| 1 | Cost and supply of good quality Granite stone of size (45cms to 75cms-L) x (45 cms to 50 cms- W) x (Thickness 35 cms to 40cms) to match with the existing structure including loading, unloading, transportation and stacking charges etc. complete and as directed by the site in charge of work. |
| 2 | Cost and supply of River Sand including loading, unloading, transportation and stacking charges etc. complete and as directed by the site in charge of work. |
| 3 | Cost and supply of good quality Unslaked Lime free from dust packing with air tight bags including loading, unloading, transportation and stacking charges etc. complete and as directed by the site in charge of work. |
| 4 | Cost and Supply of good quality Gallnut to the site etc., complete and as directed by the site in-charge of work |
| 5 | Cost and Supply of good quality Jaggery to the site etc., complete and as directed by the site in-charge of work. |
| 6 | Cost and Supply of good quality Treegum/Herbal ingredients including loading unloading, transportation and neatly stacking at site etc. complete and as directed by the site in-charge of work. |
| 7 | Cost and Supply of good quality stone boulders of size not lessthan 225mm including loading unloading, transportation and neatly stacking at site etc. complete and as directed by the site in-charge of work.. |
| 8 | Cost and Supply of good quality 20mm Brick Aggregate including loading, unloading, transportation and neatly stacking at the site etc., complete and as directed by the site in-charge of work. |
| 9 | Cost and Supply of good quality Rough Granite stone (90 to120cm of length, 45 to 60cm of width with a thickness Not less than 10cm) including loading, unloading, transportation and neatly stacking at the site etc., complete and as directed by the site in-charge of work. |
| 10 | Cost and Supply of good quality Chisel rod 25 mm dia to the site etc., complete and as directed by the site in-charge of work |
| 11 | Cost and Supply of good quality Charcoal to the site etc., complete and as directed by the site in-charge of work. |
| 12 | Earth work excavation for foundation in hard rock including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m complete and as directed by the sitein-charge of work. |
| 13 | Laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level: 1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources: 8 graded stone aggregate 40 mm nominal size derived from natural sources) including including cost and conveyance of all materials and labour charges, laying, curing etc complete and as directed by the site in-charge of work. |
| 14 | Construction of Random rubble masonry with hard stone in foundation with Cement mortar 1:6 (1 cement: 6 coarse sand) including cost and conveyance of all materials and labour charges curing etc., complete and as directed by the site in-charge of work. |
| 15 | Construction of Coursed rubble masonry with hard stone (first or second sort) in superstructure above plinth level in cement mortar 1:6 (1 cement: 6 coarse sand) including all taxes etc., complete and as directed by the site in-charge of work. |
| 16 | Pointing to CR stone dwarf wall with cement mortar 1:2 including cost and conveyance of all materials and labour charges etc complete and as directed by the site in charge of work. |
| 17 | Providing MS Grill fencing by using 50X50X6mm. \"L\" Angle, 20 mm vertical square bars at 20 cm c/c @equal intervals.Flower design with MS flat of size 20X5mm as per the enclosed drawing and fixing the grill in position with Cement Concrete 1:4:8, including digging pit of size 0.15 X 0.15 X 0.30 m. in Existing RR Masonry, painting to the grill etc. including cost of all materials, Labour charges and conveyance etc. complete. |
| 18 | PCC (1:2:4) using 20mm HBG metal forcoping over dwarf wall including cost, conveyance of all materials, labor charges, GST etc. complete and as directed by the site in charge of work. |
| 19 | Supply and fixing of the 2 Nos of mild steel grill gates of size 4.00 x 1.50m to the dwarf wall (with L-angle frame of size 50x50x6mm all-round, MS flat of size 40x5mm in the centre; 12mm square bars at 10cm c/c as per the enclosed drawing) including cost and conveyance of all required materials, all labour charges, cutting of mild steel angles and bars in to required sizes, assembling, welding, conveyance by head loads to the work spot and dressing, fixing in position over the dwarf wall to work spot from the main access road |