Orissa Construction Corporation Limited has published Tender For Instrumentation Works Of Ghatakeswar Multipurpose Project.. Submission Date for this Tender is 31-08-2023. Miscellaneous Fasteners Tenders in ganjam Odisha. Bidders can get complete Tender details and download the document.
Sl. No. | Item Description |
1 | Supplying of Multi-Point Borehole Extensometer (MPBX)-(4 Points) Borehole Extensometers of Sensor range 150mm upto 20 meters depth including cost, conveyance, taxes & commissioning of all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
2 | Supplying of L Shape Mini Prism Targets (Range 0.3m - 600m) including cost, conveyance, taxes & commissioning of all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
3 | Supplying of Vibrating Wire Piezometer (Range 10 MPa) (in-built cables) including cost, conveyance, taxes & commissioning of all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
4 | Supplying of Up-Lift Pressure meter 10 Mpa including cost, conveyance, taxes & commissioning of all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
5 | Supplying of Concrete Stress Meter including cost, conveyance, taxes & commissioning of all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
6 | Supplying of Strain Meter Group of 9 including cost, conveyance, taxes & commissioningof all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
7 | Supplying of No Stress Strain Meter (NSSM) including cost, conveyance, taxes& commissioning of all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
8 | Supplying of VW Temperature Meter including cost, conveyance, taxes& commissioning of all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
9 | Supplying of Direct Plumbline (Automatic X-Y Co-ordinator) including cost, conveyance, taxes & commissioningof all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
10 | Supplying of Linear Joint Meter- Uniaxial including cost, conveyance, taxes & commissioningof all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
11 | Supplying of Tilt Meter including cost, conveyance, taxes & commissioningof all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
12 | Supplying of Strong Motion Accelerograph(SMA) including cost, conveyance, taxes& commissioning of all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
13 | Supplying of Realtime Monitoring Network : 6 core armoured Optical Fiber Cable 12000 meter & Laying converter OR Outdoor Wi-Fi Network can be used instead of Optical Fiber Network including cost, conveyance, taxes& commissioningof all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
14 | Supplying of Solar Pannel & Battery : Power Supply 150-watt Solar Panel, SMF Battery, Charge Controller, indoor LED light for SMA room, Backup 3 days without sunlight including cost, conveyance, taxes & commissioningof all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
15 | Supplying of Computer System including cost, conveyance, taxes & commissioningof all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
16 | Supplying of V-Notch-Mechanical including cost, conveyance, taxes& commissioning of all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
17 | Supplying of Weather Station with logger including cost, conveyance, taxes & commissioningof all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
18 | Supplying of Radar Type Water Level Recorder including cost, conveyance, taxes & commissioningof all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
19 | Supplying of Calibration Mark and Presentation Chart(Water Marking Level Scale)- 40 Meter length including cost, conveyance, taxes& commissioning of all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
20 | Supplying of VW Read Out Unit including cost, conveyance, taxes & commissioningof all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
21 | Supplying of Data Acquisition System (DAS) including cost, conveyance, taxes & commissioningof all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
22 | Supply of Accessories |
23 | Supplying of Cable Splicing Kit including cost, conveyance, taxes& commissioning of all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
24 | Supplying of Solvent for Splicing Kit including cost, conveyance, taxes& commissioning of all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
25 | Supplying of Cable termination Switch cum Junction Box including cost, conveyance, taxes & commissioningof all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
26 | Supplying of 4 Core Cable including cost, conveyance, taxes& commissioning of all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
27 | Supplying of 12 Core Cable including cost, conveyance, taxes& commissioning of all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
28 | Supplying of 20 core cable including cost, conveyance, taxes& commissioning of all materials & its components excluding GST etc. complete as per specification & direction of Engineer-in-Charge. |
29 | Providing labour for installation, instrumentation & monitoring including reading & recording & submission of report for aperiod of 12 months from the date of supply & commissioning of all the materials in complete shape as per specification& direction of Engineer-in-Charge including cost of all labour, incidental charges, labour cess etc. complete. |