Tender For Construction And Improvement Of Road From Pakke To Bameng Adc Hq (13.110).
Tender Overview
Project Description
Construction And Improvement Of Road From Pakke To Bameng Adc Hq ( 13.110 ) .
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 11-Mar-2023 | Information and Instruction to bidders | Other | 13-Mar-2023 |
| 2 | 10-Mar-2023 | Venue Change | Other | 13-Mar-2023 |
BOQ
| Sl. No. | Item Description |
| 1 | Excavation in Hilly Areas in Soil by Mechanical Means(Excavation in soil in Hilly Area by Mechanical Means including cutting and trimming of side slopes and disposing of excavated earth with all lift and lead upto 1000 metres. |
| 2 | Excavation in Hilly Area in Ordinary Rock by mechanical Means not requiring blasting, (Excavation in Ordinary Rock not requiring blasting by mechanical means including cutting and trimming of slopes and disposal of cut material with all lift and lead upto 1000mstres. |
| 3 | Excavation in Hilly Area in Ordinary Rock by mechanical Means not requiring blasting, (Excavation in Ordinary Rock not requiring blasting by mechanical means including cutting and trimming of slopes and disposal of cut material with all lift and lead upto 1000mstres. |
| 4 | Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification,including setting out,construction of shoring and bracing,removal of stumps and other deleterious matter,dressing of sides and bottom and backfilling with approved material.)Ordinary soilManual Meansupto 3 m depth |
| 5 | PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed,placed in foundation and compacted by vibration including curing for 14 days.) |
| 6 | Stone masonry work in cement mortar 1:3 for substructure complete as per drawing and Technical SpecificationsCoursed rubble masonry (first sort ) |
| 7 | Plain/Reinforced cement concrete in sub-structure complete as per drawing and technical specificationsPCC Grade M20Height upto 5m |
| 8 | Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure as per drawing and Technical SpecificationRCC Grade M20Using Concrete MixerFor solid slab super-structure,20-30% of (a+b+c) Height upto 5m |
| 9 | Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per drawing and technical specifications |
| 10 | Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment,wing wall/return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical specifications |
| 11 | Back filling behind abutment,wing wall and return wall complete as per drawing and Technical specification a)Granular material |
| 12 | Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications.PCC Grade M20Using Concrete Mixer |
| 13 | Supplying, fitting and placing un-coated HYSD bar reinforcement in foundation complete as per drawing and technical specifications |
| 14 | Preparation of sub grade (Preparation of sub grade by excavating earth to an average depth of 22.50 cm, dressing to camber and consolidating with road roller, making good the undulations etc. and disposal of surplus earth, lead upto 50 m.) |
| 15 | Granular Sub-base with Close Graded Material (Table:- 400-1)Plant Mix Method (Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 )for grading- I Material |
| 16 | Dry Lean Cement Concrete Sub- base (Construction of dry lean cement concrete Sub- base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement content not to be less than 150 kg/ cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10 tonnes vibratory roller, finishing and curing.) |
| 17 | Cement Concrete Pavement (Construction of un-reinforced, dowel jointed, plain cement concrete pavement over a prepared sub base with 43 grade cement @ 400 kg per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines and grades as per drawing ) |
| 18 | Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications.PCC Grade M15 |
| 19 | Direction and Place Identification signs upto 0.9 sqm size board. (Providing and erecting direction and place identification retro-reflectorised sign asper IRC:67 made of encapsulated lens type reflective sheeting vide clause 801.3, fixed over aluminium s |
| 20 | Kilo Metre Stone (Reinforced cement concrete M15grade kilometre stone of standard design as per IRC:8-1980, fixing in position including painting and printing etc) i) 5th kilometre stone (precast) |
| 21 | Ordinary Kilometer stone (Precast) |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
CompletedCorrigendum-2 Issued
Clarifications on tender conditions and amendments issued.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender