| 1 | BOQ (PERIODICAL CLEANING AND MAINT OF UG SUMPS, CANAL WATER DRAINS, OHT , STATIC WATER TANK,SWIMMING POOLAND MISC E/M WORKS AT AIR FORCE STATION SURATGARH ) |
| 2 | Dewatering the left over water from existing raw water storage tank No 1 of capacity 5 Lakh gallons, having top plan size 44 x 44 metre, bottom plan size 40 x 40 metre and depth 2.35 metre, desilting, sludge, silt, all accumulated material from the bottom and sides and removing to a distance not exceeding 50 metre from the outer perimetre of tank and depositing/spreading where directed by Engr-in-charge including preparation of surface by wire brushing and washing the surface with 2% potassium permanganate solution for disinfection and applying one coat of white wash including removal of roots and uprooting of grass etc. all around upto 5 metre from plinth of tank, complete all as specified and directed by Engineer-in-Charge.Notes : (i) Approximate depth of silt and left out raw water is approximately 50 cm.(ii) Quoted rate is inclusive of minor repair with PCC and plastering inside the tank. |
| 3 | All as per Srl item No 1 here-in-before, but raw water tank Nos 5 & 6 of storage capacity 10 Lakh gallons and having top plan size 43 m x 43 m bottom plan size 38.60 m x 38.60 m and depth 3.00 m, complete all as specified and as directed by Engineer-in-Charge. |
| 4 | All as per Srl item No 1 here-in-before, but tank No 7 at main water supply complex of 60 lakh gallons capacity and having top plan size 140 x 84 metre bottom plan size 126 x 66 metre and depth 3.50 metre , complete all as specified and as directed by Engineer-in-Charge. |
| 5 | All as per Srl item No 1 here-in-before, but raw water round shape sump having 2.40 metre internal dia and depth 6.0 metre , complete all as specified and as directed by Engineer-in-Charge. |
| 6 | All as per Srl item No 1 here-in-before, but sedimentation tank having top plan size 17.60 x 17.60 metre bottom plan size 8 x 8 metre and depth 3.20 metre , complete all as specified and as directed by Engineer-in-Charge. |
| 7 | All as per Srl item No 1 here-in-before, but clear tank of 5000 gallons capacity complete all as specified and as directed by Engineer-in-Charge. |
| 8 | All as per Srl item No 1 here-in-before, but clear tank of 10000 gallons capacity complete all as specified and as directed by Engineer-in-Charge. |
| 9 | All as per Srl item No 1 here-in-before, but clear tank of 25000 gallons capacity complete all as specified and as directed by Engineer-in-Charge. |
| 10 | All as per Srl item No 1 here-in-before, but clear tank of 150000 gallons capacity complete all as specified and as directed by Engineer-in-Charge. |
| 11 | All as per Srl item No. 1 here-in-before, but floculator tank suitable for 30,000 gallons filter plant/hr capacity in two portion at main water supply, complete all as specified and as directed by Engineer-in-Charge. |
| 12 | Cleaning of overhead Reservoirs of capacity 50,000 gallon at 18 metre staging in two compartments by tank clean process as below :-(a) Mechanical removal of all remaining dirty water by submersible pump.(b)Removal of sludge by vacuum operated pump.(c)Cleaning of walls, ceiling base by high pressure and scrapping, brushing ,brooming down and applying one coat ofwhite wash as directed by the Engineer-in-Charge.(d) Removing of all dirty particles by industrial wet vacuum cleaner leaving the tank 99.9% physical cleaned. (e)Deposited the sludge to a distance not exceeding 50 metre at the location intimated by Engineer-in-Charge(f) Sterilization of tank by eco-friendly degradable and highly effecting all pathogens agent of tank clean sterilization of tank atmosphere by industrial V.V radiator leaving the tank complete sterile and writing the date of cleaning with paint, complete all as specified and as directed by Engineer-in-Charge. Notes:(i) All Safety measures for the safety of workmen shall be ensured by the contractor as work has to be carried out at height specified in respestive items. Insurance of workers shall also be got done by the contractor before execution of these items. This aspect shall deemed to be included in quoted rates. |
| 13 | All as per srl item No. 11 here-in-before, but overhead reservoir of capacity 5000 gallons at 06 metre staging , complete all as specified and as directed by Engineer-in-Charge. |
| 14 | All as per srl item No. 11 here-in-before, but overhead reservoir of capacity 10000 gallons at 06 metre staging , complete all as specified and as directed by Engineer-in-Charge. |
| 15 | All as per srl item No. 11 here-in-before, but overhead reservoir of capacity 75000 gallons at 18 metre staging , complete all as specified and as directed by Engineer-in-Charge. |
| 16 | All as per srl item No. 11 here-in-before, but overhead reservoir of capacity 40000 gallons at 12 metre staging , complete all as specified and as directed by Engineer-in-Charge. |
| 17 | All as per item No 8 here-in-before, but reservoirs of capacity 25000 gallons, complete all as specified and as directed by Engineer-in-Charge. |
| 18 | M&L for preparation of old painted surface of MS/CI pipes such as rising main, distribution mains, washout and over flow pipes,MS covers of valve pit and canal drains and painting with one coat of synthetic enamel paint, as per colour code given by the deptt , complete all as specified and as directed by Engineer-in-Charge.(Note :- The rates includes for writing and marking description of pipes with white enamel paint) |
| 19 | Cutting and uprooting grass, vegetation shrubs, bushwood undergrowth, roots and trees not exceeding 30 cm girth (measure one metre above ground level) and removing rubbish to a distance upto 50 metres outside the periphery of the area,complete all as specified and as directed by Engineer-in-Charge. |
| 20 | Cleaning and desilting of water channel from canal to raw water storage tanks of any cross section and shape.Taking out sludge including all accumulated material from bottom and sides of water channel by scrapping, brushing the water course, washing including white washing inner surface of water channel including removing excavated material to a distance not exceeding 50 metre and depositing where directed,complete all as specified and as directed by Engineer-in-Charge.Note : The cross section of channel is 60 cm x 75 cm |
| 21 | Dewatering the left over water from existing floculator wash out tank having top plan size 12 x 12 metre bottom plan size 10 x 8 metre and depth 4.00 metre, desilting, sludge, silt, all accumulated material from the bottom and sides and removing to a distance not exceeding 50 metre from the outer perimetre of tank and depositing where directed by Engr-in-charge including preparation of surface by wire brushing and applying one coat of white wash, complete all as specified and directed by Engr-in-charge .Note :Approximate depth of silt 185 cm and depth of water approximately 100 cm. |
| 22 | Desilting, sludge, silt and kai from bottom and outer sides of static water tank of capacity 50,000 gallons, by scrapping, brushing, brooming down, cleaning with water and applying one coat of white wash to inner surface and depositing sludge to a distance not exceeding 50 metre , complete all as specified and as directed by Engineer-in-Charge. |
| 23 | Desilting, sludge, silt and kai from bottom and outer sides of static water tank of capacity 10,000 gallons, by scrapping, brushing, brooming down, cleaning with water and applying one coat of white wash to inner surface and depositing sludge to a distance not exceeding 50 metre , complete all as specified and as directed by Engineer-in-Charge. |
| 24 | Removing/pumping of used water with new/fresh water from station swimming pool at Maru Vihar.Desilting, removal of sludge and all accumulated dirt/foreign objects from bottom surface and sides including drain along the swimming pool entire plinth surrounding the swimming pool.All dirt to be cleaned outside the perimeters of swimming pool building upto 50mtrs.Use of pottassium permanganate solution and iron brushes for cleaning of swimming pool for entire disinfection, complete all as specified and all as directed by Engineer-in-Charge. |
| 25 | Cutting the tree branches hanging over raw water UG sumps andwater supply complex and depositing the tree branches /leaves at 500m distance away from the site , complete all as specified and as directed by Engineer-in-Charge..Note : Any number of tree branches cut in one branch will be measured as one length for payment purpose, complete all as specified and as directed by Engineer-in-Charge. |
| 26 | Taking up CI/DI/GI water mains 80/100 mm dia from trenches (including all fittings), with spigot and socket ends and lead/tyton/Flanged joints including burning out joints and recovering lead complete all as specified and directed. |
| 27 | S&F ductile Iron pipes of 100mm bore with spigot and socketed ends, Class “K-7”, suitable for and including rubber tyton joints complete all as specified and directed.Note:- Earthwork and excavation required shall be measured and paid under respective items. Existing GI connections are to be done in newly laid pipeline including required clamp, ferrules etc, cost for the same shall be included in quoted rate. |
| 28 | Material and labour for DI specials such as tees, bends of any sizeand radius, tapers, collars, tail pieces, caps and plugs etc. complete all as specified and directed. |
| 29 | Taking up old unserviceable Air valves, Material and labour for Air release valve with two air out lets confirming to IS 14845 of size 50 mm dia bore and fixing in DI/GI/CI water supply mains of size 50mm to 150 mm dia with all fittings complete all as specified and as directed. |
| 30 | Excavation in trenches loose/soft soil not .exceeding 1.5 mtr wide and not exceeding 1.5 mtr depth for foundations, laying water mains, pipes, cables, etc getting out and forming bottom surface to required gradient complete all as specified and as directed. |
| 31 | Returing filling in incl spreading leveling, watering and well ramming in layer not less than 25 cm each layer complete all as specified and as directed. |
| 32 | Removing excavated material to a distance not exc 50M anddepositing where directed at a level n.exc 1.5 mtr above the starting point complete all as specified and as directed. |
| 33 | Demolition of brick work or stone/boulder masonary built in cement mortar including all quions arches pillars etc, but excluding ashlar facings dressed stone work and precast concrete articles, complete all as specified and all as directed by Engineer-in-Charge. |
| 34 | Demolition of cement concrete of any description and in any position, complete all as specified and all as directed by Engineer-in-Charge. |
| 35 | M&L for brickwork with subclass B bricks straight or curved on plan exc 6m mean radius built in cement mortar 1:6, complete all as specified and all as directed by Engineer-in-Charge. |
| 36 | M&L for cement concrete in foundations filling in mass concrete Type D2 1:4:8 (using 40 mm graded aggregate), complete all as specified and all as directed by Engineer-in-Charge. |
| 37 | M&L for providing cement concrete Type C1 1:3:6 (using 20 mm graded aggregate), complete all as specified and all as directed by Engineer-in-Charge. |
| 38 | Material and labour for rendering 10mm thick on fair faces of brick work or concrete surfaces in CM 1:4, complete all as specified and all as directed by Engineer-in-Charge. |
| 39 | Contract Amount shall be derived after affecting the amount of Schedule of Credit in General Summary on serial page No 17 of tender documents. |