Uttar Pradesh Jal Nigam-UPJN has published Tender For I & D And 13 Mld Stp Works At Vrindavan City, District Mathura Under Namami Gange Programme. Submission Date for this Tender is 26-06-2023. Sewage Treatment Plant Tenders in vrindavan Uttar Pradesh. Bidders can get complete Tender details and download the document.
Sr No | CorrigendumDate | Corrignedum | CorrigendumType | NewSubmissionDate |
1 | 10-May-2023 | Web link for Pre bid meeting on 11.05.2023 | Other | 26-05-2023 |
2 | 25-May-2023 | Extension of date | Date | 16-06-2023 |
3 | 12-Jun-2023 | Extension of bid submission date | Date | 26-06-2023 |
Sl. No. | Item Description |
1 | Design,development,supplyofequipment, erection of equipment, civil, electro mechanical andinstrumentationworks,including testing, commissioning of 13 MLD STP inVrindavan, District Mathura on open technology with disinfection & tertiary treatment, provision for handling co treatment of septage/faecal sludge (10 KLD) and allied works. The scope of work also includes providing all material, labour T&P etc. and construction of electrical sub station, D.G. Sets,substation building, meter room, panel rooms with DG sets, transformers and switch gears, Construction of transformer yard, Platform for D.G., shed over the generators,fully furnished administrative building having fully functional testing laboratory, PLC/SCADA Rooms, Power Generation building, Blower building, sludge handling system & other building required for technology proposed. OCEMS system at inlet & outlet of STP and master control station (MCS) at STP. Conference room suitable for 15 people, 4 rooms with a attached toilet for supervisory staff and a toilet block, drinking water cooler, all office rooms and conference room (Air Conditioned). The scope also including. Ancillary works like R.C.C. approch road 235 m length approximate 3.75 m width with 1.5 m wide inter locking shoulder each side from, Saubharivan road to proposed STP entry gate, boundary wall of campus with gate, staff quarter type II (06 Nos), office cum resident building for jal nigam officers type IV (1 No.), internal C.C. roads 3.75 m wide and 2.0 m wide C.C. path ways, water supply arrangement, fire fighting arrangement, land scaping, site development & require furniture etc. and other works as defined in bid documents. |
2 | Break-up of price of item 1 above. |
3 | Civil and Structural Works (including that required for disposal and reuse of treated effluent) |
4 | Supply, Installation, testing and commissioning of Electro – mechanical and Instrumentation equipment and accessories including equipment for electricity generation from solar photovoltaic arrangement (including required for disposal and reuse of treatet effluent) . |
5 | Ancillary works like approach roads Saubharivan to proposed STP Gate approximate length 235 m width 3.75 m wide shoulder each side, boundary wall of campus with gate, staff quarter type II (6 Nos), office cum resident building for jal nigam officers type IV (01 No.)internal C.C. roads 3.75 m wide and 2.0 m wide C.C. path ways, Provision for construction of Co-treatment facility in Vrindavan which includes infrasturcture like, collection tank, fine/coarse screen sitting chamber, equilization tank, filter press/belt press/screw press for dewatering etc. of septage/faecal sludge (10 KLD), water supply arrangement, fire fighting arrangement, land scaping, site development & require furniture etc. |
6 | Implementation of Environmental Management Plan and ESHS-MSIP, as per Appendix 1 of Schedule 2 (Design Build Services). |
7 | I & D Works |
8 | Tapping and Diversion Structure Making of earthen bund across the existing drain for diversion of flow. |
9 | 0.00 to 1.50 M BGL |
10 | Chaitanya Vihar Drain |
11 | Sunrakh Village Drain |
12 | Excavationofearth inordinary soil(loan, clayandsand)fordiversionofdrain, chamber for depth upto 1.50m below G.L. including watering, ramming, dressing, filling back between wall and foundation and disposal of surplus earth with 50M including supply of all labours and T&P etc. required for the proper completion of work. |
13 | 0.00 to 1.50 M BGL |
14 | Chaitanya Vihar Drain |
15 | Sunrakh Village Drain |
16 | Supply of 40mm stone ballast in to trench following drain including supply of all materials, labours and T&P etc. required for the proper completion of work. |
17 | Chaitanya Vihar Drain |
18 | Sunrakh Village Drain |
19 | Concrete in 1:4:8 with cement, coarse sand and 40mm gauge stone ballast including supply of all materials, labours and T&P etc. required for the proper completion of work for nala bed as per direction of E/I. |
20 | Chaitanya Vihar Drain |
21 | Sunrakh Village Drain |
22 | Cement Concrete 1:2:4 in cement coarse sand & stone grit 12 to 20 mm guage including supply of all material labour and T&P etc. required for proper completion of work. For making of nala bed including its toe wall at starting and end point of pucca nala bed as per proposed drawing and as per direction of E/I |
23 | Chaitanya Vihar Drain |
24 | Sunrakh Village Drain |
25 | Reinforced cement concrete 1:1.5:3 with cement coarse sand and 20mm stone grit in foundation footing, vertical wall, slab etc. excluding supply of reinforcement and its bending but including its haunching and toe wall at starting and end point of pucca nala bed as per proposed drawingfixing,bindingthesamewith0.50mm thickbindingwire(tobesuppliedbythe contractor) including of all materials, labour, andT&Petc.requiredfortheproper completion of work as per direction of E/I. |
26 | Chaitanya Vihar Drain |
27 | Sunrakh Village Drain |
28 | Supply, Installation, Testing and Commissioning of CI Open Channel Sluice Gates, Manually operated, Rising Spindle type suitable for mounting in between two parallel walls of an Open Channel. Water sealing shall be provided at two vertical sides and bottom side of gate aperture by means of rubber seal, mounted on gate slide and having forced contact with gate aperture. The gate shall be designed in such a manner, so that it can be operated at 2 meter head. Gate frame & Shutter of CI Grade IS 210 FG 260, Head Stock IS 210 Grade FG 260, Hinge Pin SS ASTMA276, Yoke IS MS 2062, Flush Bottom Seal Support Bar of SS ASTM A276 , Stem Operating Nut ASTM A276., Duly tested for tensile strength, Chemical testing and tested Shop tested for over all dimensions as per approved GA drawing complete in all respect as per specification and direction of Engineer for following PEAK FLOW up to 3m channel depth. Upto 3.76 MLD. |
29 | 0.50 x 0.75 m size (indicative size) |
30 | 3.00 x 2.00 m size (indicative size) |
31 | Supply, fabrication, fixing and Testing of stainless steel (SS-316) Manual Coarse Bar screen with flat bar 50mm X 10mm, Spacing of bars 50mm suitable for mounting in channel of specified size with inclination not more than 45 degree and a movable covered containers of 1 cum capacity complete in all respect as per technical specification and the direction of the Engineer. Manually Raked Coarse Bar Screen with 50 mm clear opening for following PEAK FLOW and upto 3m channel depth. |
32 | Mild steel or iron work in plane work such as in R.C.C work (When not included in over all rates) wrought to the required shape as necessary including bending for the completion of work and including supply of all materials, labours, T&P etc. complete. 1.5% of Total R.C.C quantity. |
33 | Chaitanya Vihar Drain and Sunrakh Village Drain |
34 | Renovation of MPS (at Kalideh) |
35 | Renovation of wet well including all works |
36 | Construction of Screen Channels |
37 | Construction of Staff quarter type -II (02 No.), PLC/SCADA Rooms, construction of sub station building,transformar yard, Generator Building, Renovation/New construction of boundary wall as required, Security room, internal C.C. road 3.75 m wide, land scaping, site development and required furniture etc. |
38 | Laying of Gravity Intercepting Sewer (Open Trench Method) Supply & laying of following sizes of R.C.C. Hume pipe NP3 Class Socket spigot pipes, rubber rings jointing materials and specials from store to the work lowering the same in to the trenches up to depth as specified below G.L. true to alignment and gradient including barricading of site, traffic diversion arrangement, dismantling of roads, mechanical/ manual excavation, dewatering (as per requirement), shoring & timbering with mild steel/ wooden planks, construction of required class beddings, construction of RCC/ brick masonry circular/ rectangular or precast manholes in accordance with the provisions laid down in latest version of IS 4111 (Part 1), refilling of trenches with proper compaction including disposal of surplus earth with in 8 km radius, temporary reinstatement of dismantled roads, cost of all jointing material, testing & commissioning etc. complete including supply of all material, labour, T&P etc. required for proper completion of work. |
39 | Chaitanya Vihar Drain 700 mm dia NP3 Pipe 3.00 to 4.500m BGL |
40 | Sunrakh Village Drain 250 mm dia NP3 Pipe 1.50 to 3.000m BGL |
41 | 250 mm dia NP3 Pipe 3.00 to 4.500m BGL |
42 | 250 mm dia NP3 Pipe 4.50 to 6.000m BGL |
43 | Sewage Pumping Stations for E&M works 13.50 MLD and Civil work 22.50 MLD Peak Capacity Construction of MPS |
44 | Construction of wet well |
45 | Construction of Screen Channels |
46 | Valve chamber |
47 | Constructionofspecialmanholechamberof 2.00mdiameter,anditsinterconnectionwith adjacentmanholeofthesewerlinewiththe appropriate size of sewer pipe of RCC NP3 pipe. |
48 | Treated Water Sump for E&M works 29.25 MLD and Civil work 29.25 MLD Peak Capacity with allied works. |
49 | Laying of Rising main |
50 | SupplyoffollowingdiameterDIK9Socket/spigot pipes, rubber rings jointing materials and specials from store to the work lowering the same in to the trenches up to depth as specified below G.L.trueto alignment dismantlingof roads, mechanical/ manual excavation, dewatering, shoring & timbering, if required,with mild steel/wooden planks,refilling of trenches with proper compactionincludingdisposalofsurplusearth with in 8 km radius, temporary reinstatement of dismantled roads, cost of all jointing material, testing & commissioning including supply of all material, labour, T&P etc. required for proper completion of work including supply & fixing of same size sluice valves & 100/150 mm size air valves. |
51 | 400 mm DI K9 pipe from MPS to STP |
52 | 500 mm DI K9 pipe from Kalideh MPS to STP |
53 | 600 mm DI K9 pipe from treated water sump well to disposal point |
54 | E/M Works at New MPS |
55 | Supply, installation, testing and commissioning of following items/equipment/material with all accessories, labor, material, T&P etc. complete as per IS/applicable codes, CPHEEO Manual and as specified in bid document for proper completion of work: |
56 | Electrical Actuator Operated Sluice Gates for screen chambers and by pass arrangement. |
57 | Manually cleaned coarse bar screen with ventilation arrangement. |
58 | Mechanically cleand coarse bar screen with ventilation arrangement and screw conveyor cum compactor. |
59 | Non clog sewage Submersible Pumping Plants each of peak/2 capacity with guide rails, lifting chain, Auto coupling system etc. (peak flow pumps). |
60 | Non clog sewage Submersible Pumping Plants each of peak/4 capacity with guide rails, lifting chain, Auto coupling system etc. (non-peak flow pumps). |
61 | C.I.D.F. actuator operated sluice valves for individual delivery line of peak flow pumps |
62 | C.I.D.F. actuator operated sluice valves for individual delivery line of non peak flow pumps |
63 | C.I.D.F. actuator operated sluice valves for Common Header and by pass. |
64 | C.I.D.F. Reflex valves for individual delivery line of peak flow pumps |
65 | C.I.D.F. Reflex valves for individual delivery line of non peak flow pumps |
66 | D.I.D.F./C.I.D.F. main piping including riser pipes, delivery piping, dismantling joints, Tees, Bends, Duckfoot bends, distance pieces and other specials, nut bolts, washers, rubber packing, insertions, jointing material, other required hardware etc. |
67 | Painting on pumps, piping and valves complete |
68 | Soft Starters for peak flow pumps |
69 | Soft Starters for non peak flow pumps |
70 | Direct online Electro-magnetic flowmeter with CVT, control cables etc. |
71 | Mono Rail Traveling Trolley with chain pulley block (EOT) of required capacity, travel and lift. |
72 | Supply and fixing of tools & tackles, fire extinguishers -6 Nos., electric resistance rubber sheets- as per requirement, steel chairs- 4 nos., steel almirah- 1no., fire bucket with stand- 1 set, steel tubular table- 1no., safety equipment(Gas Masks, rope, safety belt, first aid kit, oxygen cylinder etc. as recommended by CPHEEO) etc. |
73 | Internal-external electrification & lighting for panel rooms, pump house, staff quarter, campus etc. with required decorative fixtures, poles, lamps, distribution boards, wiring, points, LED, fluorescent lamps, fans, exhaust fans, fittings etc. |
74 | Power wiring/cable of pumping plants(from LT panel to starter and from starter to pumping plants) with end termination,cable jointing, chequered plates etc. |
75 | Aluminium Junction Boxes for cabling between starter and pumping plant |
76 | L.T. Panel of SPS with APFC panel having required no. of incomings, outgoings, bus couplers, relays, MFMs etc. |
77 | Power wiring/cable from PCC/PMCC Panel of STP to MCC LT panel of SPS with end termination,cable jointing, chequered plates etc. |
78 | Automation-PLC/SCADA system for sewage pumping station (SPS) with all instruments (pressure transmitters for individual pump as well as common header, LT for sump, DLT for screens, etc.), complete cabeling/wiring, HMI, CCTV Cameras, JBs, LPBS" etc. |
79 | E/M Works at Treated Effluent Pumping Station (TEPS) |
80 | Supply, installation, testing and commissioning of following items/equipment/material with all accessories, labor, material, T&P etc. complete as per IS/applicable codes, CPHEEO Manual and as specified in bid document for proper completion of work: |
81 | Non clog sewage Submersible Pumping Plants each of peak/2 capacity with guide rails, lifting chain, Auto coupling system etc. |
82 | C.I.D.F. actuator operated sluice valves for individual delivery line of pumps |
83 | C.I.D.F. actuator operated sluice valves for Common Header and by pass |
84 | C.I.D.F. Reflex valves for individual delivery line of peak flow pumps |
85 | D.I.D.F./C.I.D.F. main piping including riser pipes, delivery piping, dismantling joints, Tees, Bends, Duckfoot bends, distance pieces and other specials, nut bolts, washers, rubber packing, insertions, jointing material, other required hardware etc. |
86 | Painting on pumps, piping and valves complete. |
87 | Soft Starters for peak flow pumps. |
88 | Direct online Electro-magnetic flowmeter with CVT, control cables etc. |
89 | Mono Rail Traveling Trolley with chain pulley block (EOT) of required capacity, travel and lift |
90 | Supply and fixing of tools & tackles, fire extinguishers -2 Nos., electric resistance rubber sheets- as per requirement, steel chairs- 4 nos., steel almirah- 1no., fire bucket with stand- 1 set, steel tubular table- 1no., safety equipment(Gas Masks, rope, safety belt, first aid kit, oxygen cylinder etc. as recommended by CPHEEO) etc. |
91 | Internal-external electrification & lighting for panel rooms, pump house, staff quarter, campus etc. with required decorative fixtures, poles, lamps, distribution boards, wiring, points, LED, fluorescent lamps, fans, exhaust fans, fittings etc. |
92 | Power wiring/cable of pumping plants(from LT panel to starter and from starter to pumping plants) with end termination,cable jointing, chequered plates etc. |
93 | Aluminium Junction Boxes for cabling between starter and pumping plant |
94 | L.T. Panel of SPS with APFC panel having required no. of incomings, outgoings, bus couplers, relays, MFMs etc. |
95 | Power wiring/cable from PCC/PMCC Panel of STP to MCC LT panel of SPS with end termination,cable jointing, chequered plates etc. |
96 | Automation-PLC/SCADA system for sewage pumping station (SPS) with all instruments (pressure transmitters for individual pump as well as common header, LT for sump, DLT for screens, etc.), complete cabeling/wiring, HMI, CCTV Cameras, JBs, LPBS" etc. |
97 | E/M Works at Kalideh MPS |
98 | Supply, installation, testing and commissioning of following items/equipment/material with all accessories, labor, material, T&P etc. complete as per IS/applicable codes, CPHEEO Manual and as specified in bid document for proper completion of work. |
99 | Electrical Actuator Operated Sluice Gates for screen chambers and by pass arrangement. |
100 | Manually cleaned coarse bar screen with ventilation arrangement |
101 | Mechanically cleand coarse bar screen with ventilation arrangement and screw conveyor cum compactor. |
102 | Non clog sewage Submersible Pumping Plants each of peak/2 capacity with guide rails, lifting chain, Auto coupling system etc. (peak flow pumps). |
103 | Non clog sewage Submersible Pumping Plants each of peak/4 capacity with guide rails, lifting chain, Auto coupling system etc. (non-peak flow pumps). |
104 | C.I.D.F. actuator operated sluice valves for individual delivery line of peak flow pumps. |
105 | C.I.D.F. actuator operated sluice valves for individual delivery line of non peak flow pumps. |
106 | C.I.D.F. actuator operated sluice valves for Common Header and by pass. |
107 | C.I.D.F. Reflex valves for individual delivery line of peak flow pumps |
108 | C.I.D.F. Reflex valves for individual delivery line of non peak flow pumps. |
109 | D.I.D.F./C.I.D.F. main piping including riser pipes, delivery piping, dismantling joints, Tees, Bends, Duckfoot bends, distance pieces and other specials, nut bolts, washers, rubber packing, insertions, jointing material, other required hardware etc. |
110 | Painting on pumps, piping and valves complete. |
111 | Soft Starters for peak flow pumps. |
112 | Soft Starters for non peak flow pumps. |
113 | Direct online Electro-magnetic flowmeter with CVT, control cables etc. |
114 | Mono Rail Traveling Trolley with chain pulley block (EOT) of required capacity, travel and lift. |
115 | Copper Wound Electric Transformers (11kV/0.415kV) (01W+01S) with transformer yard works. |
116 | DG set(s) (415V) with AMF & Control/Control-Synchronization panels, batteries etc. |
117 | 11 kV HT VCB Panel (01 incoming+02 outgoing) with DC supply system. |
118 | HT Power wiring./cabling from UPPCL meter to HT panel and from HT panel to transformers with cable jointing, end termination, chequered plate etc. |
119 | Earthing of all equipment & switchgear and lightening protection. |
120 | Supply and fixing of tools & tackles, fire extinguishers -6 Nos., electric resistance rubber sheets- as per requirement, steel chairs- 4 nos., steel almirah- 1no., fire bucket with stand- 1 set, steel tubular table- 1no., safety equipment(Gas Masks, rope, safety belt, first aid kit, oxygen cylinder etc. as recommended by CPHEEO) etc. |
121 | Internal-external electrification & lighting for panel rooms, pump house, staff quarter, campus etc. with required decorative fixtures, poles, lamps, distribution boards, wiring, points, LED, fluorescent lamps, fans, exhaust fans, fittings etc. |
122 | Power wiring/cable of pumping plants(from LT panel to starter and from starter to pumping plants) with end termination,cable jointing, chequered plates etc. |
123 | Aluminium Junction Boxes for cabling between starter and pumping plant |
124 | L.T. Panel of SPS with APFC panel having required no. of incomings, outgoings, bus couplers, relays, MFMs etc. |
125 | Power wiring/cable from Transformers & DG Set(s) Panels to LT panel of SPS with end termination,cable jointing, chequered plates etc. |
126 | Automation-PLC/SCADA system for sewage pumping station (SPS) with all instruments (pressure transmitters for individual pump as well as common header, LT for sump, DLT for screens, etc.), complete cabeling/wiring, HMI, CCTV Cameras, JBs, LPBS" etc. |
127 | Dismantling of existing E&M equipment at the Kalideh SPS and handing over to Jal Kal Vibhag, Mathura. |
128 | Trial-run of the Pumping Stations and STP for three months complete in all respect as specified in tender document. |
129 | Operation and Maintenance for 15 Years |
130 | STP (PART A) Operation and Maintenance Price for Treatment of threshold sewage flow of 10 MLD at STP & Co- Treatment facility (10 KLD) & TEPS with all civil, electrical-mechanical and instrumentation works, effluent chanel, appurtment and other allied works for 15 years as specified in tender document and as per norms of CPHEEO manual on Sewerage and Sewage Treatment System-2013 (Bidder is required to quote the year wisse O&M price for 15 years |
131 | 1st year |
132 | 2nd year |
133 | 3rd year |
134 | 4th year |
135 | 5th year |
136 | 6th year |
137 | 7th year |
138 | 8th year |
139 | 9th year |
140 | 10th year |
141 | 11th year |
142 | 12th year |
143 | 13th year |
144 | 14th year |
145 | 15th year |
146 | PART B AdditionalOperation and Maintenance Price for Treatment of additional sewage in excess of the threshold on per MLD basisat STP & Co- Treatment facility (10 KLD) with all civil, electrical-mechanical and instrumentation works, effluent chanel, appurtenant and other allied works for 15 years as specified in tender document and as per norms of CPHEEO manual on Sewerage and Sewage Treatment System-2013 |
147 | 1st year |
148 | 2nd year |
149 | 3rd year |
150 | 4th year |
151 | 5th year |
152 | 6th year |
153 | 7th year |
154 | 8th year |
155 | 9th year |
156 | 10th year |
157 | 11th year |
158 | 12th year |
159 | 13th year |
160 | 14th year |
161 | 15th year |
162 | Total O&M Price- assuming indicative Sewage Flow reaching the STP C=a+b x (x= indicative flow minus threshold sewage flow) |
163 | 1st year (X=10-10=0) |
164 | 2nd year (X=10.21-10=0.21) |
165 | 3rd year (X=10.42-10=0.42) |
166 | 4th year (X=10.63-10=0.63) |
167 | 5th year(X=10.84-10=0.84) |
168 | 6th year(X=11.05-10=1.05) |
169 | 7th year(X=11.26-10=1.26) |
170 | 8th year(X=11.47-10=1.47) |
171 | 9th year (X=11.68-10=1.68) |
172 | 10th year (X=11.89-10=1.89) |
173 | 11th year (X=12.10-10=2.10) |
174 | 12th year (X=12.31-10=2.31) |
175 | 13th year (X=12.52-10=2.52) |
176 | 14th year (X=12.73-10=2.73) |
177 | 15th year (X=13.0-10=3) |
178 | Operation and Maintenance cost of New MPS and rising main with all civil, electrical-mechanical and instrumentation works, appurtment and other allied works for 15 years as specified in tender document and as per norms of CPHEEO manual on Sewerage and Sewage Treatment System-2013 (Bidder is required to quote the year wise O&M price for 15 years |
179 | 1st year |
180 | 2nd year |
181 | 3rd year |
182 | 4th year |
183 | 5th year |
184 | 6th year |
185 | 7th year |
186 | 8th year |
187 | 9th year |
188 | 10th year |
189 | 11th year |
190 | 12th year |
191 | 13th year |
192 | 14th year |
193 | 15th year |
194 | Operation and Maintenance cost of Kalideh MPS and rising main with all civil, electrical-mechanical and instrumentation works, appurtment and other allied works for 15 years as specified in tender document and as per norms of CPHEEO manual on Sewerage and Sewage Treatment System-2013 (Bidder is required to quote the year wise O&M price for 15 years |
195 | 1st year |
196 | 2nd year |
197 | 3rd year |
198 | 4th year |
199 | 5th year |
200 | 6th year |
201 | 7th year |
202 | 8th year |
203 | 9th year |
204 | 10th year |
205 | 11th year |
206 | 12th year |
207 | 13th year |
208 | 14th year |
209 | 15th year |
210 | Operation and Maintenance cost of all I&D works, tapping arrangement, related interceptor sewers with all civil, electrical-mechanical and instrumentation works,appurtment and other allied works for 15 years as specified in tender document and as per norms of CPHEEO manual on Sewerage and Sewage Treatment System-2013 (Bidder is required to quote the year wise O&M price for 15 years |
211 | 1st year |
212 | 2nd year |
213 | 3rd year |
214 | 4th year |
215 | 5th year |
216 | 6th year |
217 | 7th year |
218 | 8th year |
219 | 9th year |
220 | 10th year |
221 | 11th year |
222 | 12th year |
223 | 13th year |
224 | 14th year |
225 | 15th year |
226 | Total O&M Price |
227 | 1st year |
228 | 2nd year |
229 | 3rd year |
230 | 4th year |
231 | 5th year |
232 | 6th year |
233 | 7th year |
234 | 8th year |
235 | 9th year |
236 | 10th year |
237 | 11th year |
238 | 12th year |
239 | 13th year |
240 | 14th year |
241 | 15th year |
242 | NPV of total O&M |
243 | 1st year (NPV Factor-0.909) |
244 | 2nd year(NPV Factor-0.826) |
245 | 3rd year(NPV Factor-0.751) |
246 | 4th year(NPV Factor-0.683) |
247 | 5th year(NPV Factor-0.621) |
248 | 6th year(NPV Factor-0.564) |
249 | 7th year(NPV Factor-0.513) |
250 | 8th year(NPV Factor-0.467) |
251 | 9th year(NPV Factor-0.424) |
252 | 10th year(NPV Factor-0.386) |
253 | 11th year(NPV Factor-0.350) |
254 | 12th year(NPV Factor-0.319) |
255 | 13th year(NPV Factor-0.290) |
256 | 14th year(NPV Factor-0.263) |
257 | 15th year(NPV Factor-0.239) |
258 | Electricity and fuel charges during O&M for 15 Years |
259 | Guaranteed Energy Consumption for 13 MLD STP a At Vrindavan City(Value should be entered in all cell from 28.02 to 28.07. The permissible value of maximum to minimum GEC quoted in cell28.02 to 28.07 should be less than or equal to 1.4) |
260 | For flow< 11.50 MLD and BOD < 135 mg/L |
261 | For flow< 11.50 MLD and BOD > 135 mg/L and < 165 mg/L |
262 | For flow< 11.50 MLD and BOD > 165 mg/L |
263 | For flow> 11.50 MLD and BOD < 135 mg/L |
264 | For flow> 11.50 MLD and BOD > 135 mg/L and < 165 mg/L |
265 | For flow> 11.50 MLD and BOD > 165 mg/L |
266 | STPAverage GEC |
267 | Power Charges for 13 MLD STP at Vrindavan City for Indicative Flow (=172.11 MLD X Unit Consumed/MLD X 365 X 8.5 X 1.3) (Not to be filled by the bidder) |
268 | Guaranteed Energy Consumption for 13 MLD TEPS at Vrindavan City(Value should be entered in all cell from 29.01 to 29.02. The permissible value of maximum to minimum GEC quoted in cell 27.01 to 27.02 should be less than or equal to 1.4) |
269 | For flow< 11.50 MLD |
270 | For flow> 11.50 MLD |
271 | TEPS Average GEC |
272 | Power Charges for 13 MLD TEPS at Vrindavan Cityfor Indicative Flow (=172.11 MLD X Unit Consumed/MLD X365 X 8.5 X 1.2) (Not to be filled by the bidder) |
273 | Guaranteed Energy Consumption for Kalideh MPS at Kalideh, Vrindavan City(Value should be entered in all cell from 30.01 to 30.02. The permissible value of maximum to minimum GEC quoted in cell to 30.01 to 30.02 should be less than or equal to 1.4) |
274 | For flow< 6.50 MLD |
275 | For flow> 6.50 MLD |
276 | Kalideh MPS Average GEC |
277 | Power Charges for Kalideh MPS. At Kalideh, Vrindavan Cityfor Indicative Flow (=96.51 MLD X Unit Consumed/MLD X 365 X 8.5 X 1.2) (Not to be filled by the bidder) |
278 | Guaranteed Energy Consumption for New MPS at STP Campus (Value should be entered in all cell from 31.01 to 31.02.The permissible value of maximum to minimum GEC quoted in cell to 31.01 to 31.02should be less than or equal to 1.4) |
279 | For flow< 5.00 MLD |
280 | For flow> 5.00 MLD |
281 | New MPS Average GEC |
282 | Power Charges forNew MPS for Indicative Flow (=75.60 MLD X Unit Consumed/MLD X 365 X 8.5 X 1.2) (Not to be filled by the bidder) |
283 | Add GST (Excluding Sl.No. 26 to 29 and 31, 32) |
284 | Land requirement (sqm) - 13 MLD STP and New MPS at (Circle rate is Rs 25000 per sq.m.) (Bidder is required to quote the land requirement under column 5 of this row including land required for Solar Power Plant if proposed, subject to lavailable land i.e.12500 sq.m.) |
285 | Land requirement (sqm) - Kalideh MPS at (Circle rate is Rs 15500 per sq.m.) (Bidder is required to quote the land requirement under column 5 of this row including land required for Solar Power Plant if proposed, subject to lavailable land i.e.600 sq.m.) |
286 | Total in Figures (based on NPV of O&M Price and including Land Price) |
287 | Total in Figures (based on actual O&M Price and excluding Land Price) |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy
For Tender Information Services Visit : TenderDetail