| 1 | Execution of works -(As per CPWD specifications 2021 as well as approved by the Competent authority .) |
| 2 | Erection and dismantling ofdouble scaffolding system all around boundary wall/column up to 10 meter height above ground level including additional rows of scaffolding in stepped manner as per requirement of site made with bamboo, placed 1.5m centre to centrehorizontal and vertical joint with bamboo coir string and staircase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for the execution of work and removing it thereafter. The scaffolding system shall be stiffened with the wall etc. wherever required iffeasible for inspection of work at required location with essentialsafety features for the workers including cost of material labours and T&P etccomplete as per direction of engineer in charge for the required duration as approved and removing it thereafter. Complete as per direction and approval of Engineer-in-charge |
| 3 | Provision for Repairs to Plaster of thickness 12 mm to 20 mm in Patches of area 2.5 sq. meters and under, including cutting the patch in proper shade, raking out joints and preparing and plastering the surface of the walls complete, including disposal of rubbish to the dumping ground all complete as per direction of Engineer-in-charge. with Cement Mortar 1:4 (1 cement : 4 fine sand) including materials and labour etc. Complete. |
| 4 | Provision for Dismantling and Taking out Doors, Windows and clerestory windows(steel or wood) shutter including Chowkhats, architrave. holdfasts etc complete and stacking within 50 meters lead of area 3 sq. meters and below. (Size= 2.1m X 1.2m). |
| 5 | Provision of Removing white or colour wash by scrapping and sand papering and preparing the surface smooth including necessary repairs to scratches etc. complete |
| 6 | Providing and applying white cement based putty of average thickness 1 to 2 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete. ( two coat) |
| 7 | Distempering (02 coat) with 1st quality acrylic distemper, having VOC ( Volatile Organic Compound ) content less than 50 grams/ litre, of approved brand and manufacture, including applying additional coats wherever required, to even shade and colour. |
| 8 | Provision for Painting Steel work with deluxe Multi Surface Paint to give an even shade. Two or more coat applied @ 0.90 ltr/10 sqm over an under coat of primer applied @ 0.80 ltr/10 sqm of approved brand and manufacture |
| 9 | Providing and fixing 12 nos. Door chowkat (2.1mx1.2m)existing opening including embedding chowkhats in floors of walls cutting massonry for holdfasts. embedding hold fasts in cement concrete blocks of size 15 x 10 x 10 cm with cement concrete 1:3:6 (1 cement: 3 course sand: 6 graded stone aggregate 20 mm nominal size) painting two coats of approved wood preservative to sides of chowkhats and making good the damages to walls and floors as required complete, including disposal of rubbish to the dumping ground all complete as per direction of Engineer- in- charge. |
| 10 | Providing and fixing 6nos. Window chowkat (1.2mx1m) existing opening including embedding chowkhats in floors of walls cutting massonry for holdfasts. embedding hold fasts in cement concrete blocks of size 15 x 10 x 10 cm with cement concrete 1:3:6 (1 cement :3 course sand : 6 graded stone aggregate 20 mm nominal size) painting two coats of approved wood preservative to sides of chowkhats and making good the damages to walls and floors as required complete. including disposal of rubbish to the dumping ground all complete as per direction of Engineer- in –charge. |
| 11 | Providing and Fixing 12 nos flush door (2.1mx1.2m) and 6 nos. Window (1.2mx1m) Flush Doors with decorative veneering instead of non decorative ISI marked flush door shutters conforming to IS : 2202. including materials and labour etc complete |
| 12 | Providing and Fixing precoated galvanised steel sheet roofing accessories 0.50 mm total coated thickness, zinc coating 120 gm per sqm as per IS: 277 in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns using self drilling / self tapping screws complete and including material and labour cost all complete. |
| 13 | Provision for 50 mm Cement Concrete Flooring 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate) finished with a floating coat of neat cement including cement slurry, etc all complete.) |
| 14 | Provision for Plumbing Work for Inspection room some of Water tank maintenance work, water supply Pipe line Repairing work, Toilet sanitary items and CPVC drain system Repairing work including Material and labor charge all complete. |
| 15 | Provision for Electricity Work some of Repairing of Switch boards light fitting work, Electric wire cables repairing work M.CB box etc including material and labour charge all complete.(LS) |