| 1 | Part - I (Initial Rehabilitation) |
| 2 | Excavation in foundation for retaining, breast walls etc, in all types of soils and rocks including all lead, lift and disposal of surplus material as per direction of engineer - in - charge, as per drawing and technical specifications Clause 305.1 of MORD Specifiction |
| 3 | Construction of R.R. stone masonary laid dryexcluding bond stones, supply of all materials, labour,T&P & Royalty etc.required for propercompletion of workasdirected by Engineer-in-chargeMORD Specification for Rural Roads 2014. |
| 4 | Hand Packed stone filling in back of wallls including cost of all materials, royality, T&P etc. complete as per direction of Engineer-in- charge. (As per PWD Uttarakhand specifications) |
| 5 | Providing concrete for plain/ reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203R.C.C. grade M 25 |
| 6 | Cement plum Masonry with 40% plum & 60% 1:3:6 cement concrete including supply of all material, labour, T&P etc. required for proper completion of the work. As per drawings and technical specifications Clause 802, 803, 1202 & 1203 of MORD Specifiction |
| 7 | Patch repair on already filled pot holes with 75 mm BM with 20 mm premix carpet and seal coat Type B as per drawings and technical specification Clause 1904.2 |
| 8 | Part - II (Routine Maintenance) |
| 9 | Maintenance Activities: |
| 10 | Emergency Maintenance |
| 11 | Deploying Hydraulic Excavators of 0.90 cum Bucket for clearance of major slip in all type of Soil, Rock and Boulders includingits Operator, Fuel, all other charge and taxes required for proper completion of work. |
| 12 | Year 3 |
| 13 | Year 4 |
| 14 | Year 5 |
| 15 | Major Slip clearance in all type of Soil, Rock and Bouldersincluding cast of all material , Machine, T&P and Taxes etc required for proper completion of work as per MoRD specifications, Clause 1611 |
| 16 | Year 3 |
| 17 | Year 4 |
| 18 | Year 5 |
| 19 | Coolie walling including supply of all material, labour, T&P , royalty etc. required for proper completion of the work , asdirected by Engineer-in-charge and as per PWD specifications 8.90 (For Opening Communication Only) |
| 20 | Year 3 |
| 21 | Year 4 |
| 22 | Year 5 |
| 23 | Providing and laying of boulder apron laid in wire crates with 4 mm dia GI wire (@ 32 Kg/ 10 Sqm) conforming to IS:280 and IS:4826 in 100 mm x 100 mm mesh (woven diagonally) including 10 per cent extra for laps and joints laid with stone boulders weighing not less than 25 kg each as per drawing and technical specifications Clause 1301 |
| 24 | Year 3 |
| 25 | Year 4 |
| 26 | Year 5 |
| 27 | PBMC |
| 28 | Maintenance under PBMC for 1] Trimming of grass and weeds from the shoulders/berms and disposing off the same to suitable locations as per technical specifications Clause 1914.2] Maintenance of road side drain including minor slip clearance, reshaping, deepening and regrading as well as catch water drains as per technical specification Clause 19073] Maintenance of shoulder to the required level by filling/cutting the soil and its compaction including disposal of the surplus material in approved muck disposal points as per specification clause 1903.4] Maintenance of scupper & culvert by way of clearing, cleaning, Erosion repair, repairs to cracks, parapet walls andprotection works as per drawing and technical specification clause 1908.5] Maintenance of Causeway by way of minor Surface repairs, replacing Guide Posts, repair of flood gauges, removal of debris, providing boulders and protection work and painting as per technical specification Clause 1909.6] Maintenance of road signs by way of cleaning and repainting of mandatory / requlatory / cautionary / informatory and place dentifications sign board as perdrawings and technical specification Clause 1910.7]Maintenance of 200 metre km stone by way of refiting of tilted stones repairing with cement mortar, cleaning, repairing and lettering on 200 metre km stone and 5th km stone as per drawing and technical specification Clause 1912.8] Repairing of pot holes by removal of loose material, trimming of sides, cleaning of surface by providing tack coat with bitumen emulsion, 20 mm thick pre-mix carpet using catonic bitumen emulsion and seal coat type B with bitumen emulsion. [in 3rd & 5th Year]9] Two coat White washing on parapet walls of CD work, edge stones, tree trunks and prominent rock patcheson hill sides including preparation of surface by cleaning, scraping etc. as per technical specifications clause 191 |
| 29 | 3rd year |
| 30 | 4th year |
| 31 | 5th year |