Building Construction Department-BCD has published Tender For Construction Of Fencing, Gate And Sitting Benches At Naspati Bagan, Neterhat, Jharkhand.. Submission Date for this Tender is 02-09-2023. Civil Work Tenders in latehar Jharkhand. Bidders can get complete Tender details and download the document.
Sl. No. | Item Description |
1 | Earthworkinexcavationinfoundationtrenchesinordinarysoil(vide classification of soil item - A0 and disposal of excavated earth as obtained to a distance upto 50M including all lifts levelling, ramming the foundation trenches,removingrootsoftrees,shurbsallcompleteasperapproved design, building specification and direction of E/I. |
2 | Extra for earthwork in hard soil as per specification and direction of E/I. ( vide classification of soil item-B) |
3 | Providing coarse clean Sand in Filling in foundation trenches or in plinth includingrammingandwateringinlayersnotexceeding150mmthick with all leads and liftsincludingcost of all materials, labour,royalty and taxes all complete as per building specification and direction of E/I. (Mode of measurement compacted volume). |
4 | Providing and laying in position cement concrete of specified gradeexcludingthecost ofcenteringand shuttering - All work up to plinth level : |
5 | 1:1.5:3(1 Cement : 1.5 coarse sand (zone-III) : 3gradedstone aggregate 20 mm nominal size) |
6 | 1:3:6(1Cement :3coarsesand(zone-III) :6 graded stone aggregate 20 mm nominal size) |
7 | 1:4:8(1 Cement : 4coarse sand (zone-III) : 8gradedstone aggregate 40 mm nominal size) |
8 | Centering and shuttering including strutting, propping etc. and removal of form for |
9 | Foundations, footings, bases of columns, etc. for mass concrete |
10 | Suspended floors, roofs, landings, balconies and access platform |
11 | Columns, Pillars, Piers, Abutments, Posts and Struts |
12 | Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and applying aprimingcoatofapprovedsteelprimer,includingweldingandbolted with special shaped washers etc. complete. |
13 | Fencingwithangleironpostplacedatrequireddistanceembeddedin cement concrete blocks, every 15th post, last but one end post and corner postshallbestruttedonbothsidesandendpostononesideonlyand provided with horizontal lines and two diagonals interwoven with horizontal wires, of barbed wire weighing 9.38 kg per 100 m (minimum), between the two posts fitted and fixed with G.I. staples, turn buckles etc. complete. (Cost of posts, struts, earth work and concrete work to be paid forseparately).Paymenttobemadepermetrecostoftotallengthof barbed wire used. |
14 | Carriage of material |
15 | Sand - 6 +2 km |
16 | Chips - 5Km |
17 | FILLING IN FOUNDATION TRENCHES AND PLINTH in layers not exceeding 150 mm thick wellwatered, rammed, fully compacted and fine dressed with earth obtained from excavation foundation trenches within aleadof50Mandliftof1.5Mallcompleteasper buildingspecificationanddirectionofE/I.(modeof measurement compacted volume) |
18 | Providingandlayinginpositionspecifiedgradeof reinforced cement concrete, excluding the cost of centering,shuttering,finishingandreinforcement- All work up to plinth level. |
19 | 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size) |
20 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers,abutments,postsandstrutsetc.aboveplinth level up to floor five level, excluding cost of centering, shuttering,finishingandreinforcement:1:1.5:3(1 cement:1.5coarsesand(zone-III):3gradedstone aggregate 20 mmnominal size) |
21 | ProvidingT.M.T. Reinforcementoffollowing dia Rods as perapproved designanddrawing including carriage of M.S. Rods of (Straightorin coils)to work site,cutting,bendingand binding withannealed wirewithcostofwireremoval ofrustplacingthe rodsinpositionallcompleteasper building specification and direction and direction of E/I. |
22 | 8 mm |
23 | 10 mm |
24 | 12 to 32mm |
25 | Providing 12mm cement plaster (1:6) with clean coarse sand of F.M. 1.5 including screening, curing with allleads andlifts ofwater,scaffoldingtaxes androyalty all complete as perbuildingspecification and direction of E/l. |
26 | Finishing walls with Premium Acrylic Smooth exterior paint with Silicone additives of required shade: |
27 | New work (Two or more coats applied @ 1.43 ltr/10 sqm over and including priming coat of exterior primer applied @ 2.20 kg/10 sqm) |
28 | Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steelprimer usingstructuralsteeletc.asrequired. Ingratings, frames, guard bar, ladder, railings, brackets, gates and similar works |
29 | Providing two coats of synthetic enamel paint of approved shade and make over steel surface including cleaning the surface thoroughly, scaffolding and taxes allcompleteasperbuildingspecificationand direciton of E/l |
30 | Cost of RCC Bench Gokuls lables bearing-type of material and brand name manufactureu"s name precast concrete reinforced bench (Each Bench Cost Rs. 9322.03) |
31 | Add 18 % GST (in Basic Rate must fill 12) |
32 | Add 1% Labour Cess (in Basic Rate must fill 1) |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy