Road Transport and Highways Government Departments Closing in 0 days TDR #39042312

Tender For Widening From Single Lane To Intermediate Lane And Strengthening At Km 7/2 - 10/0, 11/250 - 12/6, 14/8 - 15/6 Of Vilathikulam-Perunali Road Including Cd Works At Km 7/8, 7/10, 8/2, 9/6, 15/2 (Tnv 48)Road A : Widening From Single Lane To Interme

Issued by Government Departments · vilathikulam, Tamil Nadu
Tender Value
Ref. Documents
Estimated cost
Bid Submission
21 Aug 2023
0 days left
EMD
3.25 Lakhs
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online

Tender Overview

Competition Type
NCB
Bidding Type
Tender
Location / State
vilathikulam → Tamil Nadu
EMD Exemption
Not Available
Quantity
Not Available

Project Description

Widening From Single Lane To Intermediate Lane And Strengthening At Km 7 / 2 - 10 / 0, 11 / 250 - 12 / 6, 14 / 8 - 15 / 6 Of Vilathikulam-Perunali Road Including Cd Works At Km 7 / 8, 7 / 10, 8 / 2, 9 / 6, 15 / 2 ( Tnv 48 ) Road A : Widening From Single Lane To Intermediate Lane And Strengthening At Km 7 / 2 - 10 / 0, 11 / 250 - 12 / 6, 14 / 8 - 15 / 6 Of Vilathikulam-Perunali Road Including Cd Works At Km 7 / 8, 7 / 10, 8 / 2, 9 / 6, 15 / 2

BOQ

Widening from Single Lane to Intermediate Lane and Strengthening at km 7/2 - 10/0, 11/250 - 12/6, 14/8 - 15/6 of Vilathikulam-Perunali road including CD Works at Km 7/8, 7/10, 8/2, 9/6, 15/2 (TNV 48)Road A : Widening from Single Lane to Intermediate Lane and Strengthening at km 7/2 - 10/0, 11/250 - 12/6, 14/8 - 15/6 of Vilathikulam-Perunali road including CD Works at Km 7/8, 7/10, 8/2, 9/6, 15/2
Sl. No. Item Description
1Picking the existing BT surface upto 50mm depth as directed bythe departmental officers and collecting the picked up salvagedmetal and stacking the same for reuse and deposting the debris excludingcost of materials including all labour charges for picking and all othertools and plants employed of the work and including all other incidental charges etc., complete as per standard specifications as per MORTH Rev. V Clause No. 111, 112, 202
2Road A
3Earthwork excavation in all classes of soils except hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B including cost of all labour, materials tool and equipments and all other incidental charges such as baling our water,sheeting, shoring, bracing and their subsequent removal, removal and obstructions, trimming bottom of excavation backfilling and clearing the site and disposal of all surplus materials etc., indicated by the Engineer as per Box Cutting
4Road A
5Granular Sub-base with Graded Material (Table:- 400-1) - Plant Mix Method (Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 ) - for grading-V Material for widening portion.
6Road A
7Granular Sub-base with Graded Material (Table:- 400-1) - Plant Mix Method (Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 ) - for grading-IIIMaterial for widening portion.
8Road A
9Wet Mix Macadam (Table 400-13) (Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density, Complete as per clause 406) as per MORTH Rev. V Clause No. 111, 112, 406 & 900.
10Road A
11Prime Coat (Providing and applying primer coat with bitumen emulsion (SS-I type) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means as per clause 502) - over WMM/ WBM as per MORTH Rev. V Clause No. 111, 112,501,502 &900 .
12Road A
13Tack Coat- Providing and applying tack coat with bitumen emulsion (RS-I type) using emulsion pressure distributor at the rate of 0.25 kg per sqm on the prepared bituminous/granular surface cleaned with mechanical broom as per clause 503 - over granular surfaces treated with primer as per MORTH Rev. V Clause No. 111, 112,501, 503 & 900.
14Road A
15Tack Coat - Providing and applying tack coat over dry lean cement concrete surface using 3.00 Kg bitumen emulsion (RS-I type) per 10 sqm for preparatory to another bituminous construction over it including cost of material, labour charges,rentals for machinary,fuel and all other incidental charges etc.,,complete as per clause 503 of MORTH Rev. V
16Road A
17Dense Bituminous Macadam (Table - 500-10) (Providing and laying dense bituminous macadam with Hot Mix Plant using crushed aggregates of specified grading, premixed with bituminous binder (Viscosity Grade 30) at percentage specified by JMF by weight of total mix of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisherto the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No.505) Grading I
18Road A
19Bituminous Concrete (Table500-17) (Providing and laying bituminous concrete with hot mix plant using crushed aggregates of specified grading, premixed with bituminous binder(Viscosity Grade-30) at percentage specified by Job Mix Formula of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects) - Grading II as per MORTH Rev. V Clause No. 111, 112, 501, 507 & 900.
20Road A
21Excavation including removal and satisfactory disposal of all materials necessary for theconstructionof roadway and side drains in accordance with the specifications andthe lines, grades and cross sections shown in the drawings or as indicated by the Engineer.a. Formation of embankment using Box Cut Earth including compaction by Power Roller as per MORTH Rev. V Clause No. 111, 112, 301 to 305, 900
22Road A
23Excavation including removal and satisfactory disposal of all materials necessary for theconstructionof roadway and side drains in accordance with the specifications andthe lines, grades and cross sections shown in the drawings or as indicated by the Engineer.a. Formation of embankment usingCarted Earth including compaction by Power Roller as per MORTH Rev. V Clause No. 111, 112, 301 to 305, 900
24Road A
25Box Culvert
26Dismantling salvaging and removal and disposing of resulting materials and back filling the resulting trenches and pits etc.. as per MORTH Rev V Clause No.111,112 & 202 Dismantling Plain Cement Concrete
27Road A3
28Road A5
29Dismantling salvaging and removal and disposing of resulting materials and back filling the resulting trenches and pits etc.. as per MORTH Rev V Clause No.111,112 & 202 Dismantling Random Rubble Masonry
30Road A1
31Road A4
32Dismantling the existing RCC Slab and clearing away from the work site and carefully stacking the usefull materials for reuse on the road side as directed by the departmental officers including all labour and incidental charges etc.
33Road A1
34Earthwork excavation in all classes of soil except Kankar / Soft disintegrated rock not requiring blasting, medium rockand hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all labour, equipments and all incidental charges such as baling our water, providing and maintaining necessary cofferdams, sheeting, shoring bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant standard specification for FOUNDATION OF BOX CULVERT AND RETURN WALL.
35Road A1
36Road A3
37Road A4
38Road A5
39PlainCement Concrete of grade M20 Nominal Mix, 1:1.5:3 using 40mm ISS size HBG graded metal including cost and conveyance of all materials to site including cost of cementat siteincluding cost of formwork, soft water, labour charges for mixing, transporting, layingand curing concrete , working at depths , tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications, for LEVELLING COURSE OF BOX CULVERT AND RETURN WALL.
40Road A1
41Road A3
42Road A4
43Road A5
44Vibrated Reinforced Cement Concrete M25 Grade using 20mm ISS HBG metal including cost and conveyance of all materials to site, including cost and labour charges for formwork and centering, labour charges, compacting, curing, and all incidental charges etc., complete for BOTTOM SLAB OF BOX CULVERT.
45Road A1
46Road A3
47Road A4
48Road A5
49Vibrated Reinforced Cement Concrete M25 Grade using 20mm ISS HBG metal including cost and conveyance of all materials to site, including cost and labour charges for formwork and centering, labour charges, compacting, curing, and all incidental charges etc., complete for BODY WALL OF BOX CULVERT.
50Road A1
51Road A3
52Road A4
53Road A5
54Vibrated Reinforced Cement Concrete M25 Grade using 20mm ISS HBG metal including cost and conveyance of all materials to site, including cost and labour charges for formwork and centering, labour charges, compacting, curing, and all incidental charges etc., complete for TOP SLAB OF BOX CULVERT.
55Road A1
56Road A3
57Road A4
58Road A5
59Supply and fabrication of steel Grade Fe-500 / required for all RCC items of works involved in the schedule including cost of steel cost of fabrication labour charges for cleaning the bars straightening cutting bending tying grills hoisting and placing the reinforcement in position as specified in the drawings including cost of binding wire provision of spacer bars, cover blocks and all other incidental charges etc. complete as per standard specification.
60Road A1
61Road A3
62Road A4
63Road A5
64VibratedCement Concrete of grade M20 Nominal Mix, 1:1:5:3 using 40mm ISS size HBG graded metal including cost and conveyance of all materials to site including cost of cementat siteincluding cost of formwork, soft water, labour charges for mixing, transporting, layingand curing concrete and all incidental charges etc., Complete for Parapet
65Road A1
66Road A3
67Road A4
68Road A5
69VibratedCement Concrete of grade M20 Nominal Mix, 1:1:5:3 using 40mm ISS size HBG graded metal including cost and conveyance of all materials to site including cost of cementat siteincluding cost of formwork, soft water, labour charges for mixing, transporting, layingand curing concrete , working at depths , tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications, for FOOTINGS OF RETURN WALL.
70Road A1
71Road A3
72Road A4
73Road A5
74VibratedCement Concrete of grade M20 Nominal Mix, 1:1.5:3 using 40mm ISS size HBG graded metal including cost and conveyance of all materials to site including cost of cementat siteincluding cost of formwork, soft water, labour charges for mixing, transporting, layingand curing concrete , working at depths , tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications, for STEM OF RETURN WALL - BELOW SILL LEVEL
75Road A1
76Road A3
77Road A4
78Road A5
79VibratedCement Concrete of grade M20 Nominal Mix, 1:1.5:3 using 40mm ISS size HBG graded metal including cost and conveyance of all materials to site including cost of cementat siteincluding cost of formwork, soft water, labour charges for mixing, transporting, layingand curing concrete , working at depths , tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications, for STEM OF RETURN WALL - ABOVE SILL LEVEL
80Road A1
81Road A3
82Road A4
83Road A5
84Excavation including removal and satisfactory disposal of all materials necessary for the construction ofroad way and side drains inaccordance with specifications and the lines, grades and crosssections shown in the drawingsor as indicatedby the Engineer for Carted Eath with a lead of 5 km for formation of Diversion Road 95%
85Road A1
86Road A3
87Road A4
88Road A5
89Excavation including removal and satisfactory disposal of all materials necessary for the construction ofroad way and side drains inaccordance with specifications and the lines, grades and crosssections shown in the drawingsor as indicatedby the Engineer for gravel for formation of Diversion Road 97%
90Road A1
91Road A3
92Road A4
93Road A5
94Supply and hoisting of RCC NP3 class pipes of 1000mm dia standard length supplied by the Contractor at his own cost specified below confirming to IS 458 / 2003 cost of pipe as a finished workincluding all other incidental charges, testing charges, including loading and unloading, transport and delivery in good condition at work site as directed by the departmental officers etc., complete as per MORTH specication Rev. V for forming forDiversion Road
95Road A1
96Road A3
97Road A4
98Road A5
99Providing and Laying Gravel Soling for Specified thick with clean good gritty gravel over the well prepared sub grade from the approved quarry including cost and conveyence of material,laying in accordance with the requirements and specification.The materials shall be laid in one or more layers as sub - base according to the line and grade and cross action shown in the drawing or as directed by the Engineers For Diversion Road
100Road A1
101Road A3
102Road A4
103Road A5
104Sub Estimate For Pipe Culvert
105Dismantling salvaging and removal and disposing of resulting materials and back filling the resulting trenches and pits etc.. as per MORTH Rev V Clause No.111,112 & 202Dismantling existing Plain cement concrete
106Road A2
107Earth work excavation in all classes of soils excepthard rock requiring blasting and depositing on bank with all leads and liftsas per SS 20 B including cost of all labour, materials, tools, equipments and all incidental charges and sheeting, shoring and bracing and their subsequent removal of all logs, stumps and other deleterious mattter and obstructions, bottom of excavation back filling clearing up the site and disposal of all trimming of surplus materials etc. complete as per standard specification for foundation of body wall
108Road A2
109Earth work excavation in all classes of soils excepthard rock requiring blasting and depositing on bank with all leads and liftsas per SS 20 B including cost of all labour, materials, tools, equipments and all incidental charges and sheeting, shoring and bracing and their subsequent removal of all logs, stumps and other deleterious mattter and obstructions, bottom of excavation back filling clearing up the site and disposal of all trimming of surplus materials etc. complete as per standard specification for foundation ofpipes.
110Road A2
111Plain Cement Concrete M10-1:3:6 Nominal Mix using 40mm ISS HBG graded metal including cost and conveyance of all materials to site but excluding cost of cement at site including soft water, labour charges for mixing, transporting, laying and curing and compacting concrete, working at heights, hire charges for Tools and Plants and incidental Charges etc., complete as per standard specifications for Levelling course below the body Wall
112Road A2
113Vibrated Cement Concrete M20 1:1.5:3 Nominal Mix using 40mm ISS HBG graded metal including cost and conveyance of all materials to site but excluding cost of cement at site including soft water, labour charges for mixing, transporting, laying and curing and compacting concrete, working at heights, hire charges for Tools and Plants and incidental Charges etc., complete as per standard specifications for Body wall.
114Road A2
115Supply of NP3 Class 1000mm dia RCC Pipe confirming to IS 458/2003 including cost of pipe as a finished work including all other incidental charges, testing charges including loading, unloading , transport and delivery in good condition at work site etc.., complete, as directed by the Departmental Officers, as per standard Specifications.
116Road A2
117Hoisting and fixing of NP3 class 1000mm dia RCC Pipe and Collars in proper gradient including all labour charges and all other incidental charges etc.., complete as directed by the Departmental Officers, as per Standard Specifications.
118Road A2
119GRAVEL FILLING in between body wall with clean good grity gravel including cost and conveyance to the site including labour charges for filling in layers, watering, tamping under optimummoisture content to get the maximum density andall incidental charges etc. complete.
120Road A2
121Calculation of SubTotal, GST and Total Amount carried out by system automatically
122Basic cost of value put to tender as per estimate
123Add GST at 18%
124Total Value put to Tender
125Negotiated Percentage
126Final Negotiated Value
127Add GST at 18% of Final Negotiated Value
128Total Value of Contract Including 18% of GST
129Basic cost of value put to tender as per Estimate
130Quoted Rate in Figures (Total Value of Contract Including 18% of GST )

AI Tender Summary

OUR REF NO 39042312
AUTHORITY Government Departments
TENDER VALUE Ref. Documents
LAST DATE 21-08-2023
Authority
Authority Name Highways Department
Work Description Widening From Single Lane To Intermediate Lane And Strengthening At Km 7 / 2 - 10 / 0, 11 / 250 - 12 / 6, 14 / 8 - 15 / 6 Of Vilathikulam-Perunali Road Including Cd Works At Km 7 / 8, 7 / 10, 8 / 2, 9 / 6, 15 / 2 ( Tnv 48 ) Road A : Widening From Single Lane To Intermediate Lane And Strengthening At Km 7 / 2 - 10 / 0, 11 / 250 - 12 / 6, 14 / 8 - 15 / 6 Of Vilathikulam-Perunali Road Including Cd Works At Km 7 / 8, 7 / 10, 8 / 2, 9 / 6, 15 / 2
Basic Detail
Tender No TN No 17 2023 24 D1 Dated 27 07 2023
Bidding Type Tender
Location
City vilathikulam
State Tamil Nadu
Key Dates
Publish Date 08 Aug 2023
Submission Date 21 Aug 2023
Open Date 22 Aug 2023
Finance
Tender Value Ref. Documents
Tender Fee Ref. Documents
EMD 3.25 Lakhs
Exemption Not Available
Document List
e366fc82-6eee-4c8b-8c87-7ac25a4cb336.html
BOQ_425279.xls
PB.pdf
PQ.pdf
Tendernotice_1.pdf

Unlock Full AI Tender Summary

Get instant access to the complete AI-generated analysis — scope, eligibility, timeline & more.

Instant Access Secure Free
Your details are secure and used only for document delivery.

Tender Timeline

Aug 08, 2023
11:30 IST

Tender Published

Tender notice published.

Completed
Aug 21, 2023
17:00 IST

Bid Submission Deadline

Online submission via eProcurement portal.

Completed
Aug 22, 2023

Bid Opening Date

Technical bids will be opened and evaluated.

Completed

Tender Documents

Download All (ZIP) ↓
html

e366fc82-6eee-4c8b-8c87-7ac25a4cb336.html

xls

BOQ_425279.xls

pdf

PB.pdf

pdf

PQ.pdf

pdf

Tendernotice_1.pdf

Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender