| 1 | Earthwork in excavation of foundation trenches or drains all the sorts of soil (including mixed soil but excluding literate or sand stone) including removing. Spreading or stacking the spoil with in a lead of 75 m. as directed. The items include necessary trimming the sides of trenches leveling and ramming the bottom bailing out water as required complete.Depth of excavation not exceeding 1500 mm. |
| 2 | Earth work in filling in foundation trenches or plinth with good earth, in layers not exceeding 150 mm. including watering and ramming etc. layer by layer complete. (Payment to be made on the basis of measurement of finished quantity of work)(a) With earth obtained from excavation of foundation. |
| 3 | Clearing compound premises of shurbs, plants, jungles etc. by cutting and removing as directed (Specific permission of Engineer-in-Charge prior to execution will be necessary). (Payment to be made on area cleared) |
| 4 | Filling in foundation or plinth by silver sand in layers not exceeding 150 mm as directed and consolidating the same by thorough saturation with water, ramming complete including the cost of supply of sand. (payment to be made on measurement of finished quantity) |
| 5 | Cement concrete with graded stone ballast (40 mm size excluding shuttering) In ground floor(A) [Pakur Variety](a) 1:3:6 proportion |
| 6 | Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any, in ground floor as per relevant IS codes.(i) Pakur Variety |
| 7 | Ordinary Cement concrete (mix 1:2:4) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement,if any, in ground floor as per relevant IS codes. |
| 8 | Reinforcement for reinforced concrete work in all sorts of structure including all distribution bars , stirrups , binders etc including supply of rods initial straightening and removal of loose rust (if necessary) cutting to requisite length, hooking and binding to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection complete as per drawing and direction.(a) For works in foundation, basement and upto roof of ground floor/upto 4 m(i) Tor steel/Mild Steel |
| 9 | 125 mm. thick brick work with 1st class bricks in cement mortar (1:4) in ground floor. i)In super structure ground floor. |
| 10 | Brick work with 1st class bricks in cement mortar (1:4)(a)In foundation and plinth |
| 11 | Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand. |
| 12 | Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface](i) With 1:6 cement mortar(b) 15 mm thick plaster |
| 13 | Neat cement punning about 1.5mm. thick in wall, dado, window sills, floor, drain etc. |
| 14 | M.S. structural works in columns, beams etc. with simple rolledstructural members (e.g. joists, angle, channel sections conforming to IS: 226, IS: 808 & SP (6)- 1964 connected to one another with bracket, gussets, cleats as per design, direction of Engineer-incharge complete including cutting to requisite shape and length,fabrication with necessary bolting, metal arc welding conforming to IS: 816- 1969 & IS: 1995 using electrodes of approved make and brand conforming to IS:814- 2004, haulage, hoisting and erection all complete. The rate includes the cost of rolled steel section, consumables such as electrodes, gas and hire charge of all tools and plants and labour required for the work including all incidental chages such as electricity charges, labour insurance charges etc. Payment to be made on the basis of calculated weight of structural members only in finished work as per IS specified weight. Payment for gusset, bracket, cleat, rivets, bolts and nuts may be make by adding the actual weight of such items with the weight of finished structural members or 7% of weight for finished structural members weighing not less than 22.5 Kg. / m. or 15 % of weight for finished structal members weighing less than 22.5 Kg. / m. may be increased allow for bracket, cleat, rivet, bolts and nuts etc. and no seperate payment being made for these items, as per direction of Engineer In Charge. The rates are considered for a height of erection 8m. / 2nd floor level from the ground. Add 1.5% extra over the rate for each additional floor or 4m. beyond initiial 8m. or part thereof. I) For structural members of specified sections weighing less thanwasher or screws etc. (length of straight not less than 230mm). |
| 15 | Applying Exterior grade Acrylic Primer of approved quality and brand on plastered or cencrete surface old or new surface to receive Distemper/ Acrylic emulsion paint including scraping and preparing the surface throughly, complete as per manufacturer\"s specification and as per direction of the EIC.(In Ground Floor)One coati) Water based interior grade Acrylic Primer |
| 16 | Priming one coat on steel or other metal surface with synthetic oil bound primer of approved quality including smoothening surfaces by sand papering etc. |
| 17 | Protective and Decorative Acrylic exterior emulsion paint of approved quality, as per manufacturer\"s specification and as per direction of Engineer-in-Charge to be applied over acrylic primer as required. The rate includes cost of material, labour, scaffolding and all incidental charges but excluding the cost ofprimer. in ground floor two coat normal acrylic emulsion |
| 18 | (A) Painting with best quality synthetic enamel paint of approved make and brand including smoothening surface by sand papering etc. including using of approved putty etc. on the surface, if necessary :(b) On steel or other metal surface :With super gloss (hi-gloss)-(iv) Two coats (with any shade except white) |
| 19 | Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor).(a) 25 mm to 30 mm thick wooden shuttering as per decision & direction of Engineer-In-Charge. |
| 20 | (f) 25 mm to 30 mm shuttering without staging in foundation |
| 21 | (a) Supplying, fitting galvanised 3 ply 12 gauge / 4 points line of barbared wire fencing (holes already made in the body of the post) or fixed by staples tightening and fixing the wires in taut condition with straining bolts including the cost of cutting and of lapping joints in the wire as necessary but excluding the cost of galvanised staples, straining bolt and binding wire as necessary.(Payment to be made on lengh of individual lines of wire.) |
| 22 | Supplying galvanised straining bolts (with eye at one end with double nuts and washers) fitted and fixed complete.(i) 10 mm dia.(b) 200 mm. |
| 23 | Supplying galvanised staples fitted and fixed complete.(a) 19 mm to 25 mm size |
| 24 | M.S. gate of Jail type as per approved design made of strong M.S. frame work, intermediate stiffeners and round / square bars or angles. M.S. sheet (not less than 14 gauge) gussets, cleats etc. including necessary riveting, bolting, welding, locking and hanging arrangements, fitting and fixing complete as per direction of the Engineer-in - charge.In ground floor. |
| 25 | Dismantling all types of masonry excepting cementconcrete plain or reinforced, stacking serviceablematerials at site and removing rubbish as directedwithin a lead of 75 m. in gr floor including roof |
| 26 | Dismantling all types of plain cement concreteworks, stacking serviceable materials at site andremoving rubbish as directed within a lead of 75m. In gr floor including roof upto 150mm thk |
| 27 | Stripping off worn out plaster and raking outjoints of walls, celings etc. upto any height and inany floor including removing rubbish within alead of 75m as directed. |
| 28 | Dismantling R.C. floor, roof, beams etc. includingcutting rods and removing rubbish as directedwithin a lead of 75 m. including stacking of steelbars |