| 1 | Earth work in excavation of foundation in hard soil or Gravelly soil within 50 m initial lead & 1.50 m initial liftincluding levelling & dressing the bed & laying in layer of 0.30m in depth,breaking the clod to maximum 5 to 7 cm in size & including cost of all labour cess etc.allcomplete . |
| 2 | Filling sand in foundation & plinth well watered & rammedincluding cost , conveyance to site , royalty,cess,etc. all taxes of all materials &cost of all labour complete |
| 3 | C.C. ( 1 : 3 : 6 ) using 40 mm size(H.B) metal free from weathered skin & all foreign materials includinglowering, laying the concrete, watering and curing etc. and including cost , conveyance to site , royalty , cessetc. all taxes of all materials & cost of all labour complete . |
| 4 | PCC work inM- 20 Grade of concrete with 20 mm & down gradedsize CBHG chips& compacting with suitablevibratorfor construction of wall & pavementincluding Lowering,laying the concrete,watering and curing etc.complete to required levels laid in layerincludingcost, conveyance to site , royalty ,cess, etc . all taxes of all materials & cost of all labour etc. allcomplete |
| 5 | Rigid & smooth Centering & shutteringfor PCC works including false work and dismentalling them after castingincluding cost & charges of all materials& cost of all labour , cess etc. all complete . |
| 6 | 12 mm thick cement Plaster in C.M ( 1 :4 )with neat cement punning after racking out the joints including cost, conveyance to site , royalty,cessetc. all taxes of all materials& cost of all labour complete . |
| 7 | R.C.C. work inM- 30 Grade of concrete with 20 mm & down gradedsize CBHG chips including hoisting & laying with cost, conveyance to site , royalty,cessetc. all taxes of all materials& cost of all labourwith rigid & smooth Centering & shuttering and dismentalling them after casting & removing the debrisclear from work sitecomplete including the cost & conveyance & labour charge for cutting , bending, binding, tying the grills& placing in position providing1.00 Qntl / cum ofConcreteof M.S./ T.S. rodcomplete . |
| 8 | Filling in with excavated earth in approaches/ site & rough dressing with cost of all labour , cess etc. all complete. |
| 9 | Supplying all labour , T & P, etc.forpreparationofDisplay Board including painting ,writing&provision of 10 nos of photto graphs in diferent stage and M.S. Jally including cost of all materials & cost of all labour complete . |