Uttranchal Jal Vidyut Nigam Ltd-UJVNL has published Tender For Consultancy Services For Detailed Civil Design And Engineering Including Project Monitoring And Control Of Tiuni Plasu Hydro Electric Project 72Mw On River Tons In District Dehradun, Uttarakhand.. Submission Date for this Tender is 01-07-2023. Consultancy Service Tenders in dakpathar Uttarakhand. Bidders can get complete Tender details and download the document.
Sr No | CorrigendumDate | Corrignedum | CorrigendumType | NewSubmissionDate |
1 | 29-May-2023 | Extension of date | Date | 21-06-2023 |
2 | 06-Jun-2023 | Addendum | Technical Bid | 21-06-2023 |
3 | 06-Jun-2023 | Clarification | Other | 21-06-2023 |
4 | 19-Jun-2023 | Date Extension Notice-2 | Date | 01-07-2023 |
Sl. No. | Item Description |
1 | PART-A (Pre-Construction Stage Consultancy) Submission of Inception Report/Design Review Report, Visit of Expert to site ,Review of Additional Investigation if carried out /Submission of Draft design/ Design Intent memorandum, Preparation of tender document for Civil works including tender level design & drawings, technical specifications, detailed bill of quantities (BoQ) etc., Preparation of tender document for HM works including tender design & drawings, technical specifications, detailed bill of quantities (BoQ) etc. of the HM components for the entire project.(For details, refer relevant clause of Appendix-I) |
2 | PART-B-1 (Construction Stage Consultancy) Submission of Draft design / Carrying out Model Studies. Submission of Draft Drawings / Model Studies report for approval of Client / Issue of excavation and other drawings as required for Main construction/ Q.A. plan / Design / Drawings etc. Issue of Final Detailed Construction Drawing as per construction schedule / Visit of expert at site as and when necessary up to final construction drawing approval stage. Review of the drawings for the HM contractor as and when received and approved thereof. Deployment of Design Coordinator for Co-ordination between Civil / HM and E&M works and on spot revision of drawings during execution of Civil and HM works. Preparation of O&M manual, Preparation of as executed drawings. (For details, refer relevant clause of Appendix-I) |
3 | PART-B-2 (Project Monitoring & Control Services) Project Monitoring & Control Services at site for Civil & HM works for the entire project area of activity (For details refer relevant clause of Appendix-I) |
4 | Team Leader/Coordinator |
5 | Quality Control Engineer |
6 | Field Engineers (Civil) |
7 | Surveyor |
8 | Geologist |
9 | Field Engineers (HM) |
10 | HSE expert |
11 | Draughtsman (Auto cad Operator) |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy