Transportation, Erection & Commissioning Of 20 Mva Transformer At 132 Kv Substation Bindki, Under Electy. Trans. Division- Fatehpur
Tender Overview
Project Description
Transportation, Erection & Commissioning of 20 MVA Transformer at 132 KV Substation Bindki, under Electy. Trans. Division- Fatehpur
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 13-Mar-2023 | DATE159 | Date | 20-Mar-2023 |
BOQ
| Sl. No. | Item Description |
| 1 | Transportation of 20MVA TF From 132KV S/S Kalpi under ETD-Orai to 132KV S/S Bindki Under ETD-Fatehpur and miner repair if any trailer or truck to be arranged by the contractor at his own cost. Insurance cost will bear by contractor Approx. dist.-(to&fro-500km) which is minimum for transport. All men, extra material(if required) & T&P will be provided by contracor without any extra cost. |
| 2 | Loading of 20MVA TF Main tank, conservator radiator, HV/LV Bushing and its others parts alongwith oil drum on the truck /trailer safely to avoid any type of damaged at 132KV S/S Kalpi under ETD-Orai. All men, extra material(if required) & T&P will be provided by contracor without any extra cost. |
| 3 | Proper packing of HV/LV Bushing of 20MVA T/F including proper wrapping with polythene/paper sheets in the wooden crate at loading site (132KV S/S Kalpi) properlywithout avoid any damage of bushing of 20MVA TF at 132KV S/S Bindki.All men, extra material(if required) & T&P will be provided by contracor without any extra cost. |
| 4 | Unloading of 20MVA TF Main tank, conservator radiator, HV/LV Bushing and its others parts alongwith oil drum from truck/trailer safely to avoid any type of damaged at 132KV S/S Bindki Under ETD-Fatehpur. All men, extra material(if required) & T&P will be provided by contracor without any extra cost. |
| 5 | Shifting of main tank of 132/33 KV 20MVA Transfromer from switchyard/ storage place at loading site(132KV S/S Kalpi) including turning of tank (if required) including men, t&p all other work required to complete the job satisfactorily. |
| 6 | Up to 20 Mtr. |
| 7 | Additional shfting of 5 mtr/ job |
| 8 | Shifting of main tank of 132/33 KV 20MVA Transfromer from unloading place(132KV S/S Bindki) upto plinth including turning of tank (if required) including men, t&p all other work required to complete the job satisfactorily. |
| 9 | Up to 20 Mtr. |
| 10 | Additional shfting of 5 mtr/ job |
| 11 | Safe handling and shifting of all accessories of132/33KV, 20 MVA transformer such as radiators, conservator tank, all bushing with its turrents, connecting pipe lines, cooling fan, motor drive mechanism of tap changer, RTCC Panel and associated oil pipelines etc from stored place of 132 KV S/S Bindki to erction site including other associated work to complete the job satisfactorily.All men, extra material(if required any) & T&P will be provided by contracor without any extra cost. |
| 12 | Complete erection of 20 MVA Transformer by erection of radiators, conservator tank, all bushing with its turrents, connecting pipe lines, cooling fan, motor drive mechanism of tap changer, RTCC Panel and associated oil pipeline etc. to complete the job satisfactorily, including first filling of oil and topping up transformer oil (not circulation) in tank, radiator, oil pipeline, conservator tank etc and attending oil lekage if any and other associated work to complete the job satisfactorily. Crane, t&p shall be provided by contractor, all assistance in getting the transformer successfully commisoned by providing qualifed manpower till commissoning.All men, extra material(if required any) & T&P will be provided by contracor without any extra cost. |
| 13 | Flushing of Main tank core and winding by hot centrifused T/F oil of Transformer.All men, extra material(if required any) & T&P will be provided by contracor without any extra cost. |
| 14 | Complete evacuation of main tank of transformer and filling of Nitrogen in vacuum up to required pressure and again evacuation the transformer tank after required time interval using nitrogen cylinder having dew point 60 to 65 degree centigrade and filling it in main tank of transformer up to pressure of 5PSI or as per instruction of site engineer of UPPTCL and maintaining it in the tank as per direction of Executive engineer required to dry out of transformer. This process shall be repeated till the desired value of 5PPM or as direction of Executive enginner of above substation.All men, extra material(if required any) & T&P will be provided by contracor without any extra cost. |
