| 1 | Supply Part of R/R of damaged/Replacement of 11 KV HT lines G.I wire from Jassourgarh tapping to S/Stn Jassouegarh-I |
| 2 | Prov.ACSR, 6/1/3.35 mm |
| 3 | Prov. Steel Pole 9 Mtr. Long (2000mm long) |
| 4 | prov. Muff for steel tubular pole |
| 5 | Prov.Cross Arm: [Channel Iron (100x50x6 mm), Length 1270 mm (i/c tolerence of 100mm either side) x2 structure( Run Through structure (Formation Tringle) |
| 6 | Prov.Angle Iron (50x50x5 mm), Length (2x750) mm x 1 structures (Run Through structure (Formation Tringle) |
| 7 | Prov.Pole Top Bracket [MSCI:100x50x6mm-100mm] |
| 8 | Prov.11 kV Pin Insulators (Porcelain, 12 kV, 10 KN): 3 No per pole structure (Run Through structure (Formation Tringle) |
| 9 | Prov.Belt Set - MS Angle Iron: 50x50x6, Length [1800 mm x 2 No.]for Dead End Structures |
| 10 | Prov.X-Bracing Set - MS Angle Iron: 50x50x6, Length [2125 mm x2 No.] for Dead End Structures |
| 11 | Prov.X-Arm(Horizental) - MS C. Iron: 50x50x6, Length [2340 mm x2 No.]for Dead End Structures |
| 12 | Prov.Discs insulator sets on Dead End structures (comprising 1 No. Disc: ^^(Porcelain, BS, 12 kV, 90 kN) including Dead End Clamps etc.) x (3 No. conductors) x (2 No. sides)for Dead End Structures |
| 13 | prov.HT Saty Set CompleteREC No 31/1983 |
| 14 | prov.Stay Wire (7/3.15 mm) (8.0 kg Per Stay Set) |
| 15 | Prov. Full clamp |
| 16 | Prov. Half clamp |
| 17 | Prov.HT Earthing set complete |
| 18 | Prov.GO AB Switch Unit (11kV, 400A, 25 KA ) Tripple pole O/D type |
| 19 | prov.M.S.Nuts & Bolt off Sizes |
| 20 | prov.Aluminium paint |
| 21 | Erection Part of R/R of damaged/Replacement of 11 KV HT lines G.I wire from Jassourgarh tapping to S/Stn Jassouegarh-I |
| 22 | Erection of 9 mtr long ST pole i.e digging of pit, drilling of holes in poles & X-Arms, dismentlement/re-erection/erection of pole, X-Arm & Shackle insulator , filling of pit and ramming, shifting of conductor to ST pole,painting muffing, re-seting of stay/tilted poles if any complete in all respect |
| 23 | Re-seting of tilted poles |
| 24 | Re-seting of Stay sets |
| 25 | Laying, stringing, Sgging/Re-sagging of ACSR, 6/1/3.35 mmconductor&G.I wire |
| 26 | Erection ofHT stay seti.e. digging of pit, fixing of stay Rod, nozzeling and tightning |
| 27 | Erection ofHT earthing set Complete |
| 28 | Erection of G.O. switch |
| 29 | Mannual carriage of ST 9 mtr. Long poles a/w other material ( i.e. stay set, stay wire, insulators, D-Iron, cond. etc.) having average lead from road to site of work1.00 KM (Avr. Lead 2.00KM) |