| 1 | Double throat SS VENTURE SCRUBBER AND WET SCRUBBER –as per TNPCB norms.WE DESIGN, SUPPLY AND ERECT DOUBLE THROAT SS VENTURE AND WET SCRUBBING ARRANGEMENT AFTER THE FURNACE CAPABLE OF REMOVING FINE DUST PARTICLES THROUGH WET WASHING.THE VENTURE SCRUBBER SHALL BE CONNECTED TO A WASH COLUMN FOR GAS-WASH WATER SEPARATION. THE VENTURE SCRUBBER SHALL BE SS OF 2.5MM THICK PLATE SUITABLY MANUFACTURED AND TESTED AT FABRICATION SHOP.6NOS OF WATER NOZZLE ,INNER SIDE FILTER CERAMIC LAYERCENTRIFUGAL PUMP OF SUITABLE TO CIRCULATE TO MILD ALKALINE WATER THROUGH THE VENTURE SCRUBBER AT A RATE OF NOT LESS THAN 2LIT/S WITH A DISCHARGE PRESSURE HEAD OF (3KG / CM2 MIN) IN THE VENTURE SCRUBBER. |
| 2 | PIPE LINE FROM FURNACE TO CHIMNEY:WESUPPLY AND ERECTION THE12’’ MS PIPE LINE TO SEND THE CLEANED FLUE GAS FROMFURNACE TO SS SCRUBBER TO BLOWER &BLOWER TO CHIMNEY.FURNACE TO SCRUBBER PIPE LINE INSIDE CASTABLEINSULATION AND CASTABLE SUPPORT WELD MESH |
| 3 | AS PER TNPCB NORMS WE DESIGN, FABRICATE & SUPPLY OF CHIMNEY OF 30M HEIGHT.THE CHIMNEY SHALL BE FABRICATED OUT OF MS MATERIAL OF THICKNESS SHEETS 8MM,6MM AND 5MM VARYING FROM BOTTOM TO TOP WITH A BOTTOM DIAMETER SHALL NOT BE LESS THAN 1000MM. DESIGN SHALL CONFORM TO IS 6533 NORM AND CHIMNEY SHALL BE PROVIDED WITH ACCESSORIES SUCH AS:STEEL ROPES, AVIATION LIGHT, SAMPLING NOZZLE, LIGHTNING ARRESTOR, DRAIN PLUG, BOTTOM DOOR ETC,. |
| 4 | WE DESIGN, SUPPLY AND ERECT 5 HP ID BLOWER-S.S TO EXHAUST THE FLUE GAS TO CHIMNEY AFTER THE FLUE COOLED AND CLEANED IN THEVENTURE SCRUBBER. |
| 5 | SUPPLY, DELIVERY, AND FIXING CJARGES FOR 2HP PUMP MOTOR AND PLUMBING LINE WORK |
| 6 | 100KG CASTING BODY BRICK |
| 7 | WE DESIGN & CONSTRUCTIONCHIMNEY FOUNDACTION CIVIL WORK 6X6X6’ FEET WITH METRIALS |
| 8 | SUPPLY, DELIVERY, AND FIXING CJARGES FOR WELD MESH & ALUMINIYAM HR PAINT INCLUDING COST OF ALL MATERIALS ETC COMPLETED.., |
| 9 | SUPPLY, DELIVERY, AND FIXING CJARGES FOR M.S 15’’ OD FLANGE INCLUDING COST OF ALL MATERIALS ETC COMPLETED.., |
| 10 | SUPPLY, DELIVERY, AND FIXING CJARGES FOR 12’’ OD M.S BEND INCLUDING COST OF ALL MATERIALS ETC COMPLETED.., |
| 11 | SUPPLY, DELIVERY, AND FIXING CJARGES FOR CASTABLE 50KG BAG INCLUDING COST OF ALL MATERIALS ETC COMPLETED.., |
| 12 | TRANSPORT AND ERECTION AND LABOUR AND OLD BODY BRICKS REMOVEL AND NEW BODY BRICKS SETTING WORK. |
| 13 | Goods and Service Tax (GST 18%) |