| 1 | Dismantling clearing away and carefully stacking the materials usefulfor reusesof Rein forced Cement concrete for roof slab, Column, Lintel and staircase steps, etc.complete |
| 2 | Dismantling clearing away and carefully stacking the materialsuseful for reuse ofplain cement concrete for floor etc.complete |
| 3 | Earth work excavation for foundation in all soils and sub-soils and to full depth as may be directed except in rock requiring blasting inclusive of shoring shuttering, bailing out water wherever necessary and depositing the surplus earth within the compound in places shown by thedepartmental officers with an initial lead of 10 mts and initial lift of 2 mts. and clearing and levelling the site, etc., complete complying with standard specification.(for Drain & Culvert) |
| 4 | Supplying and filling the foundation andbasement with stone dust in layers of not more than 15cm thick well rammed watered and compacted etc., complete complying with standard specification. |
| 5 | Plain Cement Concrete 1:4:8 (One Cement, Four sand and eight hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundationincluding dewatering wherever necessary and laid in layers of not more than 15 cm thick well rammed, consolidated and curing etc. complete complying with standard specification |
| 6 | Supplying and erecting steel centering including necessary supports for plane surfaces for Reinforced Cement Concrete works such as column footings, column pedestals, plinth beams, grade beams, staircase steps, etc. which require only nominal strutting using mild steel sheets of size 90cm x 60cm and 10 BG stiffened with welded mild steel angles of size 25mm x 25mm x 3 mm for boarding, laid over silver oakjoists of size 10cm x 6.5cm spaced at about 75cm centre to centre or at suitable intervals etc. complete in all floors complying with standard specifcation. |
| 7 | Plain Cement Concrete 1:2:4 (one cement, two sand and four hard broken stone jelly) using 20mm jelly for wearing coat including laying, compacting, finishing and curing, etc., complete as per standard specificatins and as directed by the departmental officers. |
| 8 | Plastering in cement mortar 1;4 mix (one cement, and four sand) 20mm thick including cost and conveyance ofall materials and labour charges for mixing the mortar , and the surface rubbed for smooth and curring to requried period , etc complete as per standard specification |
| 9 | Supplying, fabricating and placing in position Mild Steel / Ribbed Tor Steel grills for all RCC works as per design given including cost of steel and G.I. binding wire in all floors etc. complete complying with standard specification. |
| 10 | Providing and laying in position Standardised Concrete Mix M-20 Grade in accordance with IS 456 - 2000 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement contenet of 325Kg/ cum and maximum water cement ratio of 0.55 including admixture (Plasticiser / super plasticiser) in recommended proportions as per IS 9103 to accelerate, related setting of concrete, improve workability without imparing strength and durability with about (5.0cum), 7730Kg of 20mm machine crushed stone jelly and with about (3.3 cum), 5156kg of 10 - 12mm machine crushed stone jelly and with about (4.79cum) 7670 kg of sand, but excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary without claiming extra cost etc., complete complying with standard specification and as directed by the departmental officers - The Coarse and Fine aggregates to be used should comply with the requiremnents of IS standards. (No separate payment will be made by the Department for the excess usage of materials) - Upto Basement |
| 11 | GST 18% |