Tender For Renovation Of School Building And Toilet Sids Scheme
Tender Overview
Project Description
1 ) A.Repairs To Pum Schoolsouth Facing R C C Building At Mainroad Campus, B.Repairs To Pum Schoolnorth Facing R C C G + 1 Building, C.Repairs To Pum Schooleast Facing R C C Building At Mainroad Campus, D.Repairs To Pum School Toilet ( Girls ) At Main Road Campus, E.Repairs To Pum School Toilet ( Boys-Ii ) Main Road Campus, F. In Muniyur Panchayat.Repairs To Pum School ( Common ) Main Road Campus, G.Repairs To Pum School Toilet ( Boys ) Main Road Campusin Narthankudi Panchayat
BOQ
| Sl. No. | Item Description |
| 1 | a.Repairs to PUM SchoolSouth Facing R C C Building at Mainroad Campus |
| 2 | Dismantling the existing Damaged Grano floor area including all labour charges etc., completed |
| 3 | Dismantling the existing Damagedplastering includingall labour charges etc., completed |
| 4 | Providing granolethic floor finish in cement concrete 1:2:4 mix using 10-12mmISS metal to 25mm thick including cost and conveyance of all materials to site and all labour charges for mixing, laying, curing etc complete for 10 cum |
| 5 | Cement concrete 1:4:8 mix using 40mm HBG Metal including cost and conveyance of all materials and all labour chages etc., complete |
| 6 | Brikc work in CM 1:5 mix usihg country bricks of size 8¾x4¼x2¼ including cost and conveyance and all other labour charges etc., completed |
| 7 | Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed |
| 8 | Platering with CM 1:3, mix, 10mm thick including cost and conveynace and all laour charges etc., completed |
| 9 | White washing two coats using shell lime including cost of materils and all labour charges etc., completed |
| 10 | Distemberingone coat with best approvde distembering including cost of materils and all labour charges etc., completed |
| 11 | Exterior Emulsiontwo coats with best approvde Exterior Plastic Emulsionincluding cost of materils and all labour charges etc., completed |
| 12 | Painting two coats over oid iron works using ready mixed enamel paintincluding cost of materils and all labour charges etc., completed |
| 13 | Painting with Black Board Painting with Ready mixed Black board painting including cost of materils and all labour charges etc., completed |
| 14 | Provision for Bala Painting |
| 15 | Providing Cub boardArrangements(Sub Estimate) |
| 16 | Brikc work in CM 1:5 mix usihg country bricks of size 8¾x4¼x2¼ including cost and conveyance and all other labour charges etc., completed |
| 17 | Supplying and fixing following thickness of cuddapah slab for cupboard |
| 18 | Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed |
| 19 | Distembertwo coats with best approvdeincluding cost of materils and all labour charges etc., completed |
| 20 | Providing for Teachers Cub Board (Sub Estimate) |
| 21 | Brikc work in CM 1:5 mix usihg country bricks of size 8¾x4¼x2¼ including cost and conveyance and all other labour charges etc., completed |
| 22 | Supplying and fixing following thickness of cuddapah slab for cupboard |
| 23 | Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed |
| 24 | Distembertwo coats with best approvdeincluding cost of materils and all labour charges etc., completed |
| 25 | Supply & Fixing of 35mm thk.single leaf high density interior grade marine plywood shutters pasted both sides 1.5mm thk.laminate approved design with 35x12mm T.W.lipping on all edges with necessary adhesives and CP screws complying with standard specification.The cost is inclusive of 1 no cylindrical Lock,handel,tower bolt ,approved equivalent make SS ball bearing hinges of quivalent make of aproved make,2 no floor mounted SS door stoper ect.complete as per drawing. Make: Kutty,Sharon, Trojan. Accesseorice Make: Dorma, Godrej.1.5mm thk Laminate Basic Cost:810/M2 . |
| 26 | Providing Chappal Rack Arrangements(Sub Estimate) |
| 27 | Brikc work in CM 1:5 mix usihg country bricks of size 8¾x4¼x2¼ including cost and conveyance and all other labour charges etc., completed |
| 28 | Supplying and fixing following thickness of cuddapah slab for cupboard |
| 29 | Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed |
| 30 | Distembertwo coats with best approvdeincluding cost of materils and all labour charges etc., completed |
| 31 | Providing Drinking Arrangements(Sub Estimate) |
| 32 | Dismantling the Existing Damagedcement Plasteringincluding allchages etc for complete |
| 33 | Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth,earth mixed with small sized boulders and hard gravelly soil as per SS 20B |
| 34 | Collection and supply of sandand filling in to the basement including cost and conveyanceto the siteand all labour charges for filling as per standard speecifications |
| 35 | Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc completefor 10 cum. |
| 36 | Brikc work in CM 1:5 mix usihg country bricks of size 8¾x4¼x2¼ including cost and conveyance and all other labour charges etc., completed |
| 37 | Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed |
| 38 | Providing granolithicfloor finish in cement concrete 1:2:4 mix using 10-12mm ISS metal to 25mm thick including cost and conveyance of all materials to site and all labour charges for mixing, laying, curing etc complete for 10 cum. |
| 39 | Dadooing walls Plain Galzed tiles of size 150x150x6mm cost and conveyance of all materials to site and all labour charges etc completefor10 Sqm |
| 40 | Provision for PVC Pipe,Tank and Tap arrangements |
| 41 | Provision for Repair to Windows |
| 42 | Provision for 15Amps Socket SD 40 |
| 43 | Provision for EB Box Cover |
| 44 | Provision for String Bhandle |
| 45 | Provision for information white Board |
| 46 | Provision For Name Board |
| 47 | b.Repairs to PUM SchoolNorth Facing R C C G + 1 Building, |
| 48 | Dismantling the existing Damagedplastering includingall labour charges etc., completed |
| 49 | Providing granolethic floor finish in cement concrete 1:2:4 mix using 10-12mmISS metal to 25mm thick including cost and conveyance of all materials to site and all labour charges for mixing, laying, curing etc complete for 10 cum |
| 50 | Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed |
| 51 | Platering with CM 1:3, mix, 10mm thick including cost and conveynace and all laour charges etc., completed |
| 52 | White washing two coats using shell lime including cost of materils and all labour charges etc., completed |
| 53 | Distemberingone coats with best approvde distembering including cost of materils and all labour charges etc., completed |
| 54 | Exterior Emulsiontwo coats with best approvde Exterior Plastic Emulsionincluding cost of materils and all labour charges etc., completed |
| 55 | Painting two coats over oid iron works using ready mixed enamel paintincluding cost of materils and all labour charges etc., completed |
| 56 | Painting with Black Board Painting with Ready mixed Black board painting including cost of materils and all labour charges etc., completed |
| 57 | Provision for Bala Painting |
| 58 | Providing Cub boardArrangements(Sub Estimate) |
| 59 | Brikc work in CM 1:5 mix usihg country bricks of size 8¾x4¼x2¼ including cost and conveyance and all other labour charges etc., completed |
| 60 | Supplying and fixing following thickness of cuddapah slab for cupboard |
| 61 | Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed |
| 62 | Distembertwo coats with best approvdeincluding cost of materils and all labour charges etc., completed |
| 63 | Providing Chappal Rack Arrangements(Sub Estimate) |
| 64 | Brikc work in CM 1:5 mix usihg country bricks of size 8¾x4¼x2¼ including cost and conveyance and all other labour charges etc., completed |
| 65 | Supplying and fixing following thickness of cuddapah slab for cupboard |
| 66 | Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed |
| 67 | Distembertwo coats with best approvdeincluding cost of materils and all labour charges etc., completed |
| 68 | Providing for Teachers Cub Board (Sub Estimate) |
| 69 | Brikc work in CM 1:5 mix usihg country bricks of size 8¾x4¼x2¼ including cost and conveyance and all other labour charges etc., completed |
| 70 | Supplying and fixing following thickness of cuddapah slab for cupboard |
| 71 | Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed |
| 72 | Distembertwo coats with best approvdeincluding cost of materils and all labour charges etc., completed |
| 73 | Supply & Fixing of 35mm thk.single leaf high density interior grade marine plywood shutters pasted both sides 1.5mm thk.laminate approved design with 35x12mm T.W.lipping on all edges with necessary adhesives and CP screws complying with standard specification.The cost is inclusive of 1 no cylindrical Lock,handel,tower bolt ,approved equivalent make SS ball bearing hinges of quivalent make of aproved make,2 no floor mounted SS door stoper ect.complete as per drawing. Make: Kutty,Sharon, Trojan. Accesseorice Make: Dorma, Godrej.1.5mm thk Laminate Basic Cost:810/M2 . |
| 74 | Providing Drinking Arrangements(Sub Estimate) |
| 75 | Dismantling the Existing Damagedcement Plasteringincluding allchages etc for complete |
| 76 | Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth,earth mixed with small sized boulders and hard gravelly soil as per SS 20B |
| 77 | Collection and supply of sandand filling in to the basement including cost and conveyanceto the siteand all labour charges for filling as per standard speecifications |
| 78 | Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc completefor 10 cum. |
| 79 | Brikc work in CM 1:5 mix usihg country bricks of size 8¾x4¼x2¼ including cost and conveyance and all other labour charges etc., completed |
| 80 | Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc completefor 10 cum. |
| 81 | Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed |
| 82 | Providing granolithicfloor finish in cement concrete 1:2:4 mix using 10-12mm ISS metal to 25mm thick including cost and conveyance of all materials to site and all labour charges for mixing, laying, curing etc complete for 10 cum. |
| 83 | Dadooing walls Plain Galzed tiles of size 150x150x6mm cost and conveyance of all materials to site and all labour charges etc completefor10 Sqm |
| 84 | Provision for PVC Pipe,Tank and Tap arrangements |
| 85 | Provision for 15Amps Socket SD 40 |
| 86 | Provision for EB Box Cover |
| 87 | Provision for String Bhandle |
| 88 | Provision for Informatio Board |
| 89 | Povision For Name Board |
| 90 | c.Repairs to PUM SchoolEast Facing R C C Building at Mainroad Campus |
| 91 | Dismantling the existing Damaged Grano floor area including all labour charges etc., completed |
| 92 | Dismantling the existing Damagedplastering includingall labour charges etc., completed |
| 93 | Providing granolethic floor finish in cement concrete 1:2:4 mix using 10-12mmISS metal to 25mm thick including cost and conveyance of all materials to site and all labour charges for mixing, laying, curing etc complete for 10 cum |
| 94 | White washing two coats using shell lime including cost of materils and all labour charges etc., completed |
| 95 | DistemberingOne coat with best approvde distembering including cost of materils and all labour charges etc., completed |
| 96 | Exterior Emulsiontwo coats with best approvde Exterior Plastic Emulsionincluding cost of materils and all labour charges etc., completed |
| 97 | Painting two coats over oid iron works using ready mixed enamel paintincluding cost of materils and all labour charges etc., completed |
| 98 | Painting with Black Board Painting with Ready mixed Black board painting including cost of materils and all labour charges etc., completed |
| 99 | Provision for Bala Painting |
| 100 | Providing Cub boardArrangements(Sub Estimate) |
| 101 | Brikc work in CM 1:5 mix usihg country bricks of size 8¾x4¼x2¼ including cost and conveyance and all other labour charges etc., completed |
| 102 | Supplying and fixing following thickness of cuddapah slab for cupboard |
| 103 | Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed |
| 104 | Distembertwo coats with best approvdeincluding cost of materils and all labour charges etc., completed |
| 105 | Providing Chappal Rack Arrangements(Sub Estimate) |
| 106 | Brikc work in CM 1:5 mix usihg country bricks of size 8¾x4¼x2¼ including cost and conveyance and all other labour charges etc., completed |
| 107 | Supplying and fixing following thickness of cuddapah slab for cupboard |
| 108 | Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed |
| 109 | Distembertwo coats with best approvdeincluding cost of materils and all labour charges etc., completed |
| 110 | Providing for Teachers Cub Board (Sub Estimate) |
| 111 | Brikc work in CM 1:5 mix usihg country bricks of size 8¾x4¼x2¼ including cost and conveyance and all other labour charges etc., completed |
| 112 | Supplying and fixing following thickness of cuddapah slab for cupboard |
| 113 | Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed |
| 114 | Distembertwo coats with best approvdeincluding cost of materils and all labour charges etc., completed |
| 115 | Supply & Fixing of 35mm thk.single leaf high density interior grade marine plywood shutters pasted both sides 1.5mm thk.laminate approved design with 35x12mm T.W.lipping on all edges with necessary adhesives and CP screws complying with standard specification.The cost is inclusive of 1 no cylindrical Lock,handel,tower bolt ,approved equivalent make SS ball bearing hinges of quivalent make of aproved make,2 no floor mounted SS door stoper ect.complete as per drawing. Make: Kutty,Sharon, Trojan. Accesseorice Make: Dorma, Godrej.1.5mm thk Laminate Basic Cost:810/M2 . |
| 116 | Provision for 15Amps Socket SD 40 |
| 117 | Provision for RWH |
| 118 | Provision for String Bhandle |
| 119 | Provision for Informatio Board |
| 120 | Provision for Name board |
| 121 | d.Repairs to PUM School Toilet(Girls) at Main road Campus, |
| 122 | Dismantaling of Wall Plastering Including all labour Charges and removing depris from the work site etc, complete.,… |
| 123 | Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc completefor 10 cum. |
| 124 | Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed |
| 125 | Paving the Floor with scratch proof ceramic tiles of size 305x305x6mm includingcost and all other labour charges etc., completed |
| 126 | Dadooing of walls colour glazed Tiles of size300mmx200mmx6mm including all cost andconvenyence to Site and all labour charges etccomplete,. |
| 127 | DistemperingTwo coatsover priming coatinculding cost and conveyance of all materials to site and all loboure charges etccomplete |
| 128 | Exterior emulsion two coatsover priming coatinculding cost and conveyance of all materials to site and all loboure charges etccomplete Exterior emulsion two coatsover priming coatinculding cost and conveyance of all materials to site and all loboure charges etccomplete |
| 129 | Painting two coats over Old Iron doors, windows, ventilators, window bars, balustrades etc., withbest approved best quality of synthetic enamel paint of approved colour over the existing priming coat etc., complete complying with sta |
| 130 | Precast Slab for Septic Tank |
| 131 | Towards Septic tank Cleaning Charges |
| 132 | Provision for Name board charges etc., |
| 133 | e.Repairs to PUM School Toilet (Boys-II) main road Campus |
| 134 | Dismantling the existing Damaged Grano floor area including all labour charges etc., completed |
| 135 | Dismantaling of Wall Plastering Including all labour Charges and removing depris from the work site etc, complete.,… |
| 136 | Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed |
| 137 | Paving the Floor with scratch proof ceramic tiles of size 305x305x6mm includingcost and all other labour charges etc., completed |
| 138 | Dadooing of walls colour glazed Tiles of size300mmx200mmx6mm including all cost andconvenyence to Site and all labour charges etccomplete,. |
| 139 | Distemberingtwo coats with best approvde distembering including cost of materils and all labour charges etc., completed |
| 140 | Exterior Emulsiontwo coats with best approvde Exterior Plastic Emulsionincluding cost of materils and all labour charges etc., completed |
| 141 | Painting two coats over oid iron works using ready mixed enamel paintincluding cost of materils and all labour charges etc., completed |
| 142 | Towards Septic tank Cleaning Charges |
| 143 | Provision for Sanitary Arrangements |
| 144 | Towards Door Repair Charges |
| 145 | Provision for Name board |
| 146 | f. Repairs to PUM School (Common) Main road Campus |
| 147 | Dismantling the existing Damaged Grano floor area including all labour charges etc., completed |
| 148 | Dismantaling of Wall Plastering Including all labour Charges and removing depris from the work site etc, complete.,… |
| 149 | Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed |
| 150 | Paving the Floor with scratch proof ceramic tiles of size 305x305x6mm includingcost and all other labour charges etc., completed |
| 151 | Dadooing of walls colour glazed Tiles of size300mmx200mmx6mm including all cost andconvenyence to Site and all labour charges etccomplete,. |
| 152 | Distemberingtwo coats with best approvde distembering including cost of materils and all labour charges etc., completed |
| 153 | Exterior Emulsiontwo coats with best approvde Exterior Plastic Emulsionincluding cost of materils and all labour charges etc., completed |
| 154 | Painting two coats over oid iron works using ready mixed enamel paintincluding cost of materils and all labour charges etc., completed |
| 155 | Provision for EWC etc., |
| 156 | Provision IWC etc., |
| 157 | Provision for Supply of Toilet Door |
| 158 | Provision for Sanitary Arrangements |
| 159 | Provision for Name board |
| 160 | g.Repairs to PUM School Toilet(BOYS) Main Road Campus |
| 161 | Dismantling the existing Damaged Grano floor area including all labour charges etc., completed |
| 162 | Dismantaling of Wall Plastering Including all labour Charges and removing depris from the work site etc, complete.,… |
| 163 | Platering with CM 1:5 mix, 12mm thick including cost and conveynace and all laour charges etc., completed |
| 164 | Paving the Floor with scratch proof ceramic tiles of size 305x305x6mm includingcost and all other labour charges etc., completed |
| 165 | Dadooing of walls colour glazed Tiles of size300mmx200mmx6mm including all cost andconvenyence to Site and all labour charges etccomplete,. |
| 166 | Distemberingtwo coats with best approvde distembering including cost of materils and all labour charges etc., completed |
| 167 | Exterior Emulsiontwo coats with best approvde Exterior Plastic Emulsionincluding cost of materils and all labour charges etc., completed |
| 168 | Painting two coats over oid iron works using ready mixed enamel paintincluding cost of materils and all labour charges etc., completed |
| 169 | Provision for Septic Tank Cleaning Charges |
| 170 | Provision for Door Repair |
| 171 | Provision for Name board |
| 172 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \"BB\" for all works in this package} |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender