Tender For Strengtheningof Bt Road From Chitturnatham Kavalammal Koil To Equvarpalayam Perumal Koil Road Km 0/0-0/690 . 2. Strengtheningof Bt Road From Soorapoondi H/C Road Km 0/0-0/505 In Gummidipoondi Panchayat Union In Thiruvallur District Under Mgsmt
Tender Overview
Project Description
Tender For Strengtheningof Bt Road From Chitturnatham Kavalammal Koil To Equvarpalayam Perumal Koil Road Km 0 / 0-0 / 690 . 2. Strengtheningof Bt Road From Soorapoondi H / C Road Km 0 / 0-0 / 505 In Gummidipoondi Panchayat Union In Thiruvallur District Under Mgsmt 2022-2023
BOQ
| Sl. No. | Item Description |
| 1 | 1.Strengtheningof BT road from Chitturnatham Kavalammal koil to Equvarpalayam Perumal Koil Road Km 0/0-0/690 |
| 2 | Picking the Worn-out BT Surface including incidential charges and cleaning of all labour charges and machinery charges etc,..complet |
| 3 | Km 0/0- 0/690 |
| 4 | Collection and supply of carted earth including incidential charges and cleaning of all labour charges and machinery charges etc,..complet |
| 5 | Km 0/0- 0/690 |
| 6 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 150mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete |
| 7 | Km 0/0- 0/690 |
| 8 | Applying PRIMECOAToverWBM/ WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp. |
| 9 | Km 0/0- 0/690 |
| 10 | Applying TACKCOAToverWBM/ WMM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp. |
| 11 | Km 0/0- 0/690 |
| 12 | Construction of un - reinforced dowel jointed at expansion and construction joint only plain cement concrete pavement thickness as per design etc., |
| 13 | Km 0/0- 0/690 |
| 14 | BC 25/30/40mm Thick (Grade-II) Using VG30 Bitumen and Plastic Waste ProvidingandlayingBituminousConcreteto30/40mmthickusing0.13cumof19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 47.28kgs of VG30 bitumenand3.02KgsofWastePlasticforpremixingper10sqmincludingcostand conveyanceofallmaterialstoCMPsite,heatingthebitumenandaggregatetorequired temperatureandmixingtheminrequiredtemperatureincentralhotmixplant20-30ton capacity,conveyingthemixbytippertruckstopaversite,spreadingthemixtouniform thicknessof40mmwithmechanicalpavertothespecifiedgradesandcrosssectionsand consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending topavertositeetc.,including hirechargesandfuelchargesfor 20-30tCMPwithbitumen boiler,tippertrucks,PaverFinisher,Vibratoryrollerandallothertoolsandplantrequired, including fuel and all other incidental charges etc., complete as per specification using CMP asper clause 507 of MORTH Rev-5 |
| 15 | Km 0/0- 0/690 |
| 16 | Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for and compaction with power roller etc.complete, for Side berms etc,.complete,. |
| 17 | Km 0/0- 0/690 |
| 18 | Provision for HM Stone Charges etc,.. |
| 19 | Provision for Name Board Charges with painting etc,.. |
| 20 | Provision for Sign Board |
| 21 | Provision for White board line |
| 22 | Provision for Rumble stripes |
| 23 | Provision forReflectors |
| 24 | Routine Maintenance after completion ofwork the road sufrace and shoulder to be maintained in proper condition to make them free from excessive edge drop offs, roughness, scouring and pot holes and cleaning of surface drain including culverts for frre flow of water. Relettering name boards and K.M & H.M stone and other maintenance operation required to keep the road traffic worthly at all the time for the maintenance periodfor the following years. As per General condition of contract para 32.2.2 |
| 25 | For 1st Year |
| 26 | For 2nd Year |
| 27 | For 3rd Year |
| 28 | For 4th Year |
| 29 | For 5th Year |
| 30 | 2. Strengtheningof BT road from SOORAPOONDI H/C ROAD Km 0/0-0/505 |
| 31 | Picking the Worn-out BT Surface including incidential charges and cleaning of all labour charges and machinery charges etc,..complet |
| 32 | Km 0/0- 0/505 |
| 33 | Clearing the Scrub jungles including incidential charges and cleaning of all labour charges and machinery charges etc,..complet |
| 34 | Km 0/0- 0/505 |
| 35 | Earth work excavation and depositing on bank within initial lead of 10m & initial lift of 2min hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders SS .20.A |
| 36 | Km 0/0- 0/505 |
| 37 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 150mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete |
| 38 | Km 0/0- 0/505 |
| 39 | Applying PRIMECOAToverWBM/ WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp. |
| 40 | Km 0/0- 0/505 |
| 41 | Applying TACKCOAToverWBM/ WMM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp. |
| 42 | Km 0/0- 0/505 |
| 43 | BC 25/30/40mm Thick (Grade-II) Using VG30 Bitumen and Plastic Waste ProvidingandlayingBituminousConcreteto30/40mmthickusing0.13cumof19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 47.28kgs of VG30 bitumenand3.02KgsofWastePlasticforpremixingper10sqmincludingcostand conveyanceofallmaterialstoCMPsite,heatingthebitumenandaggregatetorequired temperatureandmixingtheminrequiredtemperatureincentralhotmixplant20-30ton capacity,conveyingthemixbytippertruckstopaversite,spreadingthemixtouniform thicknessof40mmwithmechanicalpavertothespecifiedgradesandcrosssectionsand consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending topavertositeetc.,including hirechargesandfuelchargesfor 20-30tCMPwithbitumen boiler,tippertrucks,PaverFinisher,Vibratoryrollerandallothertoolsandplantrequired, including fuel and all other incidental charges etc., complete as per specification using CMP asper clause 507 of MORTH Rev-5 |
| 44 | Km 0/0- 0/505 |
| 45 | Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for and compaction with power roller etc.complete, for Side berms etc,.complete,. |
| 46 | Km 0/0- 0/505 |
| 47 | Provision for HM Stone Charges etc,.. |
| 48 | Provision for Name Board Charges with painting etc,.. |
| 49 | Provision for Sign Board |
| 50 | Provision for White board line |
| 51 | Provision for Rumble stripes |
| 52 | Provision forReflectors |
| 53 | Routine Maintenance after completion ofwork the road sufrace and shoulder to be maintained in proper condition to make them free from excessive edge drop offs, roughness, scouring and pot holes and cleaning of surface drain including culverts for frre flow of water. Relettering name boards and K.M & H.M stone and other maintenance operation required to keep the road traffic worthly at all the time for the maintenance periodfor the following years. As per General condition of contract para 32.2.2 |
| 54 | For 1st Year |
| 55 | For 2nd Year |
| 56 | For 3rd Year |
| 57 | For 4th Year |
| 58 | For 5th Year |
| 59 | GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column \"BB\" for all works in this package}(Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD) |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender