| 1 | Earth work in excavation in soil containing 50 % or more of single or small size boulders up to 30 cm, size including in 20 cm, layers and breaking clods, ramming and dressing up for the purpose of making embankments of filling up ground depression lead up to 50 mtrs and left upto 1.50 mtrs. |
| 2 | Providing and laying in foundations and plinth cement concrete 1 : 4 : 8 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) excluding the cost of centring and shuttering. |
| 3 | Providing and fixing of RRC Ring in step wise below the level of water strate etc and above the platform hight of the Ring well . |
| 4 | Cement mortar 1 : 3 (1 cement : 3 fine sand) |
| 5 | Providing and fixing GI pipes complete with GI fittings including trenching and refilling etc (external work). a) 15 mm nominal bore |
| 6 | Providing and fixing GI pipes complete with GI fittings and clamps including cutting and making good the walls (internal work).a) 15 mm nominal bore |
| 7 | Supply of Syntex 1000 ltrs |
| 8 | Supply & installation of Water pump 1.5 HP |
| 9 | Boring/drilling bore well of 150 mmdia for dia for tube well by suitable method, including Machine drilling mounted on trucks in all strata, including hire & running charges of all equipment\"s, tools, plants & machineries required for the job, all complete as per direction of Engineer -in-charge complete as per direction of Engineer-in-charge.rate shall be including material , labour, lead , lift , transportation, GST , all taxes etc complete. Actual depth of bore shall be measured for payments. |
| 10 | Supplying, assembling, lowering and fixing in vertical position in bore well, Msmedium well casing (CM) pipe of 200mm dia, including required hire and labour charges, fittings & accessories etc. all complete as per direction of Engineer -in-charge. rate shall be including material , labour, lead , lift , transportation , GST , all taxes etc complete. Nothing extra shall be paid separately. Actual depth of bore shall be measured for payments. |
| 11 | Supply of submersible pump of approved make TEXMO/CRI/ KIRLOSKAR/CROMPTON/KSB any type of model ,as per specification.a) Submersible pump 2 HP |
| 12 | Taking \"yield test\" of newly drilled Bore well with help of 90\"\" \"\"V\"\" notch method or other suitable method with all required equipments and labours etc complete . |
| 13 | Supplying ,fitting and installingPVC 50mm nominal bore |
| 14 | Supply of Submersible star -delta stater Panel premium |
| 15 | Supply of 3 cores flat 4mm 2 copper cable |
| 16 | Supply ,fiiting and installing the following accessories of approved makes including cost of all materials,labour tools and tackles etc complete.a) 2\"\" dia carbon steel glove valve KSB/VENUS Make |
| 17 | b)2\"\" dia Carbon -steel golve Non return valve KSB/VENUS Make |
| 18 | C) MS Clam to hold 2\"\" pvcPipe |
| 19 | d)Pressure Gauge 20kg/cm2 |
| 20 | e) PVC Nipple 2\" dia |
| 21 | f) PVC Reducer 4\"x2\"/4\"x2\" dia |
| 22 | g) PVCbend 2\" |
| 23 | h) Bore well cover for 8\" dia bore well |
| 24 | i) 1/2\"\" dia PVC Rope |
| 25 | J)Toflontape |
| 26 | k) M-seal |
| 27 | l) Water proof joint kit for cable joint |
| 28 | Supply , Installtion , Testing and commissioning of Control panel with dry cable for Run&SPP protection for borewell pump , 3 phase 2 HP all complete as per direction of Engineer-in-charge. Suitable for Approved Makes : Kirloskar / CG / Deccan / Laxmi. Quoted rate shall be including material , labour, lead , lift , transportation , GST , all taxes etc complete |