Tender For Work Contract For Capital And Dcw Works In Rasingapuram Sub Division In Theni Edc - 1.01 Labor Charges For Loading & Unloading Of 7.5Mtr / 8Mtr Poles To The Vehicle Including Stacking. 1.02 Labor Charges For Loading & Unloading Of 9.0Mtr / 9.
Tender Overview
Project Description
Work Contract For Capital And Dcw Works In Rasingapuram Sub Division In Theni Edc - 1.01 Labor Charges For Loading & Unloading Of 7.5Mtr / 8Mtr Poles To The Vehicle Including Stacking. 1.02 Labor Charges For Loading & Unloading Of 9.0Mtr / 9.14Mtr Poles To The Vehicle Including Stacking. 1.03 Transporting Of Pole From Road Side To Pole Pit Including Loading Transporting And Unloading Up To A Distance Of 500Mtr 7.5Mtr / 8.0Mtr Poles Of Various Sizes And Iron Poles. 1.04 Extra For Every Additional 100Mtr Lead Or Part Thereof Over The Lead Of 500Mtr For 7.5Mtr / 8.0Mtr Rcc Poles & Iron Poles. 1.05 Transporting Of Pole From Road Side To Pole Pit Including Loading Transporting And Unloading Up To A Distance Of 500Mtr 9.0Mtr / Rsj Poles Of Various Sizes And Iron Poles. 1.06 Extra For Every Additional 100Mtr Lead Or Part Thereof Over The Lead Of 500Mtr For 9.0Mtr / Rsj Poles And Iron Poles. 1.07 Loading Of Conductor To Vehicle With Full Drum 1.08 Unloading Of Conductor To Vehicle With Full Drum 1.09 Materials Loading And Unloading Lead Above 20Mtr Up To 100Mtr And Stacking Complete. 1.1 Route Surveying And Peg Marking Of Lt / Ht Lines. 1.11 Excavation Of 7.5Mtr / 8.0Mtr Pole Pit In Medium Rock 1.12 Excavation Of 9.0Mtr / 9.14Mtr Pole In All Classes Of Soil 1.13 Excavation Of Stay Pit For Stay On All Classes Of Soil 1.14 Excavation Of Three No’S Earth Pit And Erection Of Pipes 1.15 Erection Of 7.5Mtr / 8.0Mtr Psc Rcc Poles 1.16 Erection Of 9.0Mtr / 9.14Tr Poles 1.17 Erection Of Stay Set Complete 1.18 Stringing Of Line Up To 7 / 2.59Mm ( Acsr / Aaac ) 1.19 Stringing Of Line Up To 7 / 3.35Mm ( Acsr / Aaac ) 1.2 Stringing Of Line Up To 7 / 4.09Mm ( Acsr / Aaac ) 1.21 Fixing Of Three Phase X Arm With Insulator. 1.22 Fixing Of Ht / Lt Ti Fitting With Insulator. 1.23 Fixing Of Ht V Cross Arm And Tapping Channel X Arm With Insulator. 1.24 Set Righting The Leaning Poles, In Pin Point 1.25 Set Righting The Leaning Poles, In Cut Point 1.26 Erection Of Ht Side Arm With Stud 1.27 Erection Of Lt Side Arm With Stud 1.28 Erection Of St Materials Such As Top Channel And Belting Angle Etc, Complete.. 1.29 Erection Of Hg Fuse Set 1.3 Erection Of Ab Switch 1.31 Transporting Str. Materials Ab Switch & Hg Fuse Cable Complete To Site. 1.32 Materials Loading , Unloading With Lead Above, 20Mtr Up To 100Mtr Leading And Stocking Complete. 1.33 Transformer Structure Grounding And Earthling Of Tr. 1.34 Erection Of Lt Bus Per Arrangements 1.35 Erection Of Lt Open Type Fuse Set. 1.36 Erection Of Ht Jampering Complete. 1.37 Erection Of Ht Las 1.38 Erection Of Lt Las 1.39 Earthling / Coil Earthling Of Pole Including Cutting Hooking And Binding Etc, . 1.4 Clearing Coconut Tree Branches 1.41 Clearing Other Tree Branches 1.42 Jungle Clearances Such As Seemai Karuvel Heavy Rock Etc. 1.43 Erection Of Single Pole Transformer Bed 1.44 Erection Of Single Pole Ab Switch ( Gos ) 1.45 Erection Of Single Pole Hg Fuse Set 1.46 Lt Cable Arrangement 1.47 Erection Of Plinth For 22Kv Single Pole Structure 1.48 Drilling Of Holes All Sizes ¼” To ¾” & Above ¾” 1.49 Dismantling Of Poles In Damaged Condition And Separation Of Grill And Transporting The Grill To Road Side
BOQ
| Sl. No. | Item Description |
| 1 | labor Charges for loading & Unloading of 7.5mtr / 8mtr poles to the vehicle includingstacking. |
| 2 | labor Charges for loading & Unloading of 9.0mtr / 9.14mtr poles to the vehicle includingstacking. |
| 3 | Transporting of pole from road sideto pole pit including loading transporting and unloading up to a distance of 500mtr 7.5mtr /8.0mtr poles of various sizes and iron poles. |
| 4 | Extra for every additional 100mtr lead or part thereof over the lead of 500mtr for 7.5mtr / 8.0mtr RCC poles & Iron poles. |
| 5 | Transporting of pole from road sideto pole pit including loading transporting and unloading up to a distance of 500mtr 9.0mtr / RSJ poles of various sizes and iron poles. |
| 6 | Extra for every additional 100mtr lead or part thereof over the lead of 500mtr for 9.0mtr /RSJ poles and iron poles. |
| 7 | Loading of Conductor to vehicle with full drum |
| 8 | Unloading of Conductor to vehicle with full drum |
| 9 | Materials loading and unloading Lead above 20Mtr up to 100mtr and stacking complete. |
| 10 | Route surveying and peg marking of LT / HT Lines. |
| 11 | Excavation of 7.5mtr / 8.0mtr pole pit in medium rock |
| 12 | Excavation of 9.0Mtr / 9.14mtr pole in all classes of soil |
| 13 | Excavation of stay pit for stay on all classes of soil |
| 14 | Excavation of three No’s earth pit and erection of pipes |
| 15 | Erection of 7.5mtr / 8.0mtr PSC RCC poles |
| 16 | Erection of 9.0mtr / 9.14tr poles |
| 17 | Erection of stay set complete |
| 18 | Stringing of line up to 7 / 2.59mm ( ACSR /AAAC) |
| 19 | Stringing of line up to 7 / 3.35mm ( ACSR /AAAC) |
| 20 | Stringing of line up to 7 / 4.09mm ( ACSR /AAAC) |
| 21 | Fixing of Three Phase x arm with insulator. |
| 22 | Fixing of HT / LT TI Fitting with Insulator. |
| 23 | Fixing of HT V cross arm and Tapping channel x arm with insulator. |
| 24 | Set righting the leaning poles, in Pin point |
| 25 | Set righting the leaning poles, in cut point |
| 26 | Erection of HT side arm with stud |
| 27 | Erection of LT side arm with stud |
| 28 | Erection of st materials such as Top channel and belting angle etc, complete.. |
| 29 | Erection of HG fuse set |
| 30 | Erection of AB switch |
| 31 | Transporting str. Materials AB switch & HG Fuse cable complete to site. |
| 32 | Materials Loading ,Unloading with lead above, 20mtr up to 100mtr leading and stocking complete. |
| 33 | Transformer structure grounding and earthling of Tr. |
| 34 | Erection of LT Bus Per arrangements |
| 35 | Erection of LT open type fuse set. |
| 36 | Erection of HT jampering complete. |
| 37 | Erection of HT Las |
| 38 | Erection of LT Las |
| 39 | Earthling / coil earthling of pole including cutting hooking and binding etc,. |
| 40 | Clearing coconut tree branches |
| 41 | Clearing other tree branches |
| 42 | Jungle clearances such as seemai karuvel heavy rock etc. |
| 43 | Erection of single pole Transformer Bed |
| 44 | Erection of single pole AB switch (GOS) |
| 45 | Erection of single pole HG fuse set |
| 46 | LT cable arrangement |
| 47 | Erection of Plinth for 22KV single pole structure |
| 48 | Drilling of holes all sizes ¼” to ¾” & above ¾” |
| 49 | dismantling of poles in damaged condition and separation of grill and transporting the grill to road side |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
Completed