| 15 | Centrifusing of complete transformer oil of 20 MVA Transformer in transformer tank or oil tanker by connecting pipecirculating the transformer oil through centrifusing machine to be provided by the contractor and taking the BDV value of the oil perodically till the required value is achieved as per direction of superviser engineer at 132 KV Sub-Station Bindki. All t&p labour centrifusing machine will provided by the contractor at his own cost. |
| 16 | Electrical connection of 20MVA transformer including Laying,dressing and binding of cable including fixing of cable tray support structure and termination of cable making the loop and its ferruling as per schedule and interconnection as per requirment of RTCC panel, marshalling box, WTI, OTI, Buchholz relay, cooling fans OLTC& other driving mechanism etc.All men, extra material(if required) & T&P will be provided by contracor without any extra cost. |
| 17 | Earthing of 20 MVA Transformer main body at two point using MS flat of size 75x10mm and 50x6mm connected with marshalling box and drive mechanism, OLTC panel, providing the wheel stopper with MS flat as per site requirment.(M/S Flat will be provided by Department.) |
| 18 | Painting of 75X10 mm and 50x6mm earthing strip above the ground level by one coat of red oxide and two coat of green paints. Paint will be provided by contractor. All men, extra material(if required any) & T&P will be provided by contracor without any extra cost. |
| 19 | Delta earthing for 132/33 KV 20MVA T/F consisting of fabrication of delta set with 03 Nos. 40mm dia size 3 mtr. Long electrodes its placing inside the ground and connecting all the three electrode with 75x10mm MS flat 700mm deep and connecting same with earthmat at two places with material except MS round bar provided by the department. Exavation and filling of sand will also included in this work.All men, extra material(if required any) & T&P will be provided by contracor without any extra cost. |
| 20 | Jumpering of 20MVA TF HV/LV side cutting of conductor and tightening of conductor with connector and complete all job satisfactorily.All men, extra material(if required any) & T&P will be provided by contracor without any extra cost. |
| 21 | Complete replacement of all the old & damaged gaskets including top cover of transformer by providing and fixing of new gaskets as per existing size made of rubberized cork sheet Kotika/Turboze/cork brand grade 07 after due fabrication in all respect.All men, extra material(if required any) & T&P will be provided by contracor without any extra cost. |
| 22 | Spray Painting of 20MVA T/F along with all accessories including OLTC panel with one coat of red oxide primer and two coat of standard smoke gray synthetic enamel paint first quality after proper cleaning of surface along with red, yellow & blue colour at bushing top. Colour with essential material along with T&P will be provided by contractor at his own cost. |
| 23 | Integration of 20MVA T/F WithSCADA system with all respect for successfully installation, testing andcommissioningwith SCADA System & C&R Panel. All material along with labour & T&P required along with optical fibre will be provided by contractor at his own cost. No extra cost will be included later. Testing kit will also be provided by contractor at his own cost. |
| 24 | Commissioning & testing of 20MVA TF oil for following test- BDV, PPM, DGA from NABL/CPRI approved lab andTEN- DELTA by arranging appropriate equipment at erection site of 132KV S/S Bindki. Testing kit, Labour& T&P will be provided by contractor. |
| 25 | SFRA(sweep frequency response analysis) Testing of 20MVA transformer at both substation (Before dismantling at 132KV S/S Kalpi under ETD-Orai) and after erection at 132KV S/S Bindki under ETD-Fatehpur. Testing kit, Labour& T&P will be provided by contractor at his own cost. |
| 26 | Carriage of Oil tank 20KL including loading at 220KV S/S Fatehpur & unloading at 132KV S/S Bindki under ETD-Fatehpur and after completing the work successfully oil tank will be returned back at 220KV S/S Fatehpur.(dist- to & fro-60Km). labour, hydra, extra material(if required any) & T&P will be provided by contracor without any extra cost. |
| 27 | Supply of 75x10 mm MS Flat |
| 28 | Supply of 50x6 mm MS Flat |
| 29 | Supply of 40mm dia MS electrode of 3 meter length |
| 30 | Supply of optical fibre required for SAS at 132KV S/S Bindki |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender