| 1 | Earth work in excavation by manual means in trenches for foundations, drains, pipes, cables etc.(not exceeding 1.5m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed. All kinds of soil (1meterfrom cutting edge) |
| 2 | Providing /laying of stone soling handpacked in foundation trenches including dressing,watering, compacting and all carriage up to site of work complete job |
| 3 | Providing and laying in position cement concrete of specified grade (M10 MIX) excluding the cost of centering and shuttering - All work up to plinth level: 1:3:6 (1 Cement : 3 coarse sand : 6 crushed graded stone aggregate 40 mm nominal size ) excld. carriage of all materials involved complete |
| 4 | Centring and shuttering including strutting, propping etc and removal of formwork foundation, footings, bases of columns etc for mass concrete |
| 5 | Brick work with common burnt clay F.P.S.(non-modualar) bricks of class designation 7.5 in foundation and plinth in upto floor-V level Cement mortar 1 :6 ( 1 cement : 6 coarse sand) excld.carriage of bricks |
| 6 | 12 mm cement plaster of mix 1:4 (1cement: 4 coarse sand) |
| 7 | Cement concrete flooring 1:2:4 (1cement: 2 coarse sand: 4 graded stone aggregate) finished with a floating coat of neat cement including cementslurry and curing complete, but excluding the cost of nosing of steps etc.complete. 40 mm thick with 20mm nominal size stone aggregate |
| 8 | Providing and Laying of Nallah muck/ RBM under floors including watering, dressing, ramming, incld . Carriage of material up to site of work complete job |
| 9 | Providing and fixing G.I. chain link fabric fencing of required width inmesh size 50x50 mm including strengthening with 2 mm dia wire or nuts, bolts and washers as required complete as per the direction of Engineer-incharge. Made of G.I. wire of dia 4mm |
| 10 | Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc.,including cutting , hoisting , fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete. Hot finished welded type tubes (4.0mm thick) |
| 11 | Structural steel work in built up sections, trusses and framed work, including cutting, hoisting,fixing in position and applying a priming coat of approved steel primer all complete. Welded |
| 12 | Providing and fixing precoated galvanized iron profile sheets (size, shape and pitch of corrugation as approved by Engineer-in-charge) 0.50 mm (+0.05 %) total coated thickness with zinc coating 120 grams per sqm as perIS: 277, in 240 mpa steel grade, 5-7 microns epoxy primeron both side of the sheet and polyester top coat 15-18 microns. Sheet should have protective guard film of 25 microns minimum to avoid scratches during transportation and should besupplied in single length upto 12 metre or as desired by Engineer-in-charge. The sheet shall befixed using self drilling /self tapping screws of size (5.5x 55mm) with EPDM seal, complete upto any pitch in horizontal/ vertical or curved surfaces, excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required |
| 13 | Providing and fixing precoated galvanised steel sheet roofing accessories0.50 mm (+0.05 %) total coated thickness, Zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns using self drilling/ self tapping screws complete : Ridges plain (500 - 600mm) |
| 14 | Steel work welded in built up sections/framed work, including cutting,hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works. |
| 15 | Painting with synthetic enamel paint of approved brand and manufacture to give an even shade. Two or more coats on new work |
| 16 | Finishing walls with water proofing cement paint of required shade on New work (two or more coats applied @ 3.84 kg / 10sqm) |
| 17 | Providing CIB on the wall of Shed as directed by Engineer Incharge , and taking of Photographs before, during & after execution of work complete job |
| 18 | Carriage of material by mechanical transport Sand & Bajri . From nearst source to site of work |
| 19 | Cement From nearst source to site |
| 20 | Bricks From nearst source to site |