GPH X 45 Mtr. Mounting of motor using special tools, tackles and skilled labour. Coupling ofmotor. Making of connections with starter panel. .
282For VT Pump 0.55 lac. GPH X 30 Mtr. Disconnecting of Power connections from starter panel, dismounting of motor using special tools and tackles, skilled man power
283For VT Pump 0.55 lac. GPH X 30 Mtr. Disengaging from delivery bend and extraction of VT Pump Set complete including liner assembly and pump assembly using special tool and tackles, skilled manpower, stacking of pump parts,cables.
284For VT Pump 0.55 lac. GPH X 30 Mtr. Loading of complete pump set/motor into Mechanical Transport and carriage to workshop and unloading thereof.
285For VT Pump 0.55 lac. GPH X 30 Mtr. Loading of complete pump set/ motor into Mechanical Transport and carriage from workshop and unloading at site.
286For VT Pump 0.55 lac. GPH X 30 Mtr. Lowering of VT Pump Set complete including linear assembly with proper alignment, fitting of discharge head, delivery line, packing box, ratchet assembly, coupling pulley.
287For VT Pump 0.55 lac. GPH X 30 Mtr. Mounting of motor using special tools, tackles and skilled labour. Coupling of motor. Making of connections with starter panel. .
288ForDug wells, Disconnecting of Power connections from starter panel, disengaging from delivery bend and extracting outPump Set complete along with column pipes by hoisting chain pulley block. Stacking of column pipes and cable properly.
289ForDug wells, Loading of Pump Set in Mechanical transport, carriage to the Workshop and unloading. In the range of 0 to 10 kilometer
290ForDug wells, Loading of Pump Set in Mechanical transport, carriage to the Workshop and unloading. In the range of 11 kilometers and above.
291For Dug wells, Loading in Mechanical transport and carriage back to site of work and unloading at site in the range of 0 to 10 kilometers.
292For Dug wells, Loading in Mechanical transport and carriage back to site of work and unloading at site in the range of 11 kilometers and above.
293For Dug wells, Making of cable connection of motor with cable after dressing cable ends properly. Making of each joint water proof. Lowering of Pump Set complete along with column pipes and cable with providing & fitting of jointing material and nuts and bolts. Making of connections to the starter panel.
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail