| 1 | Dismantling of Fly / Bottom ash Mixing apparatus Charges for dismantling the existing damaged (Fly & bottom ash) mixing apparatusfrom its structure along with adopter & distance picece with poking holes, etc., lead, lift and tranporting including cost of consumables likecutting gas,etc and devolution of scrap to central stores/ MTPS-II. |
| 2 | Removal of Fly/Bottom ash Mixing appratus Bed Frames and erect the New bed frames Charges for removal of existing eroded bed frame, fabrication and erection of new bed frame to withhold the mixing apparatus by using the channel of size 150X75X6 mm - 1 m long (4 Nos) and cross support angle of size 150X75X6 mm - 1.5 m (2 Nos) including cost of consumables like cutting gas, welding electrodes,channels, angles etc., |
| 3 | Fabrication of New Fly & Bottom ash Mixing appratus Charges for fabrication of new MS 90MT/Hr capacity mixing apparatus including cost of consumables like cutting gas, welding electrodes, MS plate, etc., |
| 4 | Fixing the New fly/Bottom ash mixing appratus into the bed Charges for lead, lift, positioning and fixing the new MS 90 MT/Hr capacity mixing apparatus over the new bed frame in such a way of perfectly matching it with the bottom flange. |
| 5 | Fabrication charges for providing the extension platfrom from the existing in the bottom ash silo slurryvalve operation. |
| 6 | Fabrication charges for providing the extension platfrom from the existing in theFly ash silo slurryvalve operation. |
| 7 | Fabrication charges for providing the New platfrom for Fly ash silo unloading spout valve operation. |
| 8 | Erection,testing and commisssioning of extension platfrom from the existing in the bottom ash silo slurryvalve operation. |
| 9 | Erection,testing and commisssioning of extension platfrom from the existing in theFly ash silo slurryvalve operation. |
| 10 | Erection,testing and commisssioning of New platfrom for Fly ash silo unloading spout valve operation |
| 11 | Charges for erection of 300 NB/350NB/400NB New M.S ERW pipes from silo bottom to silo top.(For an altitude of 45m from ground level) |
| 12 | Erection of 60 NB header line for replacing the worn out LP & HP seal water line in slurry pump houseincluding charge for special toolsother consumables, safty equipments & T&P\"s etc. |
| 13 | Painting the 60 NB header LP & HP seal water line in slurry pump house with one coat enamel red oxide primer & two coat enamel green paint including the hire charges for special tools required, other consumables,safety equipments & T&P\"s stc. |