Name of Work: Construction of culvert Bridge(Additional Widenning) at Pappayi Ammal Street Rahuman Nagar connecting road in municipality
Sl. No.
Item Description
1
Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrockrequiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete Earthwork Excavation - Footing
2
Supplying and filling in foundation andbasement with Crushed Stone Sand (M-Sand) in layers of not more than 15cm thick well rammed watered and compacted etc., complete complying with standard specification.- M Sand filling
3
Plain Cement Concrete 1:4:8 (one cement four fine aggregates and eight coarse aggregates) using 40mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges and all incidential charges such as water providing etc., complete as per standard specification
4
Supplying and erecting centering for sides and soffits including necessary supports and strutting upto 3.29 M height for plane surfaces as detailed below in all floors with all cross bracings using Mild Steel sheets of size 90 x 60 cm and 10 BG stiffened with welded Mild Steel angle of size 25mm x 25mm x 3 mm for boarding laid over silver oak joists of size 10cm x 6.50 cm spaced at abote 90 cm centre to centre and supported by casurina props of 10cm to 13 cm dia spaced at not more than 75 cm centre to centre etc. complete complying with the standard specificaiton. (Payment for centering shall be given after the concrete is laid) - Centering 2 For Plane surface such as slab,beam etc
5
Suppling and fabricating and placing in position MS(or) R.T.S. bar for reinforcement to all RCC works as per the design given including cost ofsteel and binding wire also in all floors.
6
Reinforced Cement concrete 1:1.5:3 (one cement, one and half sand & three course aggregate) using 20mm gauge hand broken/ and broken granite stone for all RCCitemsof works excluding centering shuttering and cost of reinforcement but including curing etc.,complete and alsoincluding fixingfan clamps and fixtures in rccworkswherever necessary as directed by departmentalofficer etc., complete.
7
Plain Cement concrete 1:1.5:3 (one cement, one and half sand & three course aggregate)using 20mm gauge hand broken/ and broken granite stone for all RCCitemsof works excluding centering shuttering and cost of reinforcement but including curing etc.,complete and alsoincluding fixingfan clamps and fixtures in rccworkswherever necessary as directed by departmentalofficer etc., complete.
8
Reinforced Cement concrete 1:2:4 (one cement, two sand& Four course aggregate) using 20mm gauge hand broken/ and broken granite stone for all RCCitemsof works excluding centering shuttering and cost of reinforcement but including curing etc.,complete and alsoincluding fixingfan clamps and fixtures in rccworkswherever necessary as directed by departmentalofficer etc., complete.
We takes all possible care for accurate & authentic tender information, however Users
are requested to refer Original source of Tender Notice / Tender Document published by
Tender Issuing Agency before taking any call regarding this tender.