Tender For Perumthuruth Vadakkekkary Padasekharam Project At Muhamma Gp In Kanjikuzhi Division (Project No 709/23 Of Alappuzha District Panchayat)
Tender Value
6.29 Lakhs
Estimated cost
Bid Submission
28 Mar 2023
0 days left
EMD
15726
Bank guarantee accepted
Document Fee
1390
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
muhamma → Kerala
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Perumthuruth Vadakkekkary Padasekharam Project At Muhamma Gp In Kanjikuzhi Division ( Project No 709 / 23 Of Alappuzha District Panchayat )
BOQ
| Sl. No. | Item Description |
| 1 | BOX CULVERT 2 Nos |
| 2 | 60.1.2RING BUND Type II Putting up ring bund with earth fille gunny bags of top width 1.0m bottom width 2.0m height 2.0 m side and filling in between with earth to form ring bund and maintaining the same leak proof till the completion of the work and clearing the site by dismantling the bund after completion of the work.etc.complete. |
| 3 | 60.2.2Bailing out water Using 5HP Pump- Bailing out water with 5HP engine and pump set including conveyance to site and erection,cost of fuel, lubrication oil and other stores, pay of staff etc complete |
| 4 | 2.6.1DR PACKING Under foundation - Dry stone packing under foundation with good quality blasted rubble including conveyance of material and labour charges etc. complete as per direction of departmental officers at site. |
| 5 | 60.7.2DR PACKING Under foundation - Dry stone packing under foundation with good quality blasted rubble including conveyance of material and labour charges etc. complete as per direction of departmental officers at site. |
| 6 | 4.1.5Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) |
| 7 | 5.1.2 Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size |
| 8 | 4.3.1 Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns |
| 9 | 5.9.2 Centering and shuttering including strutting, etc. and removal of form for: Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc. |
| 10 | 5.9.3 Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform |
| 11 | 5.22.6Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more |
| 12 | PASSAGE SLAB |
| 13 | 60.1.2RING BUND Type II Putting up ring bund with earth fille gunny bags of top width 1.0m bottom width 2.0m height 2.0 m side and filling in between with earth to form ring bund and maintaining the same leak proof till the completion of the work and clearing the site by dismantling the bund after completion of the work.etc.complete. |
| 14 | 60.2.2Bailing out water Using 5HP Pump- Bailing out water with 5HP engine and pump set including conveyance to site and erection,cost of fuel, lubrication oil and other stores, pay of staff etc complete |
| 15 | 2.6.1 DR PACKING Under foundation - Dry stone packing under foundation with good quality blasted rubble including conveyance of material and labour charges etc. complete as per direction of departmental officers at site. |
| 16 | 60.64.1 Coconut Pile - Supplying and stacking well matured straight coconut post for driving down throug various strata bellow bed level including cost coveyance labour charges etc complete. |
| 17 | 60.64.4 Coconut Pile - Driving down coconut pile to lines and levels through variuos strata including all hire charges and labour for fixing , staging platform and all other appliances necessary for pile driving down after pointing the bottom end |
| 18 | 60.64.6Cutting and removing the excess length of wooden piles to lines and levels and removing the cut end of piles and stacking within 150m |
| 19 | 60.7.2 DR PACKING Under foundation - Dry stone packing under foundation with good quality blasted rubble including conveyance of material and labour charges etc. complete as per direction of departmental officers at site. |
| 20 | 4.1.5 Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) |
| 21 | 4.1.6 Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 ( 1 cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal size) |
| 22 | 5.1.3 Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) |
| 23 | 5.1.2 Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size |
| 24 | 4.3.1 Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns |
| 25 | 5.9.1 Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete |
| 26 | 5.9.2 Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc. |
| 27 | 5.9.3 Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform |
| 28 | 5.9.5 Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers |
| 29 | 5.22.6Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more |
AI Tender Summary
Tender Timeline
Mar 21, 2023
11:30 IST
Tender Published
Tender notice published.
CompletedMar 28, 2023
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
CompletedMar 30, 2023
Bid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender