Department of Cooperation has published Tender For Fabrication Job (Major Jobs And General Jobs). Submission Date for this Tender is 08-06-2023. Drilling Rigs and Machinery Tenders in Jalandhar Punjab. Bidders can get complete Tender details and download the document.
Sr No | CorrigendumDate | Corrignedum | CorrigendumType | NewSubmissionDate |
1 | 02-Jun-2023 | EXTENSION IN DATE | Date | 08-06-2023 |
Sl. No. | Item Description |
1 | Replacement of worn out M.S. vertical supporting channels & side plate of final molasses storage tank with M.S Plate and channels. |
2 | Replacement of worn outRoofof final molasses storage tank with M.S Plate 4/5/6mm and Supporting Channel /Angle. |
3 | Dismantling , Fabrication and erection of top MS plate of Pan No1. |
4 | Strengthening of pans shell with angle and channels in round shape with MS angle 75x75mm and Dia 4.34 mtr. (3 rounds) |
5 | Strengthening of Evaporator shell with angle and channels in round shape with MS angle 75x75mm and Dia 2.80 mtr. (3 rounds) |
6 | Dismantling, Fabrication, Erection of top cone below save all of evaporators. |
7 | Dismantling, Fabrication, Erection of Complete Save all (existing design) of evaporators including top plate, inner and outer shell. |
8 | Dismantling, Fabrication, Erection of umbrella of save all Evaporator 4th body as per existing design including all supporting. |
9 | Dismantling, Fabrication and erection of All Quad condensate tank/ Syrup Bottle including all connection. Approx. Size Dia509mmxlength 1800mm |
10 | Dismantling, Fabrication, Erection of Stirrer(Fan) of Aeration Tankat ETP as per existing Design including complete commissioning and trial |
11 | Dismantling, Fabrication, Erection of Hot water Weighing tank of water weighing scale. Dia 1.6 mtr x 1.5 height X cone 1 mtr length .The Erection work for this job will also include all connections which are dismantled during dismantling. |
12 | Dismantling, Fabrication, Erection of Mix juice Weighing tank of Juice weighing scale. Dia 2 mtr x 1.5 height X cone 1 mtr length .The Erection work for this job will also include all connections which are dismantled during dismantling. |
13 | Dismantling, fabrication & Erection of Juice feed boxes of juice heater double bead valve. The Erection work for this job will also include all connections which are dismantled during dismantling. |
14 | Dismantling, fabrication & Erection of absorption tower of Juice Sulphiter. The Erection work for this job will also include all connections which are dismantled during dismantling |
15 | Dismantling, Fabrication & Erection of worn out Stainer of Mix juice tank/ Sulphited Juice tank / Syrup Tank. |
16 | Dismantling, fabrication and Erection of the sulphur furnace with existing design (By 20 mm MS plate) This work include dismantling and Erection of all connections, man hole, flanges etc of sulphur Furnace. |
17 | Dismantling, fabrication and Erection of Melter of Sulphur furnace as per Existing design. This work include dismantling and Erection of all connections, man hole, flanges etc. |
18 | Dismantling, fabrication and Erection of Scrubber of Sulphur furnace as per Existing design. This work include dismantling and Erection of all connections, man hole, flanges etc . |
19 | Dismantling, Fabrication & Erection of Dorr coils(Nipple/Flange/ reducer rates as per general fabrication, Erection Rates ) |
20 | Dismantling, fabrication and Erection of Mud tank below RVF including all connections. |
21 | Dismantling, fabrication and Erection of worn out Heavy / Light Vacuum tank of RVF including all connections. |
22 | Dismantling , fabrication and erection of worn out condensate pit along with partition plate of V.L.J.H /4th body . |
23 | Dismantling, fabrication & Erection of filter Juice Sealing Bottles of receiving pit for vacuum filter. The Erection work for this job will also include all connections which are dismantled during dismantling. |
24 | Dismantling fabrication and Erection of filtrate juice receiving tanks for vacuum filter. The Erection work for this job will also include all connections which are dismantled during dismantling. |
25 | Dismantlingfabrication and Erection of Bagacillo pipeline from MS plate 3mm |
26 | Dismantling, Fabrication & Erection of Bagacillo Cyclone. |
27 | Dismantling, Fabrication & Erection of Bagacillo Chute. |
28 | Dismantling, Fabrication & Erection of Bottom trough of Mud Mixer for RVF. |
29 | Dismantling, Fabrication & Erection of screw conveyor of Mud Mixer. |
30 | Dismantling, fabrication and Erection of MS vapour pipe of t sizes. Dia- 1050mm |
31 | Dismantling, fabrication and Erection of MS vapour pipe ofsizes. Dia - 900mm , |
32 | Dismantling, fabrication and Erection of MS vapour pipe ofsizes. Dia - 720mm |
33 | Dismantling, fabrication and Erection of MS vapour pipe ofsizes. Dia – 620mm |
34 | Dismantling, fabrication and Erection of MS vapour pipe ofsizes. Dia – 520mm |
35 | Dismantling, fabrication and Erection of MS vapour pipe ofsizes. Dia – 420mm |
36 | Dismantling, Fabrication & Erection Vapour/Exhaust pipe bend 900mm Dia |
37 | Dismantling, fabrication and Erection of distance piece of MS vapour pipe length up to 1.5 mtr. Dia- 1050mm |
38 | Dismantling, fabrication and Erection of distance piece of MS vapour pipe length up to 1.5 mtr.Dia - 900mm , |
39 | Dismantling, fabrication and Erection of distance piece of MS vapour pipe length up to 1.5 mtr. Dia - 720mm |
40 | Dismantling, fabrication and Erection of distance piece of MS vapour pipe length up to 1.5 mtr. Dia – 620mm |
41 | Dismantling, fabrication and Erection of distance piece of MS vapour pipe length up to 1.5 mtr. Dia – 520mm |
42 | Dismantling, fabrication and Erection of distance piece of MS vapour pipe length up to 1.5 mtr. Dia – 420mm |
43 | Dismantling of MS/CI condenser cone of Pans |
44 | Fabrication of MS condenser cone ofPans |
45 | Erection of MS/CI condenser cone of Pans |
46 | Dismantling, Fabrication, Erection of umbrellas of pan save all as per existing design including all supporting. |
47 | Replacement of worn out portion of bottom, side plate & supporting angle/channel of syrup and molasses tank at Pan station . |
48 | Replacement of M.S Plate Gutter of Crystallizer station and other factory units. |
49 | Replacement of worn out portion ofpan soucer. |
50 | Dismantling, fabrication and Erection of downtake of Pan from 10/12mm plate. |
51 | Replacement of Feed box of Pans including all connections. |
52 | Dismantling, fabrication and Erection Distributor of pans. |
53 | Dismantling, Fabrication & Erection of Worn out portion of molasses conditioner. This work includes dismantling and Erection of all connection pipes and their drive unit. |
54 | Dismantling, fabrication and Erection of worn out bottom portion of crystallizer |
55 | Dismantling, Fabrication and Erection of wornout portion of C-Vacuum Crystallizer. |
56 | Replacement of crystallizer arms along with supports from 75x75mm M.S angle.Dismantling. |
57 | Replacement of crystallizer arms along with supports from 75x75mm M.S angle. Fabrication. |
58 | Replacement of crystallizer arms along with supports from 75x75mm M.S angle.Erection. |
59 | Dismantling, fabrication & Erection of cooling coils3” of Crystallizer including all connections. |
60 | Dismantling and Erection of MS branch pipes of spray pond. This work includes all connections of clusters. |
61 | Dismantling of CI/MS main pipeline spray pond |
62 | Dismantling fabrication & Erection of suction pipes of injection pumps with stainer. |
63 | Dismantling fabrication & Erection of suction pipes of Spray pumps with stainer. |
64 | Dismantling, Fabrication Erection of worn out Bottom half portion of A / B magma mixture including allconnections. |
65 | Dismantling, Fabrication and Erection of worn out Bottom half portion of A pug mill including all connections. |
66 | Dismantling, Fabrication and Erection of worn out A-Magma Mixture complete including all connections. |
67 | Dismantling, Fabrication and Erection of Sugar Melter Pump stainer Including all connections |
68 | Fabrication and Erection of Bed for pump and motor of Magma mixture along with suction and delivery pipe line connections, alignment of motor with pump etc. |
69 | Dismantling, fabrication and Erection of bottom discharge chute of continuous centrifugal machine |
70 | Fabrication and Erection of new syrup tank at pan station including all connections. |
71 | Dismantling, Fabrication and Erection of ammonia coils of pans from MS pipeDia 3”including all connection |
72 | Dismantling and Erection of Tube plate (Top and Bottom)2nd evaporator body including Fabrication and erection of downtake including all connections. |
73 | Dismantling and Erection of Complete Calendria with Tube plate (Top and Bottom) of 2nd evaporator body including all connections along with Fabrication and erection of downtake |
74 | Dismantling and Erection of Complete Calendria with Tube plate (Top and Bottom) of Pan No. 5 including all connections along with Fabrication and erection of downtake and dismantling & erection of distributor. |
75 | Fabrication and erection of Beds for Pump and Motor etc. |
76 | Dismantling and Erection of Crystallizer shaft including arms and all connections, Fittings. |
77 | Dismantling, Fabrication and Erection Cane cutter hoods from8-10mm thick plate with MS Angles etc. |
78 | Dismantling and Erection of Expansion joint of power turbine exhaust line. |
79 | Replacement of side plates of cane carrier chain/ RBC and trough of RBC / Bagasse elevator/ Cross RBC. |
80 | Replacement of channel and I-Beam of RBC/ Cane Carrier/ Bagasse Elevator/ Cross RBC Runner |
81 | Dismantling, fabrication erection of juice tray of mill No. 3 from MS plate |
82 | Fabrication of screw conveyor of Mill House |
83 | Dismantling, Fabrication of trough of screw conveyor(Mill House), assembly of screw conveyor with trough & its erection. |
84 | Dismantling, fabrication erection of ash hopper of boiler (pyjamas) cone with chute bottom portion( cone tapper portion size 15” approximate) |
85 | Repair of rotary bagasse feeders of boilersBody |
86 | Repair of rotary bagasse feeders of boilersRotor |
87 | Replacement of side plate 3mm/old ms plate of boiler (with MS plate & supporting angle/ flat) |
88 | Dismantling, fabrication & erection of worn out ducting of boiler & APCD including angle, channel, Flats& flanges |
89 | Dismantling, Fabrication & Erection damper of boiler ducting |
90 | Dismantling fabrication & erection of Expansion jointof boiler ducting (3.360 mtr x 1.260 mtr) |
91 | Replacement of MS gutter of APCD plant from wet scrubber to Ash Pits |
92 | Dismantling fabrication & erection of Damper of rotary Bagasse Feeder |
93 | Dismantling, fabrication & erection of worn out portion of ID and APCD fan casing |
94 | Replacement of sieve plates of APCD scrubber. This job also includes 10/12mm holes (324 holes per square ft.) drillingin plates |
95 | Baffle plates (MS flat 65 x 6mm) of demister in Wet Scrubber |
96 | Repair/ replacement of wornout portion of wet scrubber of Boiler No. 1 & 2 |
97 | Dismantling fabrication and erection of receiving tank/ Sum Tank/ Sealing tank of Wet scrubber. |
98 | Replacement of G.I Sheet Gutter of factory building |
99 | Replacement of worn-out of M.S. Runner of inter carrier, elevator, RBC , cross carrier & cane carrier chains |
100 | Fabrication and Erection of discharge bagasse chute between last mill and bagasse elevator |
101 | Juice heater/V.L.J.H. SS tubesDismantling |
102 | Juice heater/V.L.J.H. SS tubes Fitting |
103 | Semi kestner SS tubesDismantling |
104 | Semi kestner SS tubesFitting |
105 | Quad bodies SS tubesQuad 1st to 4thDismantling |
106 | Quad bodies SS tubesQuad 1st to 4th Fitting |
107 | Pans SS/Brass tubesPan1st to 5th Dismantling |
108 | Pans SS/Brass tubesPan1st to 5th Fittings |
109 | Welding joints of water, juice,vapor and exhaust pipe line of Exhaust Pipe Lines of all Sizes. |
110 | MS Pipe line 1/2" to 12” dia Dismantling |
111 | MS Pipe line 1/2" to 12” diaErection |
112 | SS Pipe line 1/2" to 12” diaDismantling |
113 | SS Pipe line 1/2" to 12” dia Erection |
114 | CI Pipe line 1/2" to 12” diaDismantling |
115 | CI Pipe line 1/2" to 12” dia Erection |
116 | CI Pipe line above 12” dia Dismantling |
117 | CI Pipe line above 12” dia Erection |
118 | MS Pipe line above 12” dia from MS plate (other than vapour pipe of pan and quad)Dismantling |
119 | MS Pipe line above 12” dia from MS plate (other than vapour pipe of pan and quad) Fabrication |
120 | MS Pipe line above 12” dia from MS plate (other than vapour pipe of pan and quad)Erection |
121 | MS Bend upto 12” diaDismantling |
122 | MS Bend upto 12” diaFabrication |
123 | MS Bend upto 12” dia Erection |
124 | MS Bend above 12” dia from MS plate (other than V.P. pans & quad)Dismantling |
125 | MS Bend above 12” dia from MS plate (other than V.P. pans & quad)Fabrication |
126 | MS Bend above 12” dia from MS plate (other than V.P. pans & quad) Erection |
127 | CI Bends sizes 1” to 12”Dismantling |
128 | CI Bends sizes 1” to 12”Erection |
129 | Dismantling, Fabrication& Erection of M.S(all sizes) Tee, |
130 | Dismantling, Fabrication& Erection of M.S(all sizes) Nipples, |
131 | Dismantling, Fabrication& Erection of M.S(all sizes)Crosses |
132 | Dismantling, Fabrication& Erection of M.S(all sizes)Reducers |
133 | Dismantling, Fabrication& Erection of M.S(all sizes) Elbow |
134 | Dismantling, Fabrication& Erection of S.S(all sizes) Tee, |
135 | Dismantling, Fabrication& Erection of S.S(all sizes) Nipples, |
136 | Dismantling, Fabrication& Erection of S.S(all sizes) Crosses |
137 | Dismantling, Fabrication& Erection of S.S(all sizes) Reducers |
138 | Dismantling, Fabrication& Erection of S.S(all sizes) Flange |
139 | Dismantling, Fabrication& Erection of S.S(all sizes) Elbow |
140 | Dismantling, Fabrication& Erection of S.S(all sizes) Bend |
141 | Replacement of wornout MS Cone(all sizes) |
142 | MS Flanges(all sizes) Dismantling |
143 | MS Flanges(all sizes)Fabrication |
144 | MS Flanges(all sizes) Erection |
145 | Dismantling , fabrication and errection of Man Hole (all sizes) |
146 | a) Dismantling of platform. |
147 | b) Fabrication & Erection of platform |
148 | M.S. Tankhaving round & rectangular bottoms Dismantling |
149 | M.S. Tankhaving round & rectangular bottomsFabrication |
150 | M.S. Tankhaving round & rectangular bottoms Erection |
151 | M.S. Tankhaving conical bottomsDismantling |
152 | M.S. Tankhaving conical bottoms Fabrication |
153 | M.S. Tankhaving conical bottomsErection |
154 | M.S Structure Trusses, Perlins, Columns & Beams (Factory Building) Dismantling |
155 | M.S Structure Trusses, Perlins, Columns & Beams (Factory Building)Fabrication |
156 | M.S Structure Trusses, Perlins, Columns & Beams (Factory Building)Erection |
157 | Strengthening/ replacement of L-bracket/support between column and beam of factory building structure |
158 | Platform railing from old pipe & angleDismantling |
159 | Platform railing from old pipe & angleErection |
160 | Electric panel ,DB and other machinery shed GI/ACC/MS sheet Dismantling |
161 | Electric panel ,DB and other machinery shed GI/ACC/MS sheetFabrication |
162 | Electric panel ,DB and other machinery shed GI/ACC/MS sheetErection |
163 | Patch work of any part of any equipment with 3mm to 10mm thick plate max. upto 1 sq meter |
164 | Dismantling of sluice valve/ angle valve/ N.R.V. |
165 | Erection of sluice valve/ angle valve/ N.R.V. ,Butterfly Valve |
166 | Replacement of Rail line of caneunloaderwith 50mm square bar |