Tender For Nabard-Ridf Xxv- Infrastructural Development Works In Various Padasekharams Under Different Krishibhavans Of Malampuzha Legislative Assembly Constituency, Palakkad District- Gap Filling Works-Construction Of Retaining Wall Under Various Padasek
Tender Overview
Project Description
Nabard-Ridf Xxv- Infrastructural Development Works In Various Padasekharams Under Different Krishibhavans Of Malampuzha Legislative Assembly Constituency, Palakkad District- Gap Filling Works-Construction Of Retaining Wall Under Various Padasekharams Of Mundur Krishibhavan-General Civil Work
BOQ
| Sl. No. | Item Description |
| 1 | Part I |
| 2 | OD1522/2022-2023:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed. All kinds of soil(modified DSoR 2.6.1) |
| 3 | OD1523/2022-2023:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 leaner mix ( including equivalent design mix) |
| 4 | OD1525/2022-2023:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge. Nominal concrete 1:3:6 leaner mix ( including equivalent design mix)9Modified DSoR: 15.2.2) |
| 5 | OD1526/2022-2023:Demolishing stone rubble masonry manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in- Charges:In cement mortar(Modifie DSoR15.9.1) |
| 6 | 4.1.6:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 ( 1 cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal size) |
| 7 | 4.1.5:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) |
| 8 | 4.3.2:Centering and shuttering including strutting, propping etc. and removal of form work for:Retaining walls, return walls, (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc. |
| 9 | 5.1.3:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) |
| 10 | 5.9.3:Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform |
| 11 | 5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more |
| 12 | 13.1.2:12 mm cement plaster of mix:1:6 (1 cement : 6 fine sand). |
| 13 | 2.25:Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m. |
| 14 | OD1527/2022-2023:PVC Weep Holes - Providing weep holes using 75mm dia. PVC pipes working pressure 4 kg/sq.cm including cost of materials. conveyance, labour charges etc., complete. |
| 15 | OD1528/2022-2023:Dry stone packing and pitching with good quality blasted rubble including conveyance of material and labour charges etc., complte as per direction of departmental oficers at site. |
| 16 | 7.1.1:Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand) |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender