| 1 | Earth work in excavation of foundation of structures in all kinds of soil as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. as per clause 304 of MORTH specification for Road and Bridge works (5th revision)and as directed by the Engineer in charge |
| 2 | Supplying & Filling in foundation and plinth with good quality river sand including watering ramming with cost,conveyance,royalties,taxes of all materials and cost of all labour on finished compacted section) as per specification and direction of Engineer-in -Charge. |
| 3 | Filling Foundation & Plinth with excavated earth a including laying the earth in layers not exceeding 23.5(9\") thick ramming and watering with all leads and lifts including cost of all labour,T&P etc. complete as directed by the Engineer-in-charge |
| 4 | Supplying, Providing & laying Plain cement concrete (1:3:6) grade (cast-in-situ) in nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days as levelling course as per drawing and technical specification section 1000, 1500 & 2100 of MORTH specification for Road & Bridge works (5th revision)as directed by Engineer in charge |
| 5 | Providing ,Lifting ,Hoisting & Laying Reinforced Cement Concrete of M-20 Grade in all type of Concrete works of approved designs and drawings having awashed sharp river sand for morter and 10mm to 20mm. size black hard crusher broken granite stone chip of approved quality from approved quarry,washed and cleaned to be mixed in concrete mixture with approved quality of cement including hoisting,lowering ,laying and compacting concrete by using vibrators,watering and curing for 28 days excluding cost of required steel centering and shuttering there after including cost,conveyance, loading ,unloading ,stacking,royalties of all materials ,cost of all labours,scaffolding,sundries,T&P required for the work etc. complete in all respect but the excluding cost & conveyance of M.S road or Tor steel and binding wires and tying the grills and placing in proper position excluding GST as directed by Engineer in charge. |
| 6 | Supplying, straightening, cutting, bending, placing in position and tying the grills of HYSD steel reinforcementFe 500 conforming to IS-1786, 2008 in position binding with galvanized binding works of 18 gauge complete for all RCC works in as per working drawing and technical specification section 1000,1500,1600, 2300 of MORTH specification for Road & Bridge works (5th revision) as directed by Engineer in charge. |
| 7 | Rigid and smooth Steel centering and shuttering at all heights of bridge work such as well curb, well steining, well cap, pier and abutment shaft, pier and abutment cap, wing wall, tie beam,slab,beam,girder, road kerb and dirt wall using required nos of vertical and horizontal supports of scaffolding with joists, N.G. rails and channels and steel shutering plates including welding, bolting,cost, conveyance , royalty and all other , of all materials and cost of scaffolding gangway etc. including cost of conveyance of dismantling and disposing debris clear of work site complete to receive reinforcement grills and concrete as per requirement as directed by Engineer-in-Charge |
| 8 | Providing & laying moorum sand admixture on either side of the road embankment / berms, laying in layers and compacting by 8-10 TonnePRR including cost & conveyance , all taxes, royalities, all labour, T&P, sundries, hire charges of PRR etc. all complete as per the direction of Engineer in Charge. |
| 9 | GST as applicable Will be Paid Extra. |