Power Boards / Undertakings / PSU Closing in 0 days TDR #35820394

Tender For Execution Of Contract For Extension Of Supply Works And Other Works In Eeudistribution Urban Division Tirunelveli

Issued by Boards / Undertakings / PSU · Tirunelveli, Tamil Nadu
Tender Value
5 Lakhs
Estimated cost
Bid Submission
02 Feb 2023
0 days left
EMD
5000
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online

Tender Overview

Competition Type
NCB
Bidding Type
Tender
Location / State
Tirunelveli → Tamil Nadu
EMD Exemption
Not Available
Quantity
Not Available

Project Description

Execution Of Contract For Extension Of Supply Works And Other Works In Eeudistribution Urban Division Tirunelveli - Normal Ground- Excavation Of Pole Pits ( 1.25M * 0.5M*1.5M ) For 7.32M, 7.5M, 8M, 8.23M Poles 2 Normal Ground- Erection Of 7.32M, 7.5M, 8M, 8.23M Poles 3 Rocky Ground- Excavation Of Pole Pits ( 1.25M * 0.5M*1.5M ) For 7.32M, 7.5M, 8M, 8.23M Poles 4 Rocky Ground- Erection Of 7.32M, 7.5M, 8M, 8.23M Poles 5 Normal Ground- Excavation Of Pole Pits ( 1.25M * 0.6M*1.83M ) For 9M & 9.14M Poles 6 Normal Ground- Erection Of 9M & 9.14M Poles 7 Rocky Ground- Excavation Of Pole Pits ( 1.25M * 0.6M*1.83M ) For 9M & 9.14M Poles 8 Rocky Ground- Erection Of 9M & 9.14M Poles 9 Normal Ground- Excavation Of Pole Pits ( 1.25M * 0.6M*2.19M ) For Above 9.14M Poles & 36 Length Rs Joists 10 Normal Ground- Erection Ofabove 9.14M Poles & 36 Length Rs Joists 11 Rocky Ground- Excavation Of Pole Pits ( 1.25M * 0.6M*2.19M ) For Above 9.14M Poles & 36 Length Rs Joists 12 Rocky Ground- Erection Ofabove 9.14M Poles & 36 Length Rs Joists 13 Transporting Of Poles From Road Side To Pole Pit - 7.32M, 7.5M, 8M, 8.23M Rcc Pole 14 Transporting Of Poles From Road Side To Pole Pit - 9M, 9.14M Rcc / Psc Pole 15 Transporting Of Poles From Road Side To Pole Pit - Rsj 36 Pole 16 Transporting Of Poles From Road Side To Pole Pit - Rsj 42 And Above 17 Loading And Unloading Of Poles - 7.32M, 7.5M, 8M, 8.23M Rcc Pole 18 Loading And Unloading Of Poles - 9M, 9.14M Rcc / Psc Pole 19 Loading And Unloading Of Poles - Rs Joists, Tubular & Rail Pole ( Above 9.14M ) 20 Concreting Of Poles As Per Board Standards ( 2*2*5 ) . The Materialsuch As Cement, Sand, Jelly, Etc., Have To Be Supplied By The Contractor ( Cement Concrete Mix 1:4:8 Using 40Mm Hard Broken Stone Including Cost Of Labour Charges.For Placing Transporting Of Sant, Jally, From Box And Water Curing For 14 Days Etc, . ) 21 Coping Of Pole ( 0.6M*0.6M*0.35M ) 22 Concreting Of Stay ( O.3M * 0.3M * 1.5M ) Including Materials Except Cement 23 Coil Earthing Per Pole & Pole Earthing 24 Normal Ground- Excavation Of Stay Pit ( 1.00M * 0.5M*1.5M ) With Transporting Of Materials To Site ( For Stay Set ) 25 Normal Ground- Erection Of Stay Set 26 Rocky Ground- Excavation Of Stay Pit ( 1.00M * 0.5M*1.5M ) With Transporting Of Materials To Site ( For Stay Set ) 27 Rocky Ground- Erection Of Stay Set 28 Loading Charges Of Cement 29 Unloading Charges Of Cement 30 Stacking Charges 31 Fixing Of V & Channel Cross Arm 5.5 Including Transporting Of Materials From Road Side To Site 32 Fixing Of V & Channel Cross Arm 4.5 Including Transporting Of Materials From Road Side To Site 33 Fixing Of V & Channel Cross Arm 3.5 Including Transporting Of Materials From Road Side To Site 34 Fixing Of Lt 3Phase Cross Arm Including Transporting Of Materials From Road Side To Site 35 Fixing Of Lt 1Phase Cross Arm Including Transporting Of Materials From Road Side To Site 36 Fixing Of Ht Lt Ti Fitting Including Transporting Of Materials From Road Side To Site 37 Erection Of Ht Side Arm With Stud Including Transporting Of Materials From Road Side To Site 38 Erection Of Lt Side Arm With Stud Including Transporting Of Materials From Road Side To Site 39 Fixing Of Insulator ( Per Location ) Including Transporting Of Materials From Road Side To Site 40 Ht Lines - Stringing, Sagging, Binding Including Transporting Of Materials From Road Side To Site-For 7 / 2.59 Acsr ( 1Span / Wire ) 41 Ht Lines - Stringing, Sagging, Binding Including Transporting Of Materials From Road Side To Site-For 7 / 3.35 Acsr ( 1Span / Wire ) 42 Ht Lines - Stringing, Sagging, Binding Including Transporting Of Materials From Road Side To Site-For 7 / 4.09 Acsr ( 1Span / Wire ) 43 Ht Lines - Stringing, Sagging, Binding Including Transporting Of Materials From Road Side To Site-For Dog Conductor ( 1Span / Wire ) 44 For Ht Line Clear Works For For 7 / 2.59 Acsr ( 1Span / Wire ) 45 For Ht Line Clear Works For For 7 / 3.35 Acsr ( 1Span / Wire ) 46 For Ht Line Clear Works For For 7 / 4.09 Acsr ( 1Span / Wire ) 47 For Ht Line Clear Works For Fordog Conductor ( 1Span / Wire ) 48 Lt Lines - Stringing, Sagging, Binding Including Transporting Of Materials From Road Side To Site- For 7 / 2.59 Acsr 49 Lt Lines - Stringing, Sagging, Binding Including Transporting Of Materials From Road Side To Site- For 7 / 3.35 Acsr 50 Lt Lines - Stringing, Sagging, Binding Including Transporting Of Materials From Road Side To Site- For 7 / 4.09 Acsr 51 For Lt Line Clear Works For For 7 / 2.59 Acsr ( 1Span / Wire ) 52 For Lt Line Clear Works For For 7 / 3.35 Acsr ( 1Span / Wire ) 53 For Lt Line Clear Works For For 7 / 4.09 Acsr ( 1Span / Wire ) 54 Guarding Per Span Length- Spilt Neutral Guarding 55 Guarding Per Span Length- Flat Guarding ( 2 Wires ) 56 Guarding Per Span Length- Flat Guarding ( 4 Wires ) 57 Guarding Per Span Length- Flat Guarding ( 6 Wires ) 58 Guarding Per Span Length- Cradle Guarding ( Fixing Of X Arm Lacing ) 59 Guarding Per Span Length- Fixing Of One Earthing Device With Stud 60 Erection Of Transformer / Dismantling Upto 200Kva 61 Erection Of Transformer / Dismantling Upto 250Kva 62 Erection Of Transformer / Dismantling Upto 500Kva 63 Erection Of Centre Support ( Including Concrete ) 64 Erection Of Feeder Cable With Open Type Fuse Unit Per Feeder And For Each Addl Feeder 65 Erection Of Feeder Cable With Open Type Fuse Unit - For Each Addl Feeder 66 Erection Of Feeder Cable -Bus Bar Arrangement With Open Type 67 Loading & Unloading Of Distribution Transformer Below 250Kva 68 Loading & Unloading Of Distribution Transformer 250Kva 69 Loading & Unloading Of Distribution Transformer 500Kva 70 Plinth Work For 500Kva Dt With Construction Material 71 Tube Light Erection-1*40W Tube Light Complete Set ( Including Transport ) 72 Tube Light Erection-For Sv Lamp And Mercury Lamp Complete Set ( Including Transport ) 73 Tube Light Erection-For Cfl Lamp Complete Set ( Including Transport ) 74 Manufacturing Of Clamps 50*8 Mm 75 Manufacturing Of Clamps 65*10 Mm 76 Alteration Of Clamps 77 Corroded Pole Welding With 4 Pieces Of Charges ( Incl.Concreting Of Cement ) Note:Pieces Will Be Supplied By Board 78 Welding Joint For New Rsj Pole At Workshop Per Foot Run Of Welding 79 Street Light Switching Pont Arrangement 80 Drilling Less Than 23Mm Holes Per Hole / Slatted Hole 81 Cutting Of Channel 82 Cutting Of Flat 83 Cutting Of Angle 84 Rsj Pole Cutting 85 Tubular Pole Cutting 86 Rail Pole Cutting 87 Fabrication Of Lightning Arrestor Frame 88 Lt-Changing Of Pin Point To Cut Point 89 Ht-Changing Of Pin Point To Cut Point 90 Erection Of Service Connection Materials-1Ph Service 91 Erection Of Service Connection Materials-3Ph Service 92 Dismantling Of Deteriorated Poles With Concrete In Damaged Condition Including Grill Separation Etc., 93 Dismantling Of Poles Without Concrete In Damaged Condition Including Grill Separation Etc., 94 Providing Jumpering At Cut Point 95 Complete Replacement Of Worn Out Earth Wire Per Structure 96 Labour For Manufacturing Of Open Type Fuse Unit ( Materials Supplied By Board ) 97 Manufacturing Of Hg Fuse Stool Incl. Materials 98 Tree Clearence In Ht Or Lt Location- For Ordy. Tree Clearence And Throng Bushes & Trees 400 / Head / Day 99 Tree Clearence In Ht Or Lt Location- For Coconut Trees And Palmrah Trees 500 / Head / Day 100 Painting-Double Pole Transformer Structure Materials ( Double Coat ) 101 Painting-Pole ( Colour Washing With Distember ) 2 Nos 102 Painting-For Transformer Only ( Double Coat With Paint ) 103 Numbering Of Poles Without Paint ( Labour ) 104 Numbering Of Poles With Paint ( Labour ) 105 Numbering Of Distribution Trnasformer ( Painting And Writing Of Name Board Size-1-1 / 4*1 Incl Cost Of Paint And Ms Sheet 106 Writing In Seating Channel ( Paint To Be Supplied By Contractor ) 107 Painting Of Rcc Strcucture Poles All Metal Parts, Snowcem & Aluminium Paint To Be Supplied By Contractor 108 Painting Of Rcc Strcucture Poles All Metal Parts, Snowcem & Aluminium Paint To Be Supplied By Board 109 Painting Of Rsj Structure Poles & Metal Parts-Aluminium Paint To Be Supplied By Contrcator 110 Painting Of Rsj Structure Poles & Metal Parts-Aluminium Paint To Be Supplied By Board 111 Set Right Of Leaning Ht Pole / Lt Pole Including X Arms, Ti Fittings 112 Transformer Structure Erection-Excavation Of Structure Pole Pits ( Nos ) 113 Transformer Structure Erection-Erection Of Structure Poles ( Nos ) 114 Transformer Structure Erection-Excavation Of Stay Pits ( 4Nos ) 115 Transformer Structure Erection-Erection Of Stay Set ( 4Nos ) 116 Transformer Structure Erection-Concreting Of Structure Poles Incl.Materials 117 Transformer Structure Erection-Concreting Of Stays ( 4Nos ) Incl.Materials 118 Transformer Structure Erection-Base Concreting 119 Erection Of Structure Materials-Top Channel 120 Erection Of Structure Materials-Transformer Seating Channel And Belting Angle 121 Erection Of Structure Materials-Ab Switch ( Complete ) 122 Erection Of Structure Materials-Hg Fuse ( Complete ) 123 Erection Of Structure Materials-Jumpering 124 Erection Of Structure Materials-Ht Las 125 Erection Of Structure Materials-Lt Las 126 Earthing System-Excavation Of 3 Nos. Earth Pits 127 Earthing System-Excavation Of Earth Wire Trenches And Paving Of Earth Wire, Erection Of 3 Nos. Earth Pipe And Giving Earth Connection, Earthing Of All Metal Parts, Las Etc., Including Central Connection 128 Earthing System-Mason Works For Earth Pits And Structure Pole Coping ( Cementsupplied By Contractor ) 129 Earthing System-Painting Of Transformer Structure 2 Coats ( Labour Only ) 130 Earthing System-Painting With Distember Paint On Poles 131 Earthing System-Spreading Yard Jelly And Cut Stone And Bricks Including Material 132 Earthing System-Writing Of Name Board And Target Board 133 Erection Of Tapping Structure-Excavation Of Structure Pole Pit. 134 Erection Of Tapping Structure-Erection Of Structure Pole. 135 Erection Of Tapping Structure-Excavation Of Stay Pit. 136 Erection Of Tapping Structure-Erection Of Stay Set. 137 Erection Of Tapping Structure-Concreting Of Pole. 138 Erection Of Tapping Structure-Concreting Of Stay. 139 Erection Of Tapping Structure-Base Concreting. 140 Erection Of Structure Materials-Top Channel 141 Erection Of Structure Materials-Ab Switch ( Complete ) 142 Erection Of Structure Materials-Assemble, Operating Pipe Fixing Etc., Fixing Of Cross Bracing 143 Earthing System-Excavation Of 1 No. Earth Pits Excavation Of Earth Wire Trench And Paving Of Earth Wire, Erection Of 1 No. Earth Pipe And Giving Earth Connection, Earthing Of All Metal Parts, For Tapping Structure. 144 Earthing System-Mason Works For Earth Pit ( Including Material ) 145 Colour Coating On Poles With Iron Materials Including Paint And Distember 146 Transporting Of 42 Twin Rsj Pole From Roadside Pole Pit 147 Fabrication Of 42 Twin Rsj Pole, Materials Supplied By Board. 148 Excavation & Erection Of Twin 422 Fabricated Rsj Pole 149 Concreting Of 42 Twin Rsj Pole 150 Singple Pole Structure Erection- 9.0 Mtr Rcc Pole ( Square ) -Loading & Unloading Of Poles 151 Singple Pole Structure Erection- 9.0 Mtr Rcc Pole ( Square ) -Excavation Of Pole Pit & Pole Erection 152 Singple Pole Structure Erection- 9.0 Mtr Rcc Pole ( Square ) -Transporting Road Side To Pole Pit 153 Singple Pole Structure Erection-Excavation And Erection Of Stay Set Complete With Stay Clamps ( With 16Mm Stay Rod With Base Plate ) 154 Fixing Of Single Pole Structure Materials & Structure Clamps ( Tapping Channel - 1 No., Tr.Bed, Erection Ab Switch - 1 Set, Erection Hg Fuse Set - 1 Set ) 155 Erection Of 16 / 25 Kva, 11Kv / 433 Volts 3 Phase 156 Earthing For 9 Mtr Rcc Structure Square Pole ( 3 Pits ) 157 Concreting Including Materials For 9 Mtr Rcc Square Pole-Base Concreting 1:4:8 500*650*150Mm, Pole Concreting1:2:4 500*500*1700& Coping 1:2:4 ( As Per Actuals ) 158 Concreting Including Materials For Stay Sets. ( Cement, Jelly And Sand ) 159 Fixing Of 11 Kv Lighting Arrester, Metal Oxide, 9 Kv, 5 Ka ( Ht & Lt ) 160 Erection Of Lt Wiring Kit ( Double Open Type Circuit ) 161 Fixing Of Caution / Danger Board As Per Drawing 162 Painting Of Single Pole Str Including Iron Materials Double Coat With Painting Materials 163 Fixing Of Guarding X Arm 164 Fixing Of Tapping Channel X Arm 165 Fixing Of Lt Shackle 166 Fixing Of 11 Kv Strain Disc 167 Maintenance Of Ab Switch-Replacement Of Male And Female One Number Contact And Ptinsulator 168 Maintenance Of Ab Switch-Cleaning Of Contacts, Lubrication And Checking Of Operating Pipe Movments 169 Maintenance Of Distribution Transformer-Cleaning Of Ht / Lt Bushings, Oil Level Checking , Silical Gelreplacement, Terminal Tightness Checking, Cleaning Of Dt Yard, Earth Pit Watering And Maintenance Of Open Types Etc., 170 Maintenance Of Distribution Transformer-Providing Of U Jumpering 171 Dismantling Of Other Line Materials - ( Please Mention In Percentage For Respective Line Material Errection Works )

BOQ

Name of the work: Execution of contract towards Extension of supply (except agri and natural calamities) and Other works inUrban Division /Tirunelveli EDC
Sl. No. Item Description
1Normal ground- Excavation of Pole pits (1.25m * 0.5m*1.5m) for 7.32m, 7.5m, 8m, 8.23m poles
2Normal ground- Erection of 7.32m, 7.5m, 8m, 8.23m poles
3Rocky ground- Excavation of Pole pits (1.25m * 0.5m*1.5m) for 7.32m, 7.5m, 8m, 8.23m poles
4Rocky ground- Erection of 7.32m, 7.5m, 8m, 8.23m poles
5Normal ground- Excavation of Pole pits (1.25m * 0.6m*1.83m) for 9M & 9.14M poles
6Normal ground- Erection of 9M & 9.14M poles
7Rocky ground- Excavation of Pole pits (1.25m * 0.6m*1.83m) for 9M & 9.14M poles
8Rocky ground- Erection of 9M & 9.14M poles
9Normal ground- Excavation of Pole pits (1.25m * 0.6m*2.19m) for above 9.14M poles & 36\" length RS Joists
10Normal ground- Erection ofabove 9.14M poles & 36\" length RS Joists
11Rocky ground- Excavation of Pole pits (1.25m * 0.6m*2.19m) for above 9.14M poles & 36\" length RS Joists
12Rocky ground- Erection ofabove 9.14M poles & 36\" length RS Joists
13Transporting of poles from road side to pole pit - 7.32m, 7.5m, 8m, 8.23m RCC pole
14Transporting of poles from road side to pole pit - 9m, 9.14m RCC/PSC pole
15Transporting of poles from road side to pole pit - RSJ 36\" Pole
16Transporting of poles from road side to pole pit - RSJ 42\" and above
17Loading and Unloading of poles - 7.32m, 7.5m, 8m, 8.23m RCC pole
18Loading and Unloading of poles - 9m, 9.14m RCC/PSC pole
19Loading and Unloading of poles - RS Joists, tubular & rail pole (above 9.14m)
20Concreting of poles as per Board Standards (2\"*2\"*5\"). The materialsuch as cement, sand, jelly, etc., have to be supplied by the contractor (Cement concrete mix 1:4:8 using 40mm hard broken stone including cost of labour charges.for placing Transporting of sant,jally,from box and water curing for 14 days etc,.)
21Coping of pole (0.6m*0.6m*0.35m)
22Concreting of stay (o.3m * 0.3m * 1.5m) including materials except cement
23Coil earthing per pole & pole earthing
24Normal ground- Excavation of stay pit (1.00m * 0.5m*1.5m) with transporting of materials to site (For stay set)
25Normal ground- Erection of stay set
26Rocky ground- Excavation of stay pit (1.00m * 0.5m*1.5m) with transporting of materials to site (For stay set)
27Rocky ground- Erection of stay set
28Loading charges of cement
29Unloading charges of cement
30Stacking charges
31Fixing of V & Channel cross arm 5.5\" including transporting of materials from road side to site
32Fixing of V & Channel cross arm 4.5\" including transporting of materials from road side to site
33Fixing of V & Channel cross arm 3.5\" including transporting of materials from road side to site
34Fixing of LT 3Phase cross arm including transporting of materials from road side to site
35Fixing of LT 1Phase cross arm including transporting of materials from road side to site
36Fixing of HT LT TI fitting including transporting of materials from road side to site
37Erection of HT Side arm with stud including transporting of materials from road side to site
38Erection of LT Side arm with stud including transporting of materials from road side to site
39Fixing of insulator (per location) including transporting of materials from road side to site
40HT lines - Stringing, Sagging, binding including transporting of materials from road side to site-For 7/2.59 ACSR (1Span/Wire)
41HT lines - Stringing, Sagging, binding including transporting of materials from road side to site-For 7/3.35 ACSR (1Span/Wire)
42HT lines - Stringing, Sagging, binding including transporting of materials from road side to site-For 7/4.09 ACSR (1Span/Wire)
43HT lines - Stringing, Sagging, binding including transporting of materials from road side to site-For Dog Conductor (1Span/Wire)
44For HT line clear works for For 7/2.59 ACSR (1Span/Wire)
45For HT line clear works for For 7/3.35 ACSR (1Span/Wire)
46For HT line clear works for For 7/4.09 ACSR (1Span/Wire)
47For HT line clear works for ForDog conductor (1Span/Wire)
48LT lines - Stringing, Sagging, binding including transporting of materials from road side to site- For 7/2.59 ACSR
49LT lines - Stringing, Sagging, binding including transporting of materials from road side to site- For 7/3.35 ACSR
50LT lines - Stringing, Sagging, binding including transporting of materials from road side to site- For 7/4.09 ACSR
51For LT line clear works for For 7/2.59 ACSR (1Span/Wire)
52For LT line clear works for For 7/3.35 ACSR (1Span/Wire)
53For LT line clear works for For 7/4.09 ACSR (1Span/Wire)
54Guarding per span length- Spilt Neutral Guarding
55Guarding per span length- Flat Guarding (2 wires)
56Guarding per span length- Flat Guarding (4 wires)
57Guarding per span length- Flat Guarding (6 wires)
58Guarding per span length- Cradle Guarding (Fixing of \" X\" arm Lacing )
59Guarding per span length- Fixing of one earthing device with stud
60Erection of transformer/dismantling upto 200KVA
61Erection of transformer/dismantling upto 250KVA
62Erection of transformer/dismantling upto 500KVA
63Erection of centre support (Including concrete)
64Erection of feeder cable with open type fuse unit per feeder and for each addl feeder
65Erection of feeder cable with open type fuse unit - for each addl feeder
66Erection of feeder cable -Bus bar arrangement with open type
67Loading & unloading of Distribution transformer below 250KVA
68Loading & unloading of Distribution transformer 250KVA
69Loading & unloading of Distribution transformer 500KVA
70Plinth work for 500KVA DT with construction material
71Tube light erection-1*40W tube light complete set (including transport)
72Tube light erection-For SV lamp and mercury lamp complete set (including transport)
73Tube light erection-For CFL lamp complete set (including transport)
74Manufacturing of clamps 50*8 mm
75Manufacturing of clamps 65*10 mm
76Alteration of clamps
77Corroded pole welding with 4 pieces of charges (incl.Concreting of cement) note:pieces will be supplied by board
78Welding joint for new RSJ pole at workshop per foot run of welding
79Street light switching pont arrangement
80Drilling less than 23mm holes per hole/slatted hole
81Cutting of channel
82Cutting of Flat
83Cutting of Angle
84RSJ pole cutting
85Tubular pole cutting
86Rail pole cutting
87Fabrication of lightning arrestor frame
88LT-Changing of pin point to cut point
89HT-Changing of pin point to cut point
90Erection of service connection materials-1Ph service
91Erection of service connection materials-3Ph service
92Dismantling of deteriorated poles with concrete in damaged condition including grill separation etc.,
93Dismantling of poles without concrete in damaged condition including grill separation etc.,
94Providing jumpering at cut point
95complete replacement of worn out earth wire per structure
96Labour for manufacturing of open type fuse unit (Materials supplied by board)
97Manufacturing of HG fuse stool incl. materials
98Tree clearence in HT or LT location- For ordy. Tree clearence and Throng bushes & trees 400/head/day
99Tree clearence in HT or LT location- For coconut trees and Palmrah trees 500/head/day
100Painting-Double pole Transformer structure materials (Double coat)
101Painting-Pole (Colour washing with distember) 2 Nos
102Painting-For transformer only (Double coat with paint)
103Numbering of poles without paint (Labour)
104Numbering of poles with paint (Labour)
105Numbering of Distribution Trnasformer (Painting and writing of name board size-1-1/4*1 incl cost of paint and MS sheet
106Writing in seating channel (Paint to be supplied by contractor)
107Painting of RCC Strcucture poles all metal parts, snowcem & aluminium paint to be supplied by contractor
108Painting of RCC Strcucture poles all metal parts, snowcem & aluminium paint to be supplied by board
109Painting of RSJ structure poles & metal parts-aluminium paint to be supplied by contrcator
110Painting of RSJ structure poles & metal parts-aluminium paint to be supplied by board
111Set right of leaning HT pole/LT pole including x arms, TI fittings
112Transformer structure erection-Excavation of structure pole pits ( Nos)
113Transformer structure erection-Erection of structure poles ( Nos)
114Transformer structure erection-Excavation of stay pits(4Nos)
115Transformer structure erection-Erection of stay set (4Nos)
116Transformer structure erection-Concreting of structure poles incl.materials
117Transformer structure erection-Concreting of stays (4Nos) incl.materials
118Transformer structure erection-Base Concreting
119Erection of Structure materials-Top Channel
120Erection of Structure materials-Transformer seating channel and belting angle
121Erection of Structure materials-AB switch (Complete)
122Erection of Structure materials-HG fuse (Complete)
123Erection of Structure materials-Jumpering
124Erection of Structure materials-HT LAS
125Erection of Structure materials-LT LAS
126Earthing system-Excavation of 3 Nos. earth pits
127Earthing system-Excavation of earth wire trenches and paving of earth wire, Erection of 3 Nos. earth pipe and giving earth connection, Earthing of all metal parts, Las etc., including central connection
128Earthing system-Mason works for earth pits and structure pole coping (cementsupplied by Contractor)
129Earthing system-Painting of transformer structure 2 coats (Labour only)
130Earthing system-Painting with Distember paint on poles
131Earthing system-Spreading yard jelly and cut stone and bricks including material
132Earthing system-Writing of name board and target board
133Erection of Tapping structure-Excavation of structure pole pit.
134Erection of Tapping structure-Erection of structure pole.
135Erection of Tapping structure-Excavation of stay pit.
136Erection of Tapping structure-Erection of stay set.
137Erection of Tapping structure-Concreting of pole.
138Erection of Tapping structure-Concreting of stay.
139Erection of Tapping structure-Base Concreting.
140Erection of Structure materials-Top channel
141Erection of Structure materials-AB switch (complete)
142Erection of Structure materials-Assemble, operating pipe fixing etc., fixing of cross bracing
143Earthing system-Excavation of 1 No. earth pits Excavation of earth wire trench and paving of earth wire, Erection of 1 No. earth pipe and giving earth connection, Earthing of all metal parts, for tapping structure.
144Earthing system-Mason works for earth pit (including material)
145Colour coating on poles with iron materials including paint and distember
146Transporting of 42\" twin RSJ pole from roadside pole pit
147Fabrication of 42\" Twin RSJ pole, Materials supplied by Board.
148Excavation & Erection of Twin 42\"2\" fabricated RSJ pole
149Concreting of 42\" twin RSJ pole
150Singple pole structure erection- 9.0 mtr RCC POLE (square) -Loading & Unloading of poles
151Singple pole structure erection- 9.0 mtr RCC POLE (square) -Excavation of pole pit & pole erection
152Singple pole structure erection- 9.0 mtr RCC POLE (square) -Transporting road side to pole pit
153Singple pole structure erection-Excavation and erection of stay set complete with stay clamps ( with 16mm stay rod with base plate )
154Fixing of single pole structure materials & structure clamps ( Tapping channel - 1 No., Tr.bed, Erection AB switch - 1 set, Erection HG Fuse set - 1 set )
155Erection of 16/25 KVA,11KV / 433 Volts 3 phase
156Earthing for 9 mtr RCC structure square pole(3 pits)
157Concreting including materials for 9 mtr RCC square pole-Base concreting 1:4:8 500*650*150mm, Pole concreting1:2:4 500*500*1700& Coping 1:2:4 ( as per actuals )
158Concreting including materials for stay sets. (cement, jelly and sand)
159Fixing of 11 Kv lighting arrester, metal oxide, 9 KV, 5 KA(HT & LT)
160Erection of LT wiring kit ( Double open type circuit)
161Fixing of caution / Danger Board as per drawing
162Painting of single pole str including iron materials double coat with painting materials
163Fixing of guarding X arm
164Fixing of Tapping channel X arm
165Fixing of LT shackle
166Fixing of 11 KV Strain Disc
167Maintenance of AB switch-Replacement of male and female one number contact and PTinsulator
168Maintenance of AB switch-Cleaning of contacts, lubrication and checking of operating pipe movments
169Maintenance of Distribution Transformer-Cleaning of HT/LT Bushings, Oil level checking , Silical gelreplacement, Terminal tightness checking, Cleaning of DT yard,earth pit watering and maintenance of open types etc.,
170Maintenance of Distribution Transformer-Providing of \"U\" jumpering
171Dismantling of other line materials - (Please mention In percentage for respective line material errection works)

AI Tender Summary

OUR REF NO 35820394
AUTHORITY Boards / Undertakings / PSU
TENDER VALUE 5 Lakhs
LAST DATE 02-02-2023
Authority
Authority Name Tamil Nadu Generation And Distribution Corporation Limited
Work Description Execution Of Contract For Extension Of Supply Works And Other Works In Eeudistribution Urban Division Tirunelveli - Normal Ground- Excavation Of Pole Pits ( 1.25M * 0.5M*1.5M ) For 7.32M, 7.5M, 8M, 8.23M Poles 2 Normal Ground- Erection Of 7.32M, 7.5M, 8M, 8.23M Poles 3 Rocky Ground- Excavation Of Pole Pits ( 1.25M * 0.5M*1.5M ) For 7.32M, 7.5M, 8M, 8.23M Poles 4 Rocky Ground- Erection Of 7.32M, 7.5M, 8M, 8.23M Poles 5 Normal Ground- Excavation Of Pole Pits ( 1.25M * 0.6M*1.83M ) For 9M & 9.14M Poles 6 Normal Ground- Erection Of 9M & 9.14M Poles 7 Rocky Ground- Excavation Of Pole Pits ( 1.25M * 0.6M*1.83M ) For 9M & 9.14M Poles 8 Rocky Ground- Erection Of 9M & 9.14M Poles 9 Normal Ground- Excavation Of Pole Pits ( 1.25M * 0.6M*2.19M ) For Above 9.14M Poles & 36 Length Rs Joists 10 Normal Ground- Erection Ofabove 9.14M Poles & 36 Length Rs Joists 11 Rocky Ground- Excavation Of Pole Pits ( 1.25M * 0.6M*2.19M ) For Above 9.14M Poles & 36 Length Rs Joists 12 Rocky Ground- Erection Ofabove 9.14M Poles & 36 Length Rs Joists 13 Transporting Of Poles From Road Side To Pole Pit - 7.32M, 7.5M, 8M, 8.23M Rcc Pole 14 Transporting Of Poles From Road Side To Pole Pit - 9M, 9.14M Rcc / Psc Pole 15 Transporting Of Poles From Road Side To Pole Pit - Rsj 36 Pole 16 Transporting Of Poles From Road Side To Pole Pit - Rsj 42 And Above 17 Loading And Unloading Of Poles - 7.32M, 7.5M, 8M, 8.23M Rcc Pole 18 Loading And Unloading Of Poles - 9M, 9.14M Rcc / Psc Pole 19 Loading And Unloading Of Poles - Rs Joists, Tubular & Rail Pole ( Above 9.14M ) 20 Concreting Of Poles As Per Board Standards ( 2*2*5 ) . The Materialsuch As Cement, Sand, Jelly, Etc., Have To Be Supplied By The Contractor ( Cement Concrete Mix 1:4:8 Using 40Mm Hard Broken Stone Including Cost Of Labour Charges.For Placing Transporting Of Sant, Jally, From Box And Water Curing For 14 Days Etc, . ) 21 Coping Of Pole ( 0.6M*0.6M*0.35M ) 22 Concreting Of Stay ( O.3M * 0.3M * 1.5M ) Including Materials Except Cement 23 Coil Earthing Per Pole & Pole Earthing 24 Normal Ground- Excavation Of Stay Pit ( 1.00M * 0.5M*1.5M ) With Transporting Of Materials To Site ( For Stay Set ) 25 Normal Ground- Erection Of Stay Set 26 Rocky Ground- Excavation Of Stay Pit ( 1.00M * 0.5M*1.5M ) With Transporting Of Materials To Site ( For Stay Set ) 27 Rocky Ground- Erection Of Stay Set 28 Loading Charges Of Cement 29 Unloading Charges Of Cement 30 Stacking Charges 31 Fixing Of V & Channel Cross Arm 5.5 Including Transporting Of Materials From Road Side To Site 32 Fixing Of V & Channel Cross Arm 4.5 Including Transporting Of Materials From Road Side To Site 33 Fixing Of V & Channel Cross Arm 3.5 Including Transporting Of Materials From Road Side To Site 34 Fixing Of Lt 3Phase Cross Arm Including Transporting Of Materials From Road Side To Site 35 Fixing Of Lt 1Phase Cross Arm Including Transporting Of Materials From Road Side To Site 36 Fixing Of Ht Lt Ti Fitting Including Transporting Of Materials From Road Side To Site 37 Erection Of Ht Side Arm With Stud Including Transporting Of Materials From Road Side To Site 38 Erection Of Lt Side Arm With Stud Including Transporting Of Materials From Road Side To Site 39 Fixing Of Insulator ( Per Location ) Including Transporting Of Materials From Road Side To Site 40 Ht Lines - Stringing, Sagging, Binding Including Transporting Of Materials From Road Side To Site-For 7 / 2.59 Acsr ( 1Span / Wire ) 41 Ht Lines - Stringing, Sagging, Binding Including Transporting Of Materials From Road Side To Site-For 7 / 3.35 Acsr ( 1Span / Wire ) 42 Ht Lines - Stringing, Sagging, Binding Including Transporting Of Materials From Road Side To Site-For 7 / 4.09 Acsr ( 1Span / Wire ) 43 Ht Lines - Stringing, Sagging, Binding Including Transporting Of Materials From Road Side To Site-For Dog Conductor ( 1Span / Wire ) 44 For Ht Line Clear Works For For 7 / 2.59 Acsr ( 1Span / Wire ) 45 For Ht Line Clear Works For For 7 / 3.35 Acsr ( 1Span / Wire ) 46 For Ht Line Clear Works For For 7 / 4.09 Acsr ( 1Span / Wire ) 47 For Ht Line Clear Works For Fordog Conductor ( 1Span / Wire ) 48 Lt Lines - Stringing, Sagging, Binding Including Transporting Of Materials From Road Side To Site- For 7 / 2.59 Acsr 49 Lt Lines - Stringing, Sagging, Binding Including Transporting Of Materials From Road Side To Site- For 7 / 3.35 Acsr 50 Lt Lines - Stringing, Sagging, Binding Including Transporting Of Materials From Road Side To Site- For 7 / 4.09 Acsr 51 For Lt Line Clear Works For For 7 / 2.59 Acsr ( 1Span / Wire ) 52 For Lt Line Clear Works For For 7 / 3.35 Acsr ( 1Span / Wire ) 53 For Lt Line Clear Works For For 7 / 4.09 Acsr ( 1Span / Wire ) 54 Guarding Per Span Length- Spilt Neutral Guarding 55 Guarding Per Span Length- Flat Guarding ( 2 Wires ) 56 Guarding Per Span Length- Flat Guarding ( 4 Wires ) 57 Guarding Per Span Length- Flat Guarding ( 6 Wires ) 58 Guarding Per Span Length- Cradle Guarding ( Fixing Of X Arm Lacing ) 59 Guarding Per Span Length- Fixing Of One Earthing Device With Stud 60 Erection Of Transformer / Dismantling Upto 200Kva 61 Erection Of Transformer / Dismantling Upto 250Kva 62 Erection Of Transformer / Dismantling Upto 500Kva 63 Erection Of Centre Support ( Including Concrete ) 64 Erection Of Feeder Cable With Open Type Fuse Unit Per Feeder And For Each Addl Feeder 65 Erection Of Feeder Cable With Open Type Fuse Unit - For Each Addl Feeder 66 Erection Of Feeder Cable -Bus Bar Arrangement With Open Type 67 Loading & Unloading Of Distribution Transformer Below 250Kva 68 Loading & Unloading Of Distribution Transformer 250Kva 69 Loading & Unloading Of Distribution Transformer 500Kva 70 Plinth Work For 500Kva Dt With Construction Material 71 Tube Light Erection-1*40W Tube Light Complete Set ( Including Transport ) 72 Tube Light Erection-For Sv Lamp And Mercury Lamp Complete Set ( Including Transport ) 73 Tube Light Erection-For Cfl Lamp Complete Set ( Including Transport ) 74 Manufacturing Of Clamps 50*8 Mm 75 Manufacturing Of Clamps 65*10 Mm 76 Alteration Of Clamps 77 Corroded Pole Welding With 4 Pieces Of Charges ( Incl.Concreting Of Cement ) Note:Pieces Will Be Supplied By Board 78 Welding Joint For New Rsj Pole At Workshop Per Foot Run Of Welding 79 Street Light Switching Pont Arrangement 80 Drilling Less Than 23Mm Holes Per Hole / Slatted Hole 81 Cutting Of Channel 82 Cutting Of Flat 83 Cutting Of Angle 84 Rsj Pole Cutting 85 Tubular Pole Cutting 86 Rail Pole Cutting 87 Fabrication Of Lightning Arrestor Frame 88 Lt-Changing Of Pin Point To Cut Point 89 Ht-Changing Of Pin Point To Cut Point 90 Erection Of Service Connection Materials-1Ph Service 91 Erection Of Service Connection Materials-3Ph Service 92 Dismantling Of Deteriorated Poles With Concrete In Damaged Condition Including Grill Separation Etc., 93 Dismantling Of Poles Without Concrete In Damaged Condition Including Grill Separation Etc., 94 Providing Jumpering At Cut Point 95 Complete Replacement Of Worn Out Earth Wire Per Structure 96 Labour For Manufacturing Of Open Type Fuse Unit ( Materials Supplied By Board ) 97 Manufacturing Of Hg Fuse Stool Incl. Materials 98 Tree Clearence In Ht Or Lt Location- For Ordy. Tree Clearence And Throng Bushes & Trees 400 / Head / Day 99 Tree Clearence In Ht Or Lt Location- For Coconut Trees And Palmrah Trees 500 / Head / Day 100 Painting-Double Pole Transformer Structure Materials ( Double Coat ) 101 Painting-Pole ( Colour Washing With Distember ) 2 Nos 102 Painting-For Transformer Only ( Double Coat With Paint ) 103 Numbering Of Poles Without Paint ( Labour ) 104 Numbering Of Poles With Paint ( Labour ) 105 Numbering Of Distribution Trnasformer ( Painting And Writing Of Name Board Size-1-1 / 4*1 Incl Cost Of Paint And Ms Sheet 106 Writing In Seating Channel ( Paint To Be Supplied By Contractor ) 107 Painting Of Rcc Strcucture Poles All Metal Parts, Snowcem & Aluminium Paint To Be Supplied By Contractor 108 Painting Of Rcc Strcucture Poles All Metal Parts, Snowcem & Aluminium Paint To Be Supplied By Board 109 Painting Of Rsj Structure Poles & Metal Parts-Aluminium Paint To Be Supplied By Contrcator 110 Painting Of Rsj Structure Poles & Metal Parts-Aluminium Paint To Be Supplied By Board 111 Set Right Of Leaning Ht Pole / Lt Pole Including X Arms, Ti Fittings 112 Transformer Structure Erection-Excavation Of Structure Pole Pits ( Nos ) 113 Transformer Structure Erection-Erection Of Structure Poles ( Nos ) 114 Transformer Structure Erection-Excavation Of Stay Pits ( 4Nos ) 115 Transformer Structure Erection-Erection Of Stay Set ( 4Nos ) 116 Transformer Structure Erection-Concreting Of Structure Poles Incl.Materials 117 Transformer Structure Erection-Concreting Of Stays ( 4Nos ) Incl.Materials 118 Transformer Structure Erection-Base Concreting 119 Erection Of Structure Materials-Top Channel 120 Erection Of Structure Materials-Transformer Seating Channel And Belting Angle 121 Erection Of Structure Materials-Ab Switch ( Complete ) 122 Erection Of Structure Materials-Hg Fuse ( Complete ) 123 Erection Of Structure Materials-Jumpering 124 Erection Of Structure Materials-Ht Las 125 Erection Of Structure Materials-Lt Las 126 Earthing System-Excavation Of 3 Nos. Earth Pits 127 Earthing System-Excavation Of Earth Wire Trenches And Paving Of Earth Wire, Erection Of 3 Nos. Earth Pipe And Giving Earth Connection, Earthing Of All Metal Parts, Las Etc., Including Central Connection 128 Earthing System-Mason Works For Earth Pits And Structure Pole Coping ( Cementsupplied By Contractor ) 129 Earthing System-Painting Of Transformer Structure 2 Coats ( Labour Only ) 130 Earthing System-Painting With Distember Paint On Poles 131 Earthing System-Spreading Yard Jelly And Cut Stone And Bricks Including Material 132 Earthing System-Writing Of Name Board And Target Board 133 Erection Of Tapping Structure-Excavation Of Structure Pole Pit. 134 Erection Of Tapping Structure-Erection Of Structure Pole. 135 Erection Of Tapping Structure-Excavation Of Stay Pit. 136 Erection Of Tapping Structure-Erection Of Stay Set. 137 Erection Of Tapping Structure-Concreting Of Pole. 138 Erection Of Tapping Structure-Concreting Of Stay. 139 Erection Of Tapping Structure-Base Concreting. 140 Erection Of Structure Materials-Top Channel 141 Erection Of Structure Materials-Ab Switch ( Complete ) 142 Erection Of Structure Materials-Assemble, Operating Pipe Fixing Etc., Fixing Of Cross Bracing 143 Earthing System-Excavation Of 1 No. Earth Pits Excavation Of Earth Wire Trench And Paving Of Earth Wire, Erection Of 1 No. Earth Pipe And Giving Earth Connection, Earthing Of All Metal Parts, For Tapping Structure. 144 Earthing System-Mason Works For Earth Pit ( Including Material ) 145 Colour Coating On Poles With Iron Materials Including Paint And Distember 146 Transporting Of 42 Twin Rsj Pole From Roadside Pole Pit 147 Fabrication Of 42 Twin Rsj Pole, Materials Supplied By Board. 148 Excavation & Erection Of Twin 422 Fabricated Rsj Pole 149 Concreting Of 42 Twin Rsj Pole 150 Singple Pole Structure Erection- 9.0 Mtr Rcc Pole ( Square ) -Loading & Unloading Of Poles 151 Singple Pole Structure Erection- 9.0 Mtr Rcc Pole ( Square ) -Excavation Of Pole Pit & Pole Erection 152 Singple Pole Structure Erection- 9.0 Mtr Rcc Pole ( Square ) -Transporting Road Side To Pole Pit 153 Singple Pole Structure Erection-Excavation And Erection Of Stay Set Complete With Stay Clamps ( With 16Mm Stay Rod With Base Plate ) 154 Fixing Of Single Pole Structure Materials & Structure Clamps ( Tapping Channel - 1 No., Tr.Bed, Erection Ab Switch - 1 Set, Erection Hg Fuse Set - 1 Set ) 155 Erection Of 16 / 25 Kva, 11Kv / 433 Volts 3 Phase 156 Earthing For 9 Mtr Rcc Structure Square Pole ( 3 Pits ) 157 Concreting Including Materials For 9 Mtr Rcc Square Pole-Base Concreting 1:4:8 500*650*150Mm, Pole Concreting1:2:4 500*500*1700& Coping 1:2:4 ( As Per Actuals ) 158 Concreting Including Materials For Stay Sets. ( Cement, Jelly And Sand ) 159 Fixing Of 11 Kv Lighting Arrester, Metal Oxide, 9 Kv, 5 Ka ( Ht & Lt ) 160 Erection Of Lt Wiring Kit ( Double Open Type Circuit ) 161 Fixing Of Caution / Danger Board As Per Drawing 162 Painting Of Single Pole Str Including Iron Materials Double Coat With Painting Materials 163 Fixing Of Guarding X Arm 164 Fixing Of Tapping Channel X Arm 165 Fixing Of Lt Shackle 166 Fixing Of 11 Kv Strain Disc 167 Maintenance Of Ab Switch-Replacement Of Male And Female One Number Contact And Ptinsulator 168 Maintenance Of Ab Switch-Cleaning Of Contacts, Lubrication And Checking Of Operating Pipe Movments 169 Maintenance Of Distribution Transformer-Cleaning Of Ht / Lt Bushings, Oil Level Checking , Silical Gelreplacement, Terminal Tightness Checking, Cleaning Of Dt Yard, Earth Pit Watering And Maintenance Of Open Types Etc., 170 Maintenance Of Distribution Transformer-Providing Of U Jumpering 171 Dismantling Of Other Line Materials - ( Please Mention In Percentage For Respective Line Material Errection Works )
Basic Detail
Tender No EEDU ETW 0092022 dt19 01 2023
Bidding Type Tender
Location
City Tirunelveli
State Tamil Nadu
Key Dates
Publish Date 19 Jan 2023
Submission Date 02 Feb 2023
Open Date 03 Feb 2023
Finance
Tender Value 5 Lakhs
Tender Fee Ref. Documents
EMD 5000
Exemption Not Available
Document List
BOQ_335698.xls
Spec.pdf
Tendernotice_1.pdf
143a70d3-e17b-449e-aec3-332e6511e996.html

Unlock Full AI Tender Summary

Get instant access to the complete AI-generated analysis — scope, eligibility, timeline & more.

Instant Access Secure Free
Your details are secure and used only for document delivery.

Tender Timeline

Jan 19, 2023
11:30 IST

Tender Published

Tender notice published.

Completed
Feb 02, 2023
17:00 IST

Bid Submission Deadline

Online submission via eProcurement portal.

Completed
Feb 03, 2023

Bid Opening Date

Technical bids will be opened and evaluated.

Completed

Tender Documents

Download All (ZIP) ↓
xls

BOQ_335698.xls

pdf

Spec.pdf

pdf

Tendernotice_1.pdf

html

143a70d3-e17b-449e-aec3-332e6511e996.html

Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender

TenderDetail
Loading tenders