Tender For Dismantling Transporting Fitting Of 300 M Head 500 Gpm Pump With 190Kw Motor With All Valves Bends And Pipe From Plus10l23ad To 23Cd Plus10l Rerouting Of Pipeline For 180 M And Establish Pump Plus10l23ad Shift Pmp Plus10l23d To Plus12l23ad
Tender Value
5.01 Lakhs
Estimated cost
Bid Submission
14 Jul 2023
0 days left
EMD
6300
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
jhanjra → West Bengal
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Dismantling Transporting Fitting Of 300 M Head 500 Gpm Pump With 190Kw Motor With All Valves Bends And Pipe From Plus10l23ad To 23Cd Plus10l Rerouting Of Pipeline For 180 M And Establish Pump Plus10l23ad Shift Pmp Plus10l23d To Plus12l23ad In Seven
BOQ
| Sl. No. | Item Description |
| 1 | Dismantling, transporting and fitting of One no. 300 mtr head 500 GPM pump with 190 KW motor with all valves and bends and pipe from about +10L/23AD to +10L/23CD partly manually and partly by MUV at MIC,JPC |
| 2 | Dismantling and Transport of one PUMP 300m head,500 GPM,10 stage, 10 nos 6\" pipes from +10L/23ADip to 23CD/+10L by partly manually dragging on the floor and then by MUV, placing of base frame and grouting with floor bolts and alignment, shifting of 6.6KV starter, re-routing and extension of 70sqmm 6.6KV cable from+1OL/23ADip to +10L/23CD manually and partly by MUV and hanging the cable. |
| 3 | 8 nos. 6 inch suction pipe, one no. each 6\" sluice valve, foot valve fitting matching supporting with empty drums. (Fitting 4 nos 6 inch suction pipe initially and remaining 4 nos pipes( 2 no in each shift) as dewatering continues. |
| 4 | Fabrication, transporting and fitting of bends and pipe from surface to +6L/23CD through MUV for rerouting of existing pipeline from 23CD/+6L to 23D/+6L and also dismantling of existing pIpeline from 23CD/+6L to 23CD/+10L and fitting them from 23D/+6L to 23D/+10L, at MICJPC |
| 5 | Fabrication of 10(ten) nos. 90 degree bend, 08(Eight) nos. short piece for two nos. 6\" goal post, four turning, at surface |
| 6 | Rerouting, Laying and hanging of 6.6KV grade cables(270m approx.) from 23AD/+3L sub station which went originally through 23CD to 23D/+9L RVI Seam. |
| 7 | 30 nos. 6 inch pipe transport from surface to 23CD/+6L by MUV. |
| 8 | Dismantling of 30 nos of 6 inch size pipes from 23CD/+6L to 23CD/+11L and transporting them to 23D/+6L |
| 9 | Laying and fitting of 30 nos of 6 inch size pipes from 23D/+6L to 23D/+10L |
| 10 | Laying, fitting and matching of 15 nos. 6\" pipe, along 23CD/+6L to 23D/+6L and matching with existing pipeline of bore hole for delivery( 15 nos. will be done in one shift) |
| 11 | Fitting of 60 nos. flanges and welding at surface. |
| 12 | Fitting of one nos Goalpost at 23D/+10L, after transporting of 4 nos fabricated bends and 2 nos shortpiece. It requires gas cutting for matching the goalpost with existing pipeline. |
| 13 | Making nessecary arrangements for loading water in empty pipes(4 inch size) on suction side and pump (for purpose of primming in case the whole delivery side pipes becomes empty of water) from 25D pump, 23D pump(90m head), spray pipe line for manrider |
| 14 | Dismantling, transporting and fitting of One no. 300 mtr head 500 GPM pump with 190 KW mnotor with all valves and bends and pipe from about +10L/23D to +12L/23AD manually at MIC,JPC |
| 15 | Dismantling and Transport of one PUMP 300m head,500 GPM,10 stage, 10 nos 6\" pipes from +10L/23 Dip to about 12 mtrs by partly manually dragging on the floor, placing of base frame and grouting with floor bolts and alignment, shifting of 6.6KV starter, re-routing and extension of 70sqmm 6.6KV cable from+10L/23 Dip to about 12 mtrs manually and hanging the cable. |
| 16 | 8 nos. 6 inch suction pipe, one no. each 6\" sluice valve, foot valve fitting matching supporting with empty drums. (Fitting 4 nos 6 inch suction pipe initially and remaining 4 nos pipes(2 no in each shift) as dewatering continues. |
| 17 | Similarly dismantling, transporting and fitting of One no. 300 mtr head 500 GPM pump with 19O KW motor with all valves and bends and pipe from site (+10L/23D to about 12mtrs ) to +12L/23D in six more times by shifting manually at MIC,JPC. |
| 18 | Supply of Materials. |
| 19 | Supply ofOxygen Cylinder |
| 20 | Supply of DA cylinder |
| 21 | Supply of welding electrode |
| 22 | Supply of M.S. FLANGE (6\" size) |
| 23 | Supply of M.S. NUT AND BOLT (SIZE MS5/8\" X 2\") |
| 24 | Total impact of GST for the purpose of CTC |
AI Tender Summary
Tender Timeline
Jul 03, 2023
11:30 IST
Tender Published
Tender notice published.
CompletedJul 14, 2023
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
CompletedJul 15, 2023
Bid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender