Tender For Replacement Of Central Ac Plants Against Ber At Mpo And Ttd Bldg And Replacement Of Summer Appliances Against Ber Items For The Year 2014-15 And 2015-16 At Itr Chandipur, chandipur-Odisha

Military Engineer Services-MES has published Tender For Replacement Of Central Ac Plants Against Ber At Mpo And Ttd Bldg And Replacement Of Summer Appliances Against Ber Items For The Year 2014-15 And 2015-16 At Itr Chandipur. Submission Date for this Tender is 07-02-2023. Air Conditioner Tenders in chandipur Odisha. Bidders can get complete Tender details and download the document.




Tender Notice

35563995
Corrigendum : Tender For Replacement Of Central Ac Plants Against Ber At Mpo And Ttd Bldg And Replacement Of Summer Appliances Against Ber Items For The Year 2014-15 And 2015-16 At Itr Chandipur
Open Tender
Indian
Odisha
chandipur
07-02-2023

Tender Details

Replacement Of Central Ac Plants Against Ber At Mpo And Ttd Bldg And Replacement Of Summer Appliances Against Ber Items For The Year 2014-15 And 2015-16 At Itr Chandipur

Corrigendum Details

Sr No CorrigendumDate Corrignedum CorrigendumType NewSubmissionDate
1 17-Jan-2023 Corri01 BOQ 31-01-2023
2 31-Jan-2023 Bid Auto Extn Corrigendum Bid Auto Extn Corrigendum 07-02-2023

Key Value

Document Fees
INR 2000 /-
EMD
INR 449000.0 /-
Tender Value
INR 3.74 Crore /-

BOQ Items

Name of Work : REPLACEMENT OF CENTRAL AC PLANTS AGAINST BER AT MPO AND TTD BLDG AND REPLACEMENT OF SUMMER APPLIANCES AGAINST BER ITEMS FOR THE YEAR 2014-15 & 2015-16 AT ITR CHANDIPUR
Sl. No. Item Description
1SECTION-I (CENTRAL AC PLANT)
2Supply , install , commissioning and testing of Water Cooled scroll Chillers withmulti compressors, comprising of Semi - Hermetic/Open Type Compressors, DX Evaporator, Shell and Tube Condenser,suitable expansion device, suitable for operation on R - 134a /R - 407c/R - 410a refrigerants and of nominal capacity Chilled water in : 12.8° C Chilled water out : 7.2° C Chilled water flow : 84 USGPM Fouling factor : 0.0001 FPS Condenser Condenser water in : 27° C Condenser water out : 32.2° C Condenser water flow : 140 USGPM Fouling factor : 0.00025 FPS IKW shall be Max 0.68 K.W / TR(on tender condition) COP: 5.2 35 TR ( 2 Working + 1 Stand by)
3CHW PUMPSETS (Primary Pump) Supplying, erection, testing and commissioning of Centrifugal End suction type primary chilled/hot water pump set capable of delivering 84 USGPM of water against a head 12 Mtr. each pump shall comprise the following as required as per specifications. 1 No. - Split Casing type pump with bronze impeller, S.S Shaft, CED Coated C.I body and mechanical seal. Duly insulated with 80 kg/cum density resin onded fiber glass cladded with aluminium sheets of 0.5mm thickness and properly clamped to pump in two semicircular sections as per specifications. 1 No.- Suitable HP, TEFC squirrel cage induction motor with class "F" insulation,IP -55 Protection,Eff-2, 1450 RPM synchronous speed, operating on 415 volts ± 10%, 3 phase, 50 Hz A.C. supply. (2 Working + 1 Stand by )
4COND. PUMPSETS Supplying, erection, testing and commissioning of Centrifugal End suction type primary chilled/hot water pump set capable of delivering 140 USGPM of water against a head 12 Mtr. each pump shall comprise the following as required as per specifications. 1 No. - Split Casing type pump with bronze impeller, S.S Shaft, CED Coated C.I body and mechanical seal. Duly insulated with 80 kg/cum density resin bonded fiber glass cladded with aluminium sheets of 0.5mm thickness and properly clamped to pump in two semicircular sections as per specifications. 1 No.- Suitable HP, TEFC squirrel cage induction motor with class "F" insulation,IP -55 Protection,Eff-2, 1450 RPM synchronous speed, operating on 415 volts ± 10%, 3 phase, 50 Hz A.C. supply. (2 Working + 1 Stand by )
5Chilled/Hot Water Secondary Pumps (variable pumping system) Supplying, erection, testing and commissioning of package type End Suction type secondary chilled/hot water pumping system with VFD and all pump system controller, comprising of: a) Pumping set with CED Coated cast Iron casing, Bronze impellers with stainless steel shaft, connected to suitable capacity TEFC ventilated induction motor with class "F" insulation, eff-1, 3 Phase, 1450 RPM, suitable for 415 volts ± 10%, 3 phase, 50 Hz A.C. supply.b) Duly insulated with 80 kg/cum density resin bonded fiber glass cladded with aluminium sheets of 0.5mm thickness and properly clamped to pump in two semicircular sections as per specifications.c) Unless otherwise specified, renewable wear ring of bronze shall be furnished atleast on the casing d) Variable secondary Panel should have a dedicated programmable logic controller with individual drive for each pump and with required no. of sensors and the entire unit has to be procured from the Pump manufacturer to ensure the smooth operation of the system. The Programmable logic controller shall be able to control minimum 1 Pump and maximum of 4/6 Pumps, Automatic cascade control of pumps, automatic sequence change, Friction loss compensation, pump status shall be there. Display shall be graphical type with minimum 320 pixels X 240 Pixels VGA display with backlight.Drive should have rated input frequency 50 Hz and output frequency range of 0.5 to 132 Hz. An IP41/IP55 Nema Standard powder coated steel enclosure for Basement/Roof top, with sufficient capacity of cooling fan shall house all the electrical control components.
