Name of Work : Construction of Compound wall to Vacant land ( Ward No : A Block No : 2 , TS No : 2/11)at Periya Manthai in Rajapalayam Municipality Estimate : 19.50 Lakhs
Sl. No.
Item Description
1
Earth work excavation for foundation in all kinds of soils and sub soils to full depth as directed by the departmental officers except hard rockinclusive of shoring strutting and balling out water wherever necessary and refilling the sides of foundation
2
Plain cement concrete in mix 1:4:8 ( One cement ,Three sand and six aggregate) using 20mm BSS HBG metal including cost and conveyance of all materials to work site and labour charges, etc complete as per the standard specification
3
Suppling and fabricating and placing in position MS(or) R.T.S. bar for reinforcement to all RCC works as per the design given including cost ofsteel and binding wire also in all floors.
4
Supplying and Erecting Steel Centering for sides andsoffits includingwith out supports and struttingfor planesurfaces such as , Bed blocks,including cost and conveyance of all materials to work site and labour charges, etc complete as per the standard specification
5
Grade beam & Footing sides
6
Column
7
Providing and laying in position Standardised Concrete Mix M-20 Grade in accordance with IS 456 - 2000 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement contenet of 325Kg/ cum and maximum water cement ratio of 0.55 including admixture (Plasticiser / super plasticiser) in recommended proportions as per IS 9103 to accelerate, related setting of concrete, improve workability without imparing strength and durability with about (5.0cum), 7730Kg of 20mm machine crushed stone jelly and with about (3.3 cum), 5156kg of 10 - 12mm machine crushed stone jelly and with about (4.79cum) 7670 kg of Crushed Stone Sand (M- Sand), but excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary without claiming extra cost etc., complete complying with standard specification and as directed by the departmental officers -
8
Brick Work in CM 1:5 (One part of cement & five parts of sand) mix using Third Class Country Brick Kiln Burnt bricks 8 ¾ \" x 4 ¼ \" x 2 ¾\" including cost and conveyance of materialsto work site and including all labour charges for mixing, laying, curing the concrete etc., complete as per standard specifications and as directed by departmental Engineers – TNBP No:31
9
Plastering with CM 1:5(One part of cement & five parts of sand) mix for 12mm thick including cost and conveyance of all materialsto work site and including all labour charges for mixing, laying, curing,finishing etc., complete as per standard specifications and as directed by departmental Engineers – TNBP No:56&57
10
Painting 2 coats with approved cement paint over cement plastered wall surface, ceiling and other new surface and including cleaning, preparing the surface and curing etc., complete.
We takes all possible care for accurate & authentic tender information, however Users
are requested to refer Original source of Tender Notice / Tender Document published by
Tender Issuing Agency before taking any call regarding this tender.