| 1 | 1. Construction of Compound wall for Integrated DRDA Complex at Krishnagiri |
| 2 | Earth work excavation for foundation in all class of soils except hard rock requiring blasting including cost and conveyance of all etc.,complete |
| 3 | Cement concrete 1:4:8 Using 40mm ISS size Hand Broken granite stone Jelly for Foundation and Flooring including labour charges for mixing concrete watering and laying the concrete in layer |
| 4 | Rein forcement Cement concrete 1:1.5:3 using 20mm ISS HBG metal for all RCC item of works excluding cost of Rein forcement and fabricating charges, centering and shuttering but including curing and providing fixtures like fan clamps in the RCC floor |
| 5 | Supplying and erecting steel centering including necessary supports for plane surfaces for Reinforced Cement Concrete works such as column footings, column pedestals, plinth beams, grade beams, staircase steps, etc. which require only nominal strutting using mild steel sheets of size 90cm x 60cm and 10 BG stiffened with welded mild steel angles of size 25mm x 25mm x 3 mm for boarding, laid over silver oakjoists of size 10cm x 6.5cm spaced at about 75cm centre to centre or at suitable intervals etc. complete in all floors complying with standard specifcation. (Payment for centering shall be given after the concrete is laid) |
| 6 | Below Ground Level |
| 7 | Above Ground Level |
| 8 | Supplying and Fabricating and placing in position MS steel or Ribbed Tor Steel for all Reinforced Cement Concrete works as per the design given including cost of steel and binding wire in all floors etc,Complete complying with stanard specification. |
| 9 | Brick work in CM 1:5 mix using country bricks ground moulded of size 22 x 11 x 7cm for the following including curing etc., complete complying with standard specifications |
| 10 | Plastering with cement mortar 1:5 mixto 12 mm thick including cost and conveyance of all materials to site and all labour charges etc complete |
| 11 | Painting Two Coats Approved Plastic Emultion Paint with one coat primer over New Cement Plastered surface including cost and conveyance of materials and labour chargesetc., complete. |
| 12 | Supplyingand fixing M.S.Grill for opening corridor side ladder, Entrance Gate and Name board anglesetc., using necessary M.S. flats for inner member and outer members which should be fixed as directed by the departmental officers. |
| 13 | Painting new iron works such as steel doors, windows, ventilators, window bars, balustrades etc., with two coats of best approved first quality and colour of synthetic enamel paint over one coat of red oxide priming coat in all floors including cost of priming coat etc., complete complying with standard specification. |
| 14 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \"BB\" for all works in this package} |