6e) Microprocessor based control panel shall have suitable hardware & software so that it can be integrated directly to IBMS with standard communication open protocol using backnet / Modbus as well as open IP. f)(All the Pump set will have their control panel with respect to the motor rating). g) All pumps to be provided with separate variable frequency drives. Control panel should also consist of cooling fan. h) One panel for each job will be provided (for a set of two/three pumps) and the panels should be installed adjacent to each other. j) The pumps should be suitable for heating as well as chilled water circulation. k) Lot-Mounting frame work with anti vibration pads. l) Electronic Differential Pressure Transmitters as required. m) suitable flanged suction and delivery headers in C-Class MS n) Complete set system to be mounted on a common MS base frame and shall follow following duty with following no. of pumps:
7Secondary chilled water pump sets Flow Rate : 84 USGPM Head : 32 Metre WC (2 Working + 1 Stand by )
8Hot water pump sets Flow Rate :36USGPM Head : 32 Metre WC (2 Working + 1 Stand by )
9CHILLER PLANT MANAGER Supply, Installation, testing & commissioning of Chiller Plant Manager for systematic operation of AC plant comprising of: 3 Nos. 35/30 TR Water Cooled Chillers with VFD (2 Working + 1 Stand By) , 3 Nos. Primary Chilled Water pumps( 2 Working +1 Stand By) pumps & Motorized Valves etc.3 Nos. Variable Secondry Chilled Water pumps with VFDs ( 3 Working +1 Stand By) pumps & Motorized Valves etc.3 Nos. Cooling Tower( 1 Working +1 Stand By). Workstation as required (Intel core i7 processor with 4 GB RAM, 1GB Graphic Card and 500B HDD, Windows 7 64 bit.) including 21" LED Monitor, keyboard, mouse, and all required accessories complete including Latest version of MS Office and Antivirus software and as required Network superwise controller unit (Imported UL listed) for connecting all controllers to it and software integration and transfering data to P.C. The processors shall be 32 bit, 50 MHZ, shall be able to store reports and event logs & on BACnet / IP protocol Dedicated Chiller Plant manager software having inbuilt application. Programmable controller (Imported UL Listed) having processors of 32 Bit 50 MHZ, LON CHIP) BACNET compatible/Modbus/ IP protocol, controller for Pumps,Cooling Tower . The controller shall support easy Graphical Programming and shall be able to store the programme in the controller rather than store in the PC. It should include Lockable Mounting Cabinets duly powder coated, connector strip, internal wiring & relays etc. CPM should be able to communicate/interface with main IBMS. All required software and hardware to be provided. Any other hardwares required etc
10FIELD DEVICES & SENSORS FOR CHILLERS & PUMPS Immerssion type Temperature Sensor with thermowell Outside Temp. & RH Sensor Level Switch Flow sensor/ Flow meter Differential Pressure Sensors & Differential Pressure Transmitter (for zone differential pressure sensing) LOT OF CABLES, CONDUITS & CABLE TRAY Cabling from all instruments, controls & valves to DDC and communication cabling from DDC to central equipment complete with cable gland, earthing, supports & PVC conduits etc. Surface laid or cable tray laid cables shall be ferruled and tagged, and shall use lugs for termination at both ends. Wherever multicore cables are used, the price shall include the cost of Marshalling Boxes (MS Powder Coated with Elmex Terminals) to connect the multicore cables to 2 core cables for termination in equipments Chiller Plant Manager as described above
11Supply, installation, commissioning and testing of induced draft top discharge counterflow type FRP Cooling Tower (Rectangular / Round bottle shape) with FRP body and base, water spray headers, cooling tower fills, fan with motor, supporting bas frames, as per manufacturer"s standard instructions. 35 TR (2 Working + 1 Stand by )
12HOT WATER GENERATOR Providing and installing electrically operated Hot Water Generator of following nominal capacity having 1mm thick stainless steel lining with heaters arranged in banks and controlled by electronic controller and thermostats so that following flow rate hot water at 70° C and with nominal variations could be supplied including 75mm thick fibre glass/ mineral wool/ insulation finished with 1.25mm thick G.I. sheet clading including necessary electrical panel board, having suitable incoming & outgoing switch gears for boiler and pump automatic controls including inlet and outlet connections for water, foundation for boiler as per specifications complete as required. 25 KW,36/28 GPM (2 Working + 1 Stand by )
13Supplying, installing, testing and commissioning of factory built Floor mounted double skin type air handling units made of 45 mm thick panels consisting of pre plasticized G.I. casing of thickness 0.8 mm outside layer and 0.8 mm plane inside layer with polyurethene foam (PUF) insulation of density 32 kg/m3 factory injected between them by injection moulding machine, complete with blower section with blower DIDW Backward curved centrifugal fan of 60 mm WC static pressure, 6 row deep cooling coil , & 2 row deep Heating coil section with aluminium finned copper tubes (tube thickness not less than 0.5mm), filter sections with 50 mm thick washable synthetic type Pre filters having efficiency 90% down to 10 micron and provision for Fine filters having efficiency 99% down to 5 micron,provision for ewating coil, belt drive package with TEFC drive motor suitable for 415 ± 10% volts, 50 Hz, 3 phase, A.C supply, complete with drain connections with drain valve, stainless steel drain pan, thermometers and pressure gauge at the inlet and outlet of the coils, necessary vibration isolation arrangement etc, complete as per specifications of following capacities: 23500 CFM , 70 TR
14Supply, installation, commis-sioning and testing of Variable Frequency Drives with IP 55 enclosures and mainsdisconnect switch comprising of the following:(a) Built in dual 5% impedance DC link reactor (harmonic filters) on the positive and negative rails of the DC bus of the Variable Frequency Drive. (b) Built in EMC filters (electro magnetic compatibility filters) for restriction of conducted emissions to comply with IEC61800:3 (un restricted distribution) :2004 Category C 1 (50 meter). (c) Three feedback PID controller having capability to simultaneously accept 3 feedback signals from temperature sensors or pressure sensors for process optimization and accordingly control the speed of the AHUs or pumps. (d) Integral graphical keypad. Note:(i) Cost of temperature sensor and control cables not included. (ii) Separate Starter not required for switching on motor and pump 4 KW
15Supplying, laying/ fixing, testing and commissioning of chilled water piping inside the building (with necessary clamps, vibration isolators and fittings but excluding valves, strainers, gauges etc.) duly insulated with 80 kg/cum density resin bonded fiber glass or 144 Kg/ cum density mineral wool (non Combustible) pipe section insulation covered with a layer of 120 gm/sqm polythene sheet (vapour barrier) and finally applying 0.63mm aluminium sheet cladding complete with type3 , grade 1 roofing feltstrip(as per IS:1322 as amended up to date ) at joints and repairing of damage to building etc. as per specifications and as required. Note: The Pipes of sizes 150mm & below shall be M.S. "C" class as per IS : 1239 and pipes size above 150mm shall be welded black steel pipe heavy class as per IS: 3589, from minimum 6.35mm thick M.S. Sheet for pipes upto 350 mm dia. and from minimum 7mm thick MS sheet for pipe-s of 400 mm dia and above of following nominal sizes of chilled water piping:-
1680 mm dia (50 mm thick insulation)
1765 mm dia (50 mm thick insulation)
1850 mm dia (50 mm thick insulation)
1940 mm dia (50 mm thick insulation)
2032 mm dia (50 mm thick insulation)
2125 mm dia (50 mm thick insulation)
22Supplying, fixing, testing and commissioning of valves, strainers, gauges in the chilled water plumbing duly insulated to the same specifications as the connected piping and adequately supported as per specifications.
23BUTTERFLY VALVE (MANUAL) with C I body SS Disc, Nitrile Rubber Seal & O- Ring PN 16 pressure rating for chilled water/hot eater circulation as specified of following sizes:- 80 mm dia
2450 mm dia
25Ball Valve 25 mm dia
26NON - RETURN VALVE with dual plate of C I body SS plates vulcanized NBR seal flanged end & PN 16 pressure rating as specified. 65 MM DIA
27Supply and fixing Industrial type pressure gauges with gun metal / brass valves complete all as specified and as directed.
28Supply and fixing Industrial type thermometres complete all as specified and as directed
29Y - STRAINER of Ductile CI Body flanged ends with stainless steel strainer for chilled / hot water circulation including insulation as specified of following sizes:-
3065 mm dia
3150 mm dia
3280 mm dia
3325 mm dia
34BALANCING VALVE WITH BUILT IN MEASURING FACILITY with C I body flanged construction with EPDM coated disc with long pitch with protected out pipe insulation & PN 16 pressure rating for chilled / hot water circulation as specified. 50 mm dia
35MOTORISED BALANCING VALVE WITH BUILT IN MEASURING FACILITY with C I body flanged construction with EPDM coated disc with long pitch with protected out pipe insulation & PN 16 pressure rating for chilled / hot water circulation as specified.
3650 mm dia
3765 mm dia
38Flexible Connection (Neoprene Rubber Type) of size:- 50 mm dia
3980 mm dia
40Insulated M.S Closed Expansion tank of 500 Ltrs. Supply installation testing commissioning of Closed Expansion tanks for chilled water shall be of M.S. construction and of adequate capacity, to contain 200% of the maximum expansion likely to take place in the system. The tank shall be insulated and be complete with valves, drain, Safety Valve, PN16 and Pressurisation Unit complete with double pump (2CMH, 25mWC), IP55 control panel, pressure transmitter, flow meter, interconnecting piping & wiring, PN16.
41PRESSURE INDEPENDENT BALANCING CUM CONTROL VALVE WITH THERMOSTAT/HIGH RANGEABILITY VALVE WITH THERMOSTAT FOR AHU Supply, Installation, Testing and Commissioning of following sizes electronic, self-balancing, pressure independent type dynamic balancing valve with integrated 2 way modulating control valve in a single body. The actuator shall be capable of accepting upto 10V DC and upto 20 mA electric signal and shall provide similar transduced feedback output to control system. Maximum close off pressure shall not be less than 6 Bar for upto 50 mm valves and 7 Bar for 65 mm & above. Valves should have pressure rating of 25 Bar minimum. 80 mm dia.(636 LPM)
42Condensate Drain Pipe Supplying, fixing, testing and commissioning of UPVC drain piping with all fitting such as bends, tees etc. necessary clamps, adequate support duly insulate with 9 mm nitrile rubber insulation complete as per specifications and requirement. 32 mm dia.
43Supply installation testing commissioning of Pot strainer for 100mm Dia.pipe complete all as specified and as directed by engineer in charge.
44Supply installation testing commissioning of Manual Air - purge valve of 15mm dia & complete as per specifications.
45Supply installation testing commissioning of Air and Dirt Separator with complete accessories. For 100 Dia .Pipe.
46CONDENSER WATER PIPE Supplying, fixing, testing and commissioning of condenser water pipes of following sizes of MS "C" class along with necessary clamps, vibration isolators and fittings such as bends,tees etc.but excluding valves, strainers, gauges etc adequately supported on rigid supports duly painted/buried in ground excavation and refilling etc. as per specification and as required complete in all respect. Note:-The Pipes size 150mm & below shall be M.S. "C" class as per IS : 1239 and pipes size above 150mm shall be welded black steel pipe heavy class as per IS: 3589, from minimum 6.35mm thick M.S. Sheet for pipes upto 350 mm dia. And from minimum 7mm thick MS sheet for pipes of 400 mm dia and above. 100mm Dia.
47VALVES WITHOUT INSULATION Supplying, fixing, testing and commissioning of following valves, gauges and strainers for condenser water circulation as per specifications BUTTERFLY VALVE (MANUAL) with C I body SS disc nitrile sheet & O - ring & PN 16 pressure rating as specified. 80 mm Dia
48NON - RETURN VALVE with dual plate of C I body SS plates vulcanized NBR seal flanged end & PN 16 pressure rating as 80 mm dia
49DUCT AND AIR DISTRIBUTION DUCTING Supply, installation, balancing and commissioning of factory fabricated GSS sheet metal rectangular/round ducting complete with neoprene rubber gaskets, elbows, splitter dampers, vanes, hangers, supports etc. as per approved drawings and specifications of following sheet thickness complete as required.
50Thickness 0.63 mm sheet
51Thickness 0.80 mm sheet
52Thickness 1.00 mm sheet
53Thickness 1.25 mm sheet
54Supply, installation, balancing and commissioning of fabricated at site GSS sheet metal rectangular/round ducting complete with neoprene rubber gaskets, elbows, splitter dampers, vanes, hangers, supports etc. as per approved drawings and specifications of following sheet thickness complete as required. Note:- Duct only for in case of critical fittings to be fabricated at site
55Thickness 0.63 mm sheet
56Thickness 0.80 mm sheet
57Thickness 1.00 mm sheet
58Thickness 1.25 mm sheet
59Supply, installation, testing and commissioning of GI volume control duct damper complete with neoprene rubber gaskets,nuts, bolts, screws linkages, flanges etc, as per specifications.
60Supplying & fixing of powder coated extruded aluminium Supply Air Grills with aluminium volume control dampers as per specifications.
61Supplying & fixing of powder coated extruded aluminium Return Air Grills with louvers but without volume controldampers complete all as specified and directed.
62Supplying & fixing of Powder coated extruded aluminium Return Air Grills with louvers but without volume control dampers
63Supply, installation, testing and commissioning of Motorized (ON-OFF Type) duct mounted GI volume control damper/actuator with enthalpy sensor and necessary control wire (minimum 1.5 sqmm) for integration within AHU room
64Damper
65Actuator
66Supply, fixing, testing and commissioning of fire dampers in supply air duct/main branch and return air path as and where required of required sizes i/c control wiring, the damper shall be motorized and spring return so as to close the damper in the event of power failure automatically and open the same in case of power being restored. The spring return action shall be inbuilt mechanism and not externally mounted. The damper shall also be closed in the event of fire signal complete as require and as per specification.
67Fire Damper
68Actuator
69INSULATIONSupply and fixing of acoustic lining of supply air duct and plenum with 25 mm thick resin bonded glass wool having density of 32 kg/m³, with 25 mm X 25 mm GI section of 1.25 mm thick, at 600 mm centre to centre covered with Reinforced Plastic tissue paper and 0.5 mm thick perforated aluminum sheet fixed to inside surface of ducts with cadmium plated nuts, bolts, stick pins, CPRX compound etc. complete as required and as per specifications.
70Supplying and fixing of 25mm thick duly laminated aluminum foil of mat finish closed cell Nitrile rubber (Class "O") insulation on existing duct after applying suitable adhesive for Nitrile rubber. The joints shall be sealed with 50 mm wide and 3 mm thick self adhesive nitrile rubber tape insulation complete as per specifications and as required.
71Supply and fixing of CHILLER PANEL Ics = 50KA Incomers:-One number (1x400A, 4P MCCB,50KA) 1No Incomer of 400A 4P MCCB with microprocessor based over current, short circuit & earth fault release. 3 Nos. phase indicating lamps to show the incoming power with control MCB, 1 No. ON/OFF indication, 1 No. digital multifunction meter and matching cast resin CT"s. Bus Bar Section A set of TPN Aluminium bus bar rated for 500A (after considering all necessary deratings) 3 phase 4wire, 50Hz. A minimum derating factor of 0.75 must be taken for calculation of bus bar sizes. The bus bar size after derating shall be equal to the ampere given in the BOQ. current density of bus-bars shall not be more than 1 Amps/sq.mm for Aluminium and earth bus size shall be suitable of system fault level. The outgoing feeders are as follows : OUTGOING: 6 Nos. 100A feeder having one No. 100A 4P MCCB,50KA with microprocessor based releases for O/C, S/C along with time delay for all protections, 1 No. ON/OFF indications. 3 Nos. DOL starter feeder suitable for 1.5 HP motor (2Working+1Standby) with DM type MCCB with isolable neutral, 3 nos TP contactor, 1 No timer , 1 No overload relay, 1 no. ON/OFF indication and other switchgear rating as per type II coordination alongwith 1no. digital ammeter with matching cast resin CT"s and 1 no auto manual selector switch.
723 Nos. DOL starter feeder suitable for 3.0 HP motor (2Working+1Standby) with DM type MCCB with isolable neutral, 3 nos TP contactor, 1no timer , 1no overload relay, 1 no. ON/OFF indication and other switchgear rating as per type II coordination alongwith 1no. digital ammeter with matching cast resin CT"s and 1 no auto manual selector switch. 3 Nos. DOL starter feeder suitable for 2.0 HP motor (2Working+1Standby) with DM type MCCB with isolable neutral, 3 nos TP contactor, 1no timer , 1no overload relay, 1 no. ON/OFF indication and other switchgear rating as per type II coordination alongwith 1no. digital ammeter with matching cast resin CT"s and 1 no auto manual selector switch. 3 Nos. DOL starter feeder suitable for 2.0 HP motor (2Working+1Standby) with DM type MCCB with isolable neutral, 3 nos TP contactor, 1no timer , 1no overload relay, 1 no. ON/OFF indication and other switchgear rating as per type II coordination alongwith 1no. digital ammeter with matching cast resin CT"s and 1 no auto manual selector switch. 1 No. 16 A TP MCCB. 2 Nos. 32A TP MCCB. 1 set of complete wiring CHILLER PANEL as describe above and shown in SLD.
73STARTERS PANEL Supplying, assembling, erecting, connecting, testing and commissioning of dust, damp and vermin proof wall mounting factory built sheet steel enclosed non- drawout modular type single starter cubicle fabricated out of suitable sized 1.6mm thick PCRC sheet, duly painted complete with earth studs, numbering & sign writing, interconnection & including copper conductor flexible connection with all accessories, etc. complete & as per specifications and mounted with the followings etc. Item including 4core 1.5sq.mm FRLS flexible cable with ON/OFF LED iluminated push buttons in seperate enclosure box to be in recessed manner. (Starters should have NO/ NC contacts for remote/ fire control facility etc. complete as required.) Fully automatic DOL starter suitable for 7.5 KW motor including 40A 4P MCCB "C", Push Buttons, LED Indications, Auto/ Manual/ OFF selector switch, SPPR, FRLS copper control/ power wiring etc. complete all as specified and directed.
74Supply of XLPE insulated, armoured heavy duty electric cable 1100 volts grade, of following cross-sectional area:-
756 sqmm 4 core copper armoured XLPE cable
764 sqmm 4core copper armoured XLPE cable
7735 sqmm 3.5 core aluminium armoured XLPE cable
78300 sqmm 3.5 core aluminium armoured XLPE cable
79MV CABLE END TERMINATIONS Supplying and making end termination with brass compression gland and aluminium lugs for following size of PVC insulated and PVC sheathed / XLPE aluminium conductor cable of 1.1 KV grade as required.
803½ C X 35 sqmm (35mm)
813½ C X 300 sq. mm (70mm)
82Supplying and making indoor end termination with brass compression gland and Copper lugs for following size of PVC insulated and PVC sheathed / XLPE Copper conductor cable of 1.1 KV grade as required. 2/3/3.5/4 CORES Cu. CABLE WITH Cu. LUGS
834C X 6 sq. mm
844C X 4 sq. mm
85M & L for earthing complete with GI plate electrode of size 600 x 600 x 6 mm thick bured directly in ground vertically at a depth not less 2.25 mtr below normal ground level with top edge of earth plate at a depth not less than 1.5 mtr below normal ground level surrounded from all sides by 1.5 cm thick packed layer of charcoal of dust and common salt filling in alternate layers and making electrode connection by using GI strip of size 25X4 mm at two points by means of bolts nuts check nuts and washers made of brass and earth strip protected by light grade 40 mm dia GI Pipe upto test point and connected to main switch board are main controlled board with provision of GI pipe medium grade 20mm bore for watering including funnel wire mass RCC pit cover and PCC Chamber pit with 1:2: 4 type B1 (including excavation earth work) all as specified and shown on plate No 3 of SSR Part-1 including testing complete.
86Providing and fixing 25 mm X 5 mm G.I. strip on surface or in recess for connections etc. as required complete all as specified and as directed
87Providing and fixing 6 SWG dia G.I. wire on surface or in recess for loop earthing as required complete all as specified and as directed.
88CABLE TRAY Supplying and installing following size of perforated Hot Dipped Galvanised Iron cable tray (Galvanisation thickness not less than 50 microns) with perforation not more than 17.5%, in convenient sections, joined with connectors, suspended from the ceiling with G.I. suspenders including G.I. bolts & nuts, etc. as required.
89150 mm width X 50 mm depth X 1.6 mm thickness
90300 mm width X 50 mm depth X 1.6 mm thickness
91Supplying and installing following size of perforated Hot Dipped Galvanised Iron cable tray "bends" (galvanisation not less than 50 microns) with perforation not more than 17.5%, in convenient sections, joined with connectors, suspended from the ceiling with G.I. suspenders including G.I. bolts & nuts, etc.as required
92150 mm width X 50 mm depth X 1.6 mm thickness
93300 mm width X 50 mm depth X 1.6 mm thickness
94Supplying and installing following size of perforated Hot Dipped Galvanised Iron cable tray "Tee" (galvanisation not less than 50 microns) with perforation not more than 17.5%, in convenient sections, joined with connectors, suspended from the ceiling with G.I. suspenders including G.I. bolts & nuts, etc. as required
95150 mm width X 50 mm depth X 1.6 mm thickness
96300 mm width X 50 mm depth X 1.6 mm thickness
97Supplying and installing following size of perforated Hot Dipped Galvanised Iron cable tray "Cross member"(galvanisation not less than 50 microns) with perforation not more than 17.5%, in convenient sections, joined with connectors, suspended from the ceiling with G.I. suspenders including G.I. bolts & nuts, etc as required.
98150 mm width X 50 mm depth X 1.6 mm thickness
99300 mm width X 50 mm depth X 1.6 mm thickness
100Supplying and installing following size of perforated Hot Dipped Galvanised Iron cable tray "Reducer" (galvanisation not less than 50 microns) with perforation not more than17.5%, in convenient sections, joined with connectors, suspended from the ceiling with G.I. suspenders including G.I. bolts & nuts, etc as required
101150 mm width X 50 mm depth X 1.6 mm thickness
102300 mm width X 50 mm depth X 1.6 mm thickness
103Supply , install , commissioning and testing of Water Cooled scroll Chillers with multi compressors, comprising of Semi - Hermetic/Open Type Compressors, DX Evaporator, Shell and Tube Condenser,suitable expansion device, suitable for operation on R-134a/ R-407c/R - 410a refrigerants and of nominal capacity Chilled water in : 12.8° C Chilled water out : 7.2° C Chilled water flow : 72 USGPM Fouling factor : 0.0001 FPS Condenser Condenser water in : 27° C Condenser water out : 32.2° C Condenser water flow : 120 USGPM Fouling factor : 0.00025 FPS IKW shall be Max 0.68 K.W / TR(on tender condition) COP-5.2 30 TR ( 2 Working + 1 Stand by)
104CHW PUMP SETS (Primary pump) Supplying, erection, testing and commissioning of Centrifugal End suction type primary chilled/hot water pump set capable of delivering 72 USGPM of water against a head 12 Mtr. each pump shall comprise the following as required as per specifications. 1 No. - Split Casing type pump with bronze impeller, S.S Shaft, CED Coated C.I body and mechanical seal. Duly insulated with 80 kg/cum density resin bonded fiber glass cladded with aluminium sheets of 0.5mm thickness and properly clamped to pump in two semicircular sections as per specifications. 1 No.- Suitable HP, TEFC squirrel cage induction motor with class "F" insulation,IP -55 Protection,Eff-2, 1450 RPM synchronous speed, operating on 415 volts ± 10%, 3 phase, 50 Hz A.C. supply.(2 Working + 1 Stand by )
105COND. PUMPSETS (Primary pump) Supplying, erection, testing and commissioning of Centrifugal End suction type primary chilled/hot water pump set capable of delivering 120 USGPM of water against a head 12 Mtr. each pump shall comprise the following as required as per specifications. 1 No. - Split Casing type pump with bronze impeller, S.S Shaft, CED Coated C.I body and mechanical seal. Duly insulated with 80 kg/cum density resin bonded fiber glass cladded with aluminium sheets of 0.5mm thickness and properly clamped to pump in two semicircular sections as per specifications. 1 No.- Suitable HP, TEFC squirrel cage induction motor with class "F" insulation,IP -55 Protection,Eff-2, 1450 RPM synchronous speed, operating on 415 volts ± 10%, 3 phase, 50 Hz A.C. supply. (2 Working + 1 Stand by )
106Chilled/Hot Water Secondary Pumps (variable pumping system) Supplying, erection, testing and commissioning of package type End Suction type secondary chilled/hot water pumping system with VFD and all pump system controller, comprising of: a) Pumping set with CED Coated cast Iron casing, Bronze impellers with stainless steel shaft, connected to suitable capacity TEFC ventilated induction motor with class "F" insulation, eff-1, 3 Phase, 1450 RPM, suitable for 415 volts ± 10%, 3 phase, 50 Hz A.C. supply. b) Duly insulated with 80 kg/cum density resin bonded fiber glass cladded with aluminium sheets of 0.5mm thickness and properly clamped to pump in two semicircular sections as per specifications. c) Unless otherwise specified, renewable wear ring of bronze shall be furnished atleast on the casing d) Variable secondary Panel should have a dedicated programmable logic controller with individual drive for each pump and with required no. of sensors and the entire unit has to be procured from the Pump manufacturer to ensure the smooth operation of the system. The Programmable logic controller shall be able to control minimum 1 Pump and maximum of 4/6 Pumps, Automatic cascade control of pumps, automatic sequence change, Friction loss compensation, pump status shall be there. Display shall be graphical type with minimum 320 pixels X 240 Pixels VGA display with backlight.Drive should have rated input frequency 50 Hz and output frequency range of 0.5 to 132 Hz. An IP41/IP55 Nema Standard powder coated steel enclosure for Basement/Roof top, with sufficient capacity of cooling fan shall house all the electrical control components.
107e) Microprocessor based control panel shall have suitable hardware & software so that it can be integrated directly to IBMS with standard communication open protocol using backnet / Modbus as well as open IP. f) (All the Pump set will have their control panel with respect to the motor rating). g) All pumps to be provided with separate variable frequency drives. Control panel should also consist of cooling fan. h) One panel for each job will be provided (for a set of two/three pumps) and the panels should be installed adjacent to each other. j) The pumps should be suitable for heating as well as chilled water circulation. k) Lot-Mounting frame work with anti vibration pads. l) Electronic Differential Pressure Transmitters as required. m) suitable flanged suction and delivery headers in C-Class MS n) Complete set system to be mounted on a common MS base frame and shall follow following duty with following no. of pumps:
108Secondary chilled water pump sets Flow Rate : 72 USGPM Head : 32 Metre WC (2 Working + 1 Stand by )
109Hot water pump sets Flow Rate :28USGPM Head : 32 Metre WC (2 Working + 1 Stand by )
110Supply, installation, commissioning and testing of induced draft top discharge counterflow type FRP Cooling Tower (Rectangular / Round bottle shape) with FRP body and base, water spray headers, cooling tower fills, fan with motor, supporting base frames, as per manufacturer"s standard instructions. 30 TR (2 Working + 1 Stand by )
111Air Handling Units (AHU) Supplying, installing, testing and commissioning of factory built Floor mounted double skin type air handling units made of 45 mm thick panels consisting of pre plasticized G.I. casing of thickness 0.8 mm outside layer and 0.8 mm plane inside layer with polyurethene foam (PUF) insulation of density 32 kg/m3 factory injected between them by injection moulding machine, complete with blower section with blower DIDW Backward curved centrifugal fan of 60 mm WC static pressure, 6 row deep cooling coil , & 2 row deep Heating coil section with aluminium finned copper tubes (tube thickness not less than 0.5mm), filter sections with 50 mm thick washable synthetic type Pre filters having efficiency 90% down to 10 micron and provision for Fine filters having efficiency 99% down to 5 micron,provision for ewating coil, belt drive package with TEFC drive motor suitable for 415 ± 10% volts, 50 Hz, 3 phase, A.C supply, complete with drain connections with drain valve, stainless steel drain pan, thermometers and pressure gauge at the inlet and outlet of the coils, necessary vibration isolation arrangement etc, complete as per specifications of following capacities: 8000 CFM , 28 TR (For Ground Floor)
112Supplying, installing, testing and commissioning of factory built Celing suspended double skin type air handling units made of 25 mm thick panels consisting of pre plasticized G.I. casing of thickness 0.6 mm outside layer and 0.6 mm plane inside layer with polyurethene foam (PUF) insulation of density 32 kg/m3 factory injected between them by injection moulding machine, complete with blower section with blower DIDW Backward curved centrifugal fan of 60 mm WC static pressure, 6 row deep cooling coil , & 2 row deep Heating coil section with aluminium finned copper tubes (tube thickness not less than 0.5mm), filter sections with 50 mm thick washable synthetic type Pre filters having efficiency 90% down to 10 micron and provision for Fine filters having efficiency 99% down to 5 micron,provision for ewating coil, belt drive package with TEFC drive motor suitable for 415 ± 10% volts, 50 Hz, 3 phase, A.C supply, complete with drain connections with drain valve, stainless steel drain pan, thermometers and pressure gauge at the inlet and outlet of the coils, necessary vibration isolation arrangement etc, complete as per specifications of following capacities:
1132600 CFM, 8 TR (For First Floor)
1147000 CFM, 24 TR (For First Floor)
115Supply, installation, commis-sioning and testing of Variable Frequency Drives with IP 55 enclosures and mains disconnect switch comprising of the following: (a) Built in dual 5% impedance DC link reactor (harmonic filters) on the positive and negative rails of the DC bus of the Variable Frequency Drive. (b) Built in EMC filters (electro magnetic compatibility filters) for restriction of conducted emissions to comply with IEC61800:3 (un restricted distribution) :2004 Category C 1 (50 meter). (c) Three feedback PID controller having capability to simultaneously accept 3 feedback signals from temperature sensors or pressure sensors for process optimization and accordingly control the speed of the AHUs or pumps. (d) Integral graphical keypad. Note: (i) Cost of temperature sensor and control cables not included. (ii) Separate Starter not required for switching on motor and pump
1161.2 KW
1172.2 KW
118PRESSURE INDEPENDENT BALANCING CUM CONTROL VALVE WITH THERMOSTAT/HIGH RANGEABILITY VALVE WITH THERMOSTAT FOR AHU Supply, Installation, Testing and Commissioning of following sizes electronic, self-balancing, pressure independent type dynamic balancing valve with integrated 2 way modulating control valve in a single body. The actuator shall be capable of accepting upto 10V DC and upto 20 mA electric signal and shall provide similar transduced feedback output to control system. Maximum close off pressure shall not be less than 6 Bar for upto 50 mm valves and 7 Bar for 65 mm & above. Valves should have pressure rating of 25 Bar minimum.
11950 mm dia (181 LPM)
12040 mm dia (137 LPM)
12125 mm dia (60 LPM)
122Supply, installation, balancing and commissioning offabricated at site M.S sheet metal (22 G) rectangular/round ducting complete with neoprene rubber gaskets, elbows, splitter dampers, vanes, hangers, supports etc. as per approved drawings and specifications of following sheet thickness complete as required
123Supply and fixing of AHU STARTER PANEL Ics = 50kA-First FloorIncomer 1 No. Incomer 32Amps 4P MCCB with microprocessor based releases for O/C, S/C, 3 Nos. phase indicating lamps to show the incoming power with control 6A TP MCB,and 1 no. digital multifunction meter with matching cast resin CT"s. Bus Bar One set of TPN, Al. bus bar rated 200 Amps (after considering necessary deratings of 75%) for phases and neutral for half capacity of phases. The outgoing feeders are as follows : 1 No. DOL starter feeder suitable for 3.0 HP motor with DM type MCCB with isolable neutral, 3 nos TP contactor, 1no timer,1no overload relay, 1 no. ON/OFF indication and other switchgear rating as per type II coordination alongwith 1no. digital ammeter with matching cast resin CT"s and 1 no auto manual selector switch. 1 No. DOL starter feeder suitable for 1.5 HP motor with DM type MCCB with isolable neutral, 3 nos TP contactor, 1no timer,1no overload relay, 1 no. ON/OFF indication and other switchgear rating as per type II coordination alongwith 1no. digital ammeter with matching cast resin CT"s and 1 no auto manual selector switch. AHU PANEL as describe above and shown in SLD.
124STARTERS PANEL Supplying, assembling, erecting, connecting, testing and commissioning of dust, damp and vermin proof wall mounting factory built sheet steel enclosed non- drawout modular type single starter cubicle fabricated out of suitable sized 1.6mm thick PCRC sheet, duly painted complete with earth studs, numbering & sign writing, interconnection & including copper conductor flexible connection with all accessories, etc. complete & as per specifications and mounted with the followings etc. complete as required. Item including 4core 1.5sq.mm FRLS flexible cable with ON/OFF LED iluminated push buttons in seperate enclosure box to be in recessed manner. (Starters should have NO/ NC contacts for remote/ fire control facility etc. complete as required.) Fully automatic DOL starter suitable for 3.7 KW motor including 32A 4P MCCB "C", Push Buttons, LED Indications, Auto/ Manual/ OFF selector switch, SPPR, FRLS copper control/ power wiring etc. Complete as required.
125SECTION-II (MANNING & OPERATION DURING DEFECT LIABILITY PERIOD)
126Manning & Operation of Central type AC plant 3X30 TR (2W + 1SB) installed at TTD Bldg of ITR Chandipur during defect liability period with 03 shifts/day (08 hours per Shift) (0600 hrs to 1400hrs, 1400 hrs to 2200 hrs & 2200 hrs to 0600 hrs) including Saturdays, Sundays & holidays with deployment of one operator per shift (ITI/ diploma holder having adequate experience in the respective trade) during the defect liability period, starting from satisfactory completion of Phase-I test complete all as specified and directed as under:-
127Twelve (12) Months immediately after completion of phase-I test
128Twelve (12) Months after completion of item 55.10 above
129Manning & Operation of Central type AC plant 3X35 TR (2W + 1SB) installed at MPO Bldg of ITR Chandipur during defect liability period with 02 shifts/day (08 hours per Shift) (0600 hrs to 1400hrs & 1400 hrs to 2200 hrs ) excluding Sunday & holiday with deployment of one operator per shift (ITI/ diploma holder having adequate experience in the respective trade) during the defect liability period, starting from satisfactory completion of Phase-I test complete all as specified and directed as under:-
130Twelve (12) Months immediately after completion of phase-I test
131Twelve (12) Months after completion of item 56.10 above
132NOTE (For items 55 to 56.2 above) : The rates quoted for operation and maintenance of installations will include the following :- (i) Providing optimum manpower. Minimum qualification of all the manpower employed will be ITI passed in respective field of work with minimum 3 years experience. The contractor will submit the details of manpower employed before commencement of work. (ii) Duty timings will be as follows. For round the clock duties: 1st shift - 06:00 - 14:00 Hrs, 2nd shift - 14:00 - 22:00 Hrs, 3rd shift - 22:00 Hrs - 06:00 Hrs. For General duty/one shift - 08:30 - 16:30 Hrs. (iii) Al the tradesmem shall wear proper uniform with firm name and shoes at the installation, colour of uniform will be dircted by Engineer in Charge. (iv) Daily cleaning and maintenance of equipement and inside the installation shall be carried out by the staff employed by contractor without any exta cost to the departement and if fail to do the maintenance panelty @ 500/- per day imposed or decision of GE will be final & Binding. (v) Quoted rate is deemed to be inclusive of all consumables includingtoppingup required refrigerant gas, compressor oil required for maintaining the plant at good working condition and desired condition of 22ºC ± 3ºC and relative humidity 50 % ± 5 %. (vi) Daily consumables such as grease, gland rope, cotton waste etc shall be provided by contractor at installations and the unit rate quoted shall be inclusive of the same (vii) The contractor shall be responsible for safe custody of all the plants / equipements under his contract.
133(viii) Contractor shall solely responsible for any mishappening / accident and loss to life due to negligence of the workmen engaged in the work. No compensation shall be admissible on this account. (ix) The Contractor shall sign inventory of the equipment/Bldg of MES installation before commencement of work any damage/theft to the Govt. property, the contractor will be responsible and recovery to this effect will be made as decided. (x)The operators should have a sound knowledge of plants equipment . (xi) During currency of contract If there is any change of staff, same to be informed in writing