| 1 | Item No. 1 |
| 2 | Running & Maintaining the RRWS Scheme to quantites rated capacity including maining necessary personal such as operator valveman, choukidar & lineman etc. as per requirements of the scheme hand who should all so admibister chemical dose as per directed by engineer-in-charge for period shall be 1 year with raw water pumping of without treatment plant with pumps raw water pumping main leading main ESR BPT etc. complete |
| 3 | Item No. 2 |
| 4 | Rectification of leakages of Raw Water Raising main, pure water gravity main including necessary excavation pipe cutting, dewatering, Joints lowering laying, Jointing of pipe special refilling and giving satisfactory hydraulic test as directed by Engineer in Charge. |
| 5 | a) 200 mm dia PVC6kg/ cm2 |
| 6 | b) 160 mm dia PVC 6kg/ cm2 |
| 7 | c) 140 mm dia PVC 6kg/ cm2 |
| 8 | d) 90 mm dia PVC 6kg/ cm2 |
| 9 | e) 200 mm dia HDPE10kg/ cm2 |
| 10 | f) 160 mm dia HDPE 10kg/ cm2 |
| 11 | g) 140 mm dia HDPE 10kg/ cm2 |
| 12 | h) 90 mm dia HDPE 10kg/ cm2 |
| 13 | Item No.3 |
| 14 | Provision for Keeping clean & maintain WTP site, head work, pump house, ESR, MBR premises, maintain all necessary lighting arrangement , Electrification on WTP & Head Work in satisfactory condition etc. complete. |
| 15 | Item No.4 |
| 16 | Providing and fixing air valve ball etc. complete |
| 17 | a) 75 mm dia PVC air valve ball |
| 18 | b) 90 mm dia PVC air valve ball |
| 19 | Item No.5 |
| 20 | Water sample testing from govt. institution and submit the report of same as per the given instruction of Engr. In-charge etc. complete. |
| 21 | a) Bacterilogical test |
| 22 | b) Chemical test |
| 23 | Item No.6 |
| 24 | Providing and supplying bleaching powder, hydraulic oil , gear box oil,alum & giving test report etc. complete |
| 25 | a) Alum Grade I |
| 26 | b) Bleaching Powder (33% Chlorine available) |
| 27 | Item No.7 |
| 28 | Rectification of leakages of CI Pipe line including necessary excavation pipe cutting, dewatering, Joints lowering laying, Jointing of pipe special refilling and giving satisfactory hydraulic test as directed by Engineer in Charge. |
| 29 | 150 mm dia CI Pipe |
| 30 | Item No.8 |
| 31 | Rewinding of centrifugal pump motor or submersible pump motor of all types and makes with copper wire, overhauling with minor repairs, lubicating of ball bearing & bush bearing and replacing bearing, bushes, screw etc testing for the original speed and no load consumption with gurantee for one year. |
| 32 | 25.00 HP VT PumpAt. Head work |
| 33 | 10.00 HP Monoblock Pump Dubarpeth Line At. WTP |
| 34 | 7.50 HP Monoblock Pump Dongargaon Line At. WTP |
| 35 | 3.00 HP Monoblock pump MBR At. WTP |