| 1 | Earth work Excavation in all classes of soils such as hard stiff clay.Stiff block hard red earth, shales, murram, gravel etc., completed for foundation as SS 20B. |
| 2 | Cement Concrete 1:4:8 mix using 40mm metal including cost and conveyanceof all materials to work site and all labour |
| 3 | Cement Concrete 1:3:6 mix using 40mm ISS HBG metal including cost & conveyance of all materials to site etc complete., |
| 4 | Brick work in cement mortar 1:5 using country bricks of size 83/4\"x41/4\"x23/4\" etc., complete |
| 5 | Reinforced cement concrete 1:1.5:3 mix using 20mmISS metal including all charged |
| 6 | Supplying and Fabricating and placing in position MS steel Cutting bending &tying stanard specification. |
| 7 | Supplying and fixing of RCC ready made post f size 0.15x0.15x1.50m including all cost and conveyance and all labour charges etc.complete |
| 8 | Supplying, fabricating and placing in position of Diamond type wire mesh including cost of binding wire and labour charges etc. complete |
| 9 | Supply and fixing of centering materilas for Concrete works including cost and conveyance of all materials to site and all labour charges etc complete |
| 10 | Supply and fixing of Mild Steel grill gate using Hallow Rectangular tube Sectionof size 25 x 50 x 2.90mm including all cost and fixing charges etc complete., |
| 11 | Colour washing two coats with best quality Shell lime including cost and conveyance of all labour charges etc., complete. |
| 12 | Plastering with CM 1:5,12mm thick including curing including cost and conveyance of materials and labour chargesetc complete. |
| 13 | Paintingtwo coats over New Iron work with ready mixed approved paints |
| 14 | Earth work excavation in all classes of soil and depositing on bank with intial lead and lift in hard stiff clay gravelly soil murram shales etc complete as per SS 20B. |
| 15 | Supply of 32mm PVC Pipe including all charges |
| 16 | Labour charges of laying and jointing the 32mm pvc pipe etc complete |
| 17 | Refilling trench with excavated earth ofter laying the pipe |
| 18 | G.M. Gate valves 32 mm |
| 19 | Sub Estimate: Earth work excavation for foundation in all classes of soils and sub soil to full depthexcept in hard rock requiring blasting but inclusive of shoring struttingif required forthe sides of foundation. |
| 20 | Cement Concrete 1:3:6 mix using 40 mm HBG metal for foundaion including watering wherever necessary and laid in layers of not more than 15cm thick. Compacting etc., complete complying with standard specifications and as directed. |
| 21 | Supply and delivery of 50mm dia GI pipe 3.60mm thick including cost and conveyance and labour charges etc complete |
| 22 | Supply and delivery of MS square hollow tube section of size 25x25x2.60mmincluding cost and conveyance and labour charges etc complete |
| 23 | Providing green shadow arrangements using approved quality of Nylon net for nursery areaincluding cost and conveyancecharges etc complete |
| 24 | Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for fillingetc.complete, |
| 25 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \"BB\" for all works in this package} |