| 1 | Earth work excavation for foundation in ordinary soil, light black cotton sandy loam and dry silt including shoring, strutting, baling or pumping out water wherever necessary and refilling the sides of foundation with excavated earth in layers of 15cm thick and depositing the surplus earth at places as directed by the departmental officers with initial lead and lift (open Excavation) |
| 2 | Conveyance of Dismandling materials andexcavated earthupto a lead of 2KM lead including loading and unloading charges as directed by the departmental officersetc., complete |
| 3 | Providing laying spreading and compacting grading aggregates to wet mix macadam specification in 250mm thick in two layers each layer in 125mm thick inlcuding premixing the materials with water at OMC in mechanical mix plant carriage of mixed materials by tipper to work site laying in uniform layers with pavers in sub base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density etc., complete |
| 4 | Providing and laying of Tack coat using emulsion bitumen at the rate of 7.00kg/10m2 over the prime coated surface in Wet Mix Macadam preparatory to another bituminous construction over it MORT & H |
| 5 | Providing and laying of Tack coat using emulsion bitumen at the rate of 2.50 kg/10m2 over the prime coated surface in Wet Mix Macadam preparatory to another bituminous construction over it MORT & H |
| 6 | Providing and laying 50mm consolidated thick Dense Bituminous Macadam using 0.24cum of 26.50-13.20mm, 0.25 cum of 13.20-2.36mm and 0.23 cum of 2.36mm & below and with 53.20Kgs of VG30/VG40 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing the min. required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to worksite, spreading the mix to uniform thickness of 50mm with paver to the specified grades and cross sections and compacted by Vibratory / Pneumatic Roller to the required density etc., including labour for attending to paver at site etc., including hire charges and fuel charges for 20- 30t CMP with bitumen boiler, tipper trucks, Paver Finisher /7m paver finisher, Vibratory / Pneumatic rollers and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 505 MORTH Rev-5 |
| 7 | Providing and laying Bituminous Concrete to 30mm thick using 0.13 cum of 17.00 - 7.50mm, 0.17cum of 7.50 -2.36mm and 0.26cum of 2.36 and below with 50.30kgs of VG30 / VG40 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing the min required temperature in central hot mix plant 20-30ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 30mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10tonne Vibratory / Pneumatic Roller to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30t CMP with bitumen boiler, tipper trucks, Paver Finisher / 7m paver finisher, Vibratory / Pneumatic roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTHRev-5. |
| 8 | Painting center line, edge line road marking 100width with Thermoplastic paint (hot application) in such a way that painting length will be 3.00m with a gap of 3.00m with a gap of 3.00m curved for centerline will be 3.00m with a gap of 3.00m curved for center line by indigenous hand propelled road marking machine with single coat including cost of all materials such as pigments, extender, fine aggregate stand oil (binder) glass beads as per 3262:1776 for the preparation of thermoplastic paint at site mixing glass beeds 10%by weight of the ingredient at the time of application of paint on the road surface, including cost of all etc., complete |