| 1 | Earth work in excavation by mechanical means (hydraulic excavator) in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed, within a lead of 50 metres: 2.9.1 All kinds of soil : |
| 2 | Soling and supplying of stone including costs of soling stone and carriage |
| 3 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) |
| 4 | Reinforced cement concrete work in walls (any thickness) including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts upto floor five level including curing but excluding cost of centering shuttering, finishing and reinforcement.1:1½:3 (1 cement :1½ coarse sand: 3 graded stone aggregate 20 mm nominal size) |
| 5 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level 6 Thermo-Mechanically Treated bars of grade Fe-500D or more |
| 6 | Centering and shuttering including strutting, propping etc. and removal of form work for: 4.6.1 Foundations, footings, bases for columns |
| 7 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size) |
| 8 | Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works : |
| 9 | Carriage of materials by MT from source to site of work including loading, unloading complete job: cement and steel avg lead of 125km |
| 10 | Carriage of materials by MT from source to site of work including loading, unloading complete job: sand and agg. avg. lead….......70 km |