Paschimanchal Vidyut Vitran Nigam Limited has published Regarding Releasing New Various Category Connection Of M / S Western Up Tolway Pvt Ltd And Nhai Care Of Sh. Ravi Kumar At Various Sites In The Area Of Edsd-I, Ii And Iii ( Daurala / Sardhana Town / Sardhana Dehat ) , Under Edd-Ii, Meerut. Under Edc-2 M. Submission Date for this Tender is 28-08-2023. Vehicle Accessories and Component Tenders in Meerut Uttar Pradesh. Bidders can get complete Tender details and download the document.
Sr No | CorrigendumDate | Corrignedum | CorrigendumType | NewSubmissionDate |
1 | 26-Aug-2023 | T93/EDC-II/MT/2023-24_dtext | Date | 28-08-2023 |
Sl. No. | Item Description |
1 | REGARDING RELEASING NEW VARIOUS CATEGORY CONNECTION |
2 | Cartage of following material from store center Meerut to JE Store including loading & unloading at both ends maximum distance up to 40 Km. :– A) PCC Pole 8.5 mrt long/ST pole 11 mtr long. |
3 | Cartage of25 KVATO 100 KVA Transformer from store centre to je Store including loading & unloading at both site |
4 | Cartage of line material from store centre to dump site & then dump site to site of work on day to day basis, including loading & unloading at both ends maximum distance up to 20 Km. (15 Qtl.) |
5 | Cartage of following material from store center Meerut to JE Store including loading & unloading at both ends maximum distance up to 40 Km. :– A) PCC Pole 8.5 mrt long/ST pole 11 mtr long. |
6 | Cartage of25 KVATO 100 KVA Transformer fromJEStore to site of work including loading & unloading at both site |
7 | Earting of each 11 KV line pople & T/F properly after drive of electrodes if size 20mmx250mm and connection the earthing point with GL wire. |
8 | Erection ofPCC pole 8.5 mtr long/STP Pole 11 mrt long after digging a pit of size 1.20 x 0.60 x 1.6 mtr in all type of Soil including back filling of the pole with proper ramming after completion of work. |
9 | Fabrication and fixing of all 11 KV H.T/L.T. line accessories. |
10 | Erection of Double/Sectionpole on PCC pole 8.5 mtr after digging of pit of required size including fabrication and fixing of Top channel, droper channel & base channel alongwith, fixing all 11 KV accessories TPMO, Fuse set 11 KV pin insulators and making connection properly. |
11 | Fabrication and fixing of Top Channel,Dropper channel Transformer base angle -Fuse set, TPMO Etc. |
12 | Mounting of25KVA to 100KVAwith proper jumping of HT side and fixing of cable on LT. side of T/F making connection properly. |
13 | Making a section pole to exist pole after fabrication & fixing of T channel fixing of all 11 KV accessories. |
14 | Erection of stay rod complete after digging a pit of size 1.20 x 0.60 x 1.6 mtr and grouting the same in block of size 0.60 x 0.60 x 0.30 mtr and nuzzling at the both ends and filling the pit with excavated earth soil with proper ramming. |
15 | Laying lifting stringing of proper sagging of ACSR weasel conductor for 3 phase, 3 wire 11 KV line including binding & jumpering properly. |
16 | Laying lifting stringing of proper sagging of ABC bunch conductor |
17 | Grouting of PCC/ST poles with Dust, Cement & Stone blast concreting. |
18 | Cutting & chopping tree branches near side of line for making the clearance between line and tree. |
19 | installation 11 kv fuse set |
20 | Providing and fixing chemical pipe earthing. |
21 | Providing and fixing stay clamps . |
22 | Providing and fixing Holding clamps . |
23 | Providing and fixing F clamps . |
24 | Providing and fixing dead and clamp . |
25 | Providing and fixing Suspension clamps . |
26 | Providing and fixing Bolt and Nuts . |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy