Work Of Shifting Interrupted 33 Kv Overhead Line In Super Power Thermal Plant Khurja Project By Underground 33 Kv Xlpe Cable., bulandshahr-Uttar Pradesh

Paschimanchal Vidyut Vitran Nigam Limited has published Work Of Shifting Interrupted 33 Kv Overhead Line In Super Power Thermal Plant Khurja Project By Underground 33 Kv Xlpe Cable.. Submission Date for this Tender is 01-07-2023. XLPE Cable Tenders in bulandshahr Uttar Pradesh. Bidders can get complete Tender details and download the document.




Tender Notice

38183029
Corrigendum : Work Of Shifting Interrupted 33 Kv Overhead Line In Super Power Thermal Plant Khurja Project By Underground 33 Kv Xlpe Cable.
Open Tender
Indian
Uttar Pradesh
bulandshahr
01-07-2023

Tender Details

Work Of Shifting Interrupted 33 Kv Overhead Line In Super Power Thermal Plant Khurja Project By Underground 33 Kv Xlpe Cable.

Corrigendum Details

Sr No CorrigendumDate Corrignedum CorrigendumType NewSubmissionDate
1 20-Jun-2023 DATE EXT 20-06-23 Date 23-06-2023
2 23-Jun-2023 DATE EXT 23-06-23 Date 26-06-2023
3 26-Jun-2023 DATE EXT 26-06-23 Date 01-07-2023

Key Value

Document Fees
INR 1180 /-
EMD
INR 8300.0 /-
Tender Value
INR 8.30 Lakhs /-

BOQ Items

Name of Work: bZ&fufonk la[;k 25@fo0fo0ea0@iz0@cq0’kgj@2023&2024 fo|qr forj.k [k.M&[kqtkZ ds vUrxZr iw.kZ tek ;kstuk esa Vhå,påMhålhå bf.M;k] fyå lqij ikoj FkeZy IykaV [kqtkZ çkstsDV esa ckfèkr 33 dsoh vksoj gSM ykbZu dks v.MjxzkmUM 33 dsoh ,Dlå,yåihåbZå dsfcy }kjk vU;= LFkkukUrfjr djus dk dk;Z A
Sl. No. Item Description
1fo|qr forj.k [k.M&[kqtkZ ds vUrxZr iw.kZ tek ;kstuk esa Vhå,påMhålhå bf.M;k] fyå lqij ikoj FkeZy IykaV [kqtkZ çkstsDV esa ckfèkr 33 dsoh vksoj gSM ykbZu dks v.MjxzkmUM 33 dsoh ,Dlå,yåihåbZå dsfcy }kjk vU;= LFkkukUrfjr djus dk dk;Z A
2Safe carriage of fallowings from store center BSR to J.E Store/Sub station on kachcha pacaa road including loading and unloading chagres at both ends, rcquricd for proper completion of work, distance about to 60 Kms.
3S.T Pole 11 Mtr. Long
4Loading, Unloading Carriage of All line Material from store center BSR to J.E Store/Sub station as GI Wire, Earth Wire. M.S. Chanel, Angle, Stay & Earthig Rods, Barbed Wire. Disc Insulator ETC, distancewithin 0-60 Kms.
5Loading/Unloading/carriage 11 KV 3x300 sq.mm XLPE cable store center BSR to J.E Store/Sub station, distancewithin 0-60 Kms.
6Safe carriage of fallowings from J.E Store/Sub station To Pit Site on kachcha pacaa road including loading and unloading chagres at both ends, rcquricd for proper completion of work, distance about to 20 Kms.
7S.T Pole 11 Mtr. Long
8Loading, Unloading Carriage of All line Material from J.E Store/Sub station to pit site as GI Wire, Earth Wire. M.S. Chanel, Angle, Stay & Earthig Rods, Barbed Wire. Disc Insulator ETC, distancewithin-20Kms.
9Loading/Unloading/carriage 11 KV 3x300 sq.mm XLPE cablefrom J.E Store/Sub station To Pit Site distancewithin-60 Kms.
10Erection of ST Pole of 11 KVfittingsas per RESPO Drawing Top Channal, Dropper Channal, X Bracing Set, Disc Insulator, Pin Insulator, Guarding Angle F Bracket and etc as per direction of Engineer Incharge including the cost of labour, T&P and carrier etc. required for proper completion of work.
11Single Support ST Pole 11 Mtr. Long
12Double Support ST Pole 11 Mtr. Long
13Four Pole Support ST Pole 11 Mtr. Long
14Ggrouting of Poles as per RESPO Drawing and as per direction of Engineer Incharge including the cost of labour, T&P and carrier etc.The support shall be grouted with cement, sand and stone ballast in ratio 1:4:8 including the cost of Cement, Sand, Stone Ballast, Stone Pad etc. as per actual site requirement
15Single Support ST Pole 11 Mtr. Long
16Double Support ST Pole 11 Mtr. Long
17Four Pole Support ST Pole 11 Mtr. Long
18Laying sagging stringing and binding and jumpering etc of following Rabbit Conductor on the newly erected poles as per RESPO manual and as per direction of Supervising Engineer. It includes the cost of labour, T&P, carrier etc. required for proper completion of work.
19ACSR Dog Conductor
20Erection of stay set including the work of nozelling etc. as per RESPO manual and also including the cost of all grouting material, labour, T&P etc required for proper completion of work.
21Grouting of stay set including the work of nozelling etc. as per RESPO manual and also including the cost of all The support shall be grouted with cement, sand and stone ballast in ratio 1:4:8 including the cost of Cement, Sand, Stone Ballast, Stone etc. as per actual site requirement , labour, T&P etc required for proper completion of work.
22Fixing of earthing rod and Wire asper RESPO manual and as per direction of supervising engineer including the cost of labour, T&P etc. required for proper completion of work.
23Cutting/drilling/Welding ofMS Channel, Top Channal & 100X50X2600mm Dropper Channal & Pipe Channal Including the work of fixing on STP Pole for construction of the line.
24Painting of following supports/structures with 2 coats of synthetic enamel paint with one coat of ready mix primer includingwell as rubbing/cleaning of surface as required for proper completion of work.
25Single Support ST Pole 11 Mtr. Long
26Double Support ST Pole 11 Mtr. Long
27Four Pole Support ST Pole 11 Mtr. Long
28Making Jumpers on Section Points, byfixing of P.G.Clamps of proper sizes, suitable for Dog Conductor.
29Drilling of dia 160 mm in Two Parallel bores by trench less Method by horizantal Boring by HDD Machine.
30Digging of Pits Of Size For Cable Loop
31Restoration of Pit After Laying Of Cable loop
32Providing And Fixing Of Heat Shrinkable Cable Jointing Kit Indoor & Outdoor Suitable For 33 Kv 3X300 sq. mm XLPE Cable
33Laying of HDPE pipe throught HDD method HDPE 140 mm DIA
34HDPE pipe OD 140 mm DIA PN 4 PE 80 grade UV stabilized as per is 4984
35Fixing of GI pipe 6 for cable entry on pole
36Laying of one pair of 33 kv XLPE cable 3x300 Sq mm cable throught HDPE pipe
37The follwing material will be fixing/Installation.
38Fixing of 33 KV V type X arm
39Fixing of 33 KV F bracket
40Fixing of pin insulator
41Fixing disc insulator
42Fixing of Toff/Top/Drop Channel
43Fixing Danger Plate with clamps GI
44Fixing of Bracing with clamps
45The follwing materialwill be provided by the Contractor as per RESPO Drawing.
46Providing of HDPE PIPE
47Providing HDPE Socket Suitable For HDPE Pipe 140 mm dia
48Providing of GI Pipe 150 mm dia & 3 mtr long for hoisiting
49Providing of Danger Plate with clamps.
50Providing of Holding Clamps
51Providing of F-Bracket
52Providing of Earthing Clamps GI
53Providing of Stay Clamps
54Providing of Danger Plate with clamps GI
55Providing of Nuts & Bolts difference size With Barsher
56Providing of Stay Insulator
57Providing of Aluminium Paint
58Providing of Red oxide paint
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail