Tender For Ca No Cwe Sgnr Token-18 Of 2023-24Provn Of Electric Smart Prpaid Meter And Server Alongwith Allied Items At Military Station Abohar And Fazilka, abohar-Punjab

Military Engineer Services-MES has published Tender For Ca No Cwe Sgnr Token-18 Of 2023-24Provn Of Electric Smart Prpaid Meter And Server Alongwith Allied Items At Military Station Abohar And Fazilka. Submission Date for this Tender is 20-07-2023. Electrical Meter Tenders in abohar Punjab. Bidders can get complete Tender details and download the document.




Tender Notice

38306031
Corrigendum : Tender For Ca No Cwe Sgnr Token-18 Of 2023-24Provn Of Electric Smart Prpaid Meter And Server Alongwith Allied Items At Military Station Abohar And Fazilka
Open Tender
Indian
Punjab
abohar
20-07-2023

Tender Details

Ca No Cwe Sgnr Token-18 Of 2023-24Provn Of Electric Smart Prpaid Meter And Server Alongwith Allied Items At Military Station Abohar And Fazilka

Corrigendum Details

Sr No CorrigendumDate Corrignedum CorrigendumType NewSubmissionDate
1 13-Jul-2023 Bid Auto Extn Corrigendum Bid Auto Extn Corrigendum 20-07-2023

Key Value

Document Fees
INR 1000 /-
EMD
INR 184000.0 /-
Tender Value
Refer document

BOQ Items

Name of Work: PROVN OF ELECTRIC SMART PRPAID METER AND SERVER ALONGWITH ALLIED ITEMS AT MILITARY STATION ABOHAR AND FAZILKA
Sl. No. Item Description
1Supply and Installation of Smart Single Phase Meter with the following specifications: • AC Single Phase two Wire, Tamper Proof, Static Meter of Class 1.0, 240 V, 50 Hz, 10A-60A conforming to IS-16444 and relevant IEC standards with inbuilt 865-867 MHz Radio Frequency communication facility with self healing Mesh network with default and on demand display, billing data generation facility, anti-tamperfeatures, Microprocessor and LED/LCD based circuitry.. • Meter Should support the following data : 30 min instantaneous data for voltage, current, power factor, power, cumulative energy and frequency, 30 load survey data for energy, monthly billing survey for Cumulative Energy and Max Demand • Meter should have connect / disconnect functionality operable from prepaid billing software Electric supply will be disconnected under followingcondition.(a)Over Current (105 % of Max current in any phase (b) Load control limit (Programmable) (c) Disconnection signal from utility control centre (d) The meter shall confirms requirements specified in IS-15959. (e) All meters should be connected/ Integrated with their respective Data control units and approved softwares/ servers. • The meter should support open communication protocol DLMSwith the software MAKE: Secure, L&T, HPL Note: The contractor would be responsible from removing the existing meter, noting down the reading and depositing it with the MES.
2(b) It would be possible to run the meter in both prepaid and postpaid mode (c) The meters to carry 05 year guarantee. The contractorshall furnish 05 (Five) years replacement guarantee for prepaid meters installed under this contract except damage from water and fire. (d) Whole work shall be executed through Origional Equipment Manufacturer (OEM) or its authorised repersentative. (e) Contractor will submit necessary MoU on Rs 100 stamp paper with OEM/Authorized rep (Who will provide all these facility mentioned above before commencement of work) (f)The contractor should maintain reserve stock of 3% of total meter installed and replace the faulty meter within one week of complaint given to him.Otherwise penal recovery of Rs 100/day/meter will be recovered from the contractor. (g) Meter should be compliant to IS16444. Data exchange protocol used should be as per IS 15959 (2011).(h) Meter manufacturer should share LLS Key & HLS Key of each meter. (j)Thesmart meter should be RF enabled, the buyer has to insist during purchase (in specs) that their MDAS can be exchanged with other third- party billing systems, and that they will provide support to enable data exchange. Another point to be confirmed from meter manufacturing module used inside the meter is a plugin module. (k) The cost of internal wiring required for connection of meter and making good disturbed surface & matching with existing surface is deemed to included in quoted rate. (l) While installing power shutdown etc needs to be take in consulation with the user and MES .The contractor should ensure Minimum disturbance of Powerwhile changing the old Metering system to New Meters
3Supply and Installation ofSmart Three Phase Meter with the following specifications: (a) AC Three Phase Four Wire, Tamper Proof, Static Meter of Class 1.0, 415 V, 50 Hz, 10 A-100 A ISI marked conforming to IS-16444 2015(reaffirmed 2020) and relevant IEC standards with inbuilt 865-867 MHz Radio Frequency communication facility with self healing Mesh network with default and on demand display, billing data generation facility, anti-tamper features, Microprocessor and LED/LCD based circuitry. (b)Meter Should support the following data : 30 min instantaneous data for voltage, current, power factor, power, cumulative energy and frequency, 30 load survey data for energy, monthly billing survey for Cumulative Energy and Max Demand (c)Meter should have connect / disconnect functionality operable from prepaid billing software Electric supply will be disconnected under followingcondition.(a)Over Current (105 % of Max current in any phase (b) Load control limit (Programmable) (c) Disconnection signal from utility control centre (d) The meter shall confirms requirements specified in IS-15959. (e) All meters should be connected/ Integrated with their respective Data control units and approved softwares/ servers. (d) The meter should support open communication protocol DLMSwith the software MAKE: Secure, L&T, HPL Note: (a) The contractor would be responsible from removing the existing meter, noting down the reading and depositing it with the MES. (b) It would be possible to run the meter in both prepaid and postpaid mode (c) The meters to carry 05 year guarantee. The contractorshall furnish 05 (Five) years replacement guarantee for prepaid meters installed under this contract except damage from water and fire.
4(d) Whole work shall be executed through Origional Equipment Manufacturer (OEM) or its authorised repersentative. (e) Contractor will submit necessary MoU on Rs 100 stamp paper with OEM/Authorized rep (Who will provide all these facility mentioned above before commencement of work) (f)The contractor should maintain reserve stock of 3% of total meter installed and replace the faulty meter within one week of complaint given to him.Otherwise penal recovery of Rs 100/day/meter will be recovered from the contractor. (g) Meter should be compliant to IS16444. Data exchange protocol used should be as per IS 15959 (2011). (h) Meter manufacturer should share LLS Key & HLS Key of each meter. (j)Thesmart meter should be RF enabled, the buyer has to insist during purchase (in specs) that their MDAS can be exchanged with other third- party billing systems, and that they will provide support to enable data exchange. Another point to be confirmed from meter manufacturing module used inside the meter is a plugin module. (k) The cost of internal wiring required for connection of meter and making good disturbed surface & matching with existing surface is deemed to included in quoted rate. (l) While installing power shutdown etc needs to be take in consulation with the user and MES .The contractor should ensure Minimum disturbance of Powerwhile changing the old Metering system to New Meters.
5Provision of Server for Smart metering & other device for local IT infrastructure with followng accessories :- Server & Other devices for Local IT Infrastructure. (a)CISCO fire power firewall with IPS (Support for 3 years) and 100000 cocnurrent user (6000 new connections ) capacity. (b)Firewall Support - 2 years AMC suupport for VPN device for 02 No of places (c)Lan Switch- 8 Port layer - 3 Network LAN switch (d)WAN Switch- 8 Port layer - 3 Network WAN switch (e)Server for MDM, MDAS & applicationwith 16 Core processor - 2 Numbers, RAM 256 GB expandable upto 512 GB, SSD with 2 TB usable. (f)AMC support 3 years for VPN device for 2 No of places. (g)NAS storage for data archival with AMC for 5 years. System Softwares. (h)System software with operationg system (Window server standard edition latest) , Antivirus solution for 50 desktop and 12 virtual servers for quantity 05 Nos, Network management and monitoring solution at site 24/7 tool for 5 years. Data centre devices. (j)Data center devices with smart rack nos. (20U) considering 42 U smart rack space, Charges for setting up Air conditioner, UPS with 5 KVA capacity. (k) charges for 3 years AMCfor Airconditioner (l) UPS with 5 KVA capacity for years AMC (m)Internet bandwidth charges 1.50 TB data transfer/month for 60 months for Quantity 1500 Nos Backup server for redundency (n)Server for MDM, MDAS & Application 8 Core processor -2 numbers, RAM-256 GB expandable upto 512 GB SSD with 2 TB usable (n)Firewall with IPS (support for 5 years and 100000 cucnurrent user (6000 New) (o)LAN switch: 8 Port layer 2 network switch
6Supply and install hi wall split Air Conditioner (1.5 Ton AC Capacity) units indoor/outdoor complete with cordless remote control unit and with in built air ioniser and Plasma filter for better indoor air quality with minimum 5 star rating and EER 3.2 including timer arrangement of both AC complete all as specified and directed by engineer in charge
7M&L for Point wiring complete with 1100 volts grade FRLS insulated unsheathed cable of copper conductor cable multi stranded of size 1.5 Sqmm single coreincluding PVC rigid concealed conduit medium grade of suitable size (not lessthan 20mm dia) with all accessories such asbend reducers /MS hooks, MS junctionboxes 2mm thick galvanized steel pressed sunken terminal boxes of suitable sizes for mounting of switches sockets, fan regulators etc covered with 2.8mm thick plastic laminate (Hylem/Anchor) top cover including continuous earth wire of size 1.5 Sqmm PVCstrandedcopper conductor unsheathed, insulated stranded (Green colour) connected to common earthpoint dolly using colour code as per IS and making good all disturbed work to match the existing for one three pins 5 Amps switch socket outlet point on independent board complete all as specified and directed by Engr-in-charge.
8All as per item No05 here in before but for 15 Amps socket outlet with 2.5 Sqmm copper incl 2.5 Sqmm PVC insulated copper conductor cable as earth continuity conductor and connecting to common earth dolly
9All as per item No05 here in before but for 15 Amps socket outlet with 4 Sqmm copper incl 4 Sqmm PVC insulated copper conductor cable as earth continuity conductor and connecting to common earth dolly
10Supply and fixing Protector and accessories for AC starter 25 A, 2 Module grouted flush to walls complete all as specified and directed by Engineer-in- charge.
11S&F switch piano flush type, single pole, one way, 5 Amps, 230 volts AC supplycomplete all as specified and directed by Engineer-in-Charge.
12S&F socket5 pin,5 Amp, 230 Volt, AC Supply complete all as specified and directed by Engineer-in- charge.
13S&F switch piano flush type, single pole, one way, 15 Amps, 230, Volts AC supplycomplete all as specified and directed by Engineer-in-Charge.
14S&F socket two-in-one, 6 pin, 5 and 15 Amp flush type230 Volt AC supply complete all as specified and directed by Engineer-in- charge.
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail