| 1 | MATERIALS |
| 2 | Hardware Fittings-GI-for HT covered conductor 120 sq.mm |
| 3 | Pin Insulator 11kV Composite polymeric |
| 4 | Insulator Tie for Covered Conductor |
| 5 | Disc insulator 11 Kv composite polymeric-covered conductor |
| 6 | Covered conductor HT 70 sqmm |
| 7 | Insulation piercing connector set for covered conductor HT |
| 8 | Mid span joint set forcovered conductor HT |
| 9 | Single core outdoor termination kit for covered conductor |
| 10 | Lightning arrester 9 Kv,10 KA( Distribution class) composite polymer Housing |
| 11 | LABOUR |
| 12 | Fitting and erecting one HT A type pole in position incl. Fitting across arm,digging & back filling pit,drawing earth leads. |
| 13 | Additional rate for providing one disc set on any type of HT pole for making cut point. |
| 14 | Fitting one Additional V cross arm in existing single pole incl. Conveyance of materials. |
| 15 | Fitting one Additional 75 x 40 mm,1.8m channel cross arm in existing single pole incl.conveyance of materials. |
| 16 | Loading HT A type pole from the stacking place and unloading the same at work site ( transport by vehicle) |
| 17 | Drilling hole of various sizes on existing channel/cross arm. |
| 18 | Additional rate for refitting/redoing one disc set while renewing any type of 11 kV cut pole |
| 19 | Fitting one Additional 2.4m/3m channel cross arm ( 100x50x6mm),in existing 11 Kv DP incl.conveyance of materials. |
| 20 | Fitting one LT 2 line cross arm on HT or LT existing poles incl.fitting insulators and binding the same with LT Line. |
| 21 | Fitting one LT 4 line cross arm on HT or LT existing poles incl.fitting insulators and binding the same with LT Line. |
| 22 | Dismantling one damaged LT PSC/RCC poleafter disconnecting stays,strut etc. and stacking the same. |
| 23 | Dismantling ( without damage) one LT PSC/RCC strut pole after disconnecting stays,strut etc.and stacking the same. |
| 24 | Dismantling ( without damage) one LT PSC/RCC strut pole incl.removal of clamps and stacking. |
| 25 | Dismantling one section fuse. |
| 26 | Additional rate for refitting/redoing one shackle set and reshackling one span while renewing any type of pole. |
| 27 | Transferring LT 3ph 4/5 wire OH line to newly erected HT/LT pole and refitting all items to the new pole. |
| 28 | Dismantling and reconnecting Sph service connection from the OH line incl. Lowering down the WP portion. |
| 29 | Dismantling and reconnecting 3ph service connection from the OH line incl.lowering down the WP portion. |
| 30 | Fitting one No.Section fuse on LT line with dropping cables,crimping sockets,connecting with bolt & nut etc. |
| 31 | Dismantling one ordinary street light/CFL/LED fitting from existing pole and refitting the same on newly erected pole and reconnecting. |
| 32 | Pole numbering using printed Aluminium sheets/Painting the surface of pole with antialgal yellow paint and painting Letters with black paint as specified incl.cost of paint. |
| 33 | Providing concrete muffing ( 0.45x0.45x1.5m) inclusive of cost of all material ( as per specification). |
| 34 | Fitting and providing one HT stay for 11kV pole incl. Digging & back filling pit. |
| 35 | Stringing of one km 3 PH 11 kV line with XLPE Insulated ACSR Raccoon. |
| 36 | Dismantling ( without damage) one km 11 kV line ( 3 conductors) ,cross arm,insulators,disc,rolling the conductor and stacking. |
| 37 | Fitting one set (3 No .) 11 kV LA and giving connections excluding earthing |
| 38 | Doing straight joint on cables of sizes upto and incl. 3X185 sqmm using the cable jointing kit supplied departmentally as per specification. |
| 39 | Doing one cable end termination on cables of sizes upto and incl.3x185 sqmm using the cable jointing kit supplied departmentally. |
| 40 | Installation of insulation piercing connector for main to service line main : 25-95 sqmm, Tap: 25-95 sqmm. |
| 41 | Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 poles excluding loading & unloading |
| 42 | Providing one Coil Earth using GI earth wire,digging separate pit at standard distance away from the pole/structure & backfilling. |
| 43 | Providing one Earth using earth pipe incl. Digging & backfilling pit and supply of charcoal,salt,sand etc. |
| 44 | Fitting one set AB Switch and giving connection . |
| 45 | Fitting and erecting one HT DP using A type pole in position incl. Fitting 2 channel cross arms, digging & back filling pit,drawing earth leads. |
| 46 | Fitting and providing one strutusing HT PSC pole incl. Digging & back filling pit. |
| 47 | Loading HT PSC pole from the stacking place and unloading the same at work site( transport by vehicle). |
| 48 | Erecting one 100 KVA Transformer to existing DP and giving connections ,incl. Loading & unloading, excluding transportation |
| 49 | Fitting one additinal Fuse unit and giving connection from Transformer to fuse and DB to LT OH line. |
| 50 | Fitting 5 channel cross arms,AB switch,DO fuse,LA,HT & LT connections on existing DP,3 LT fuses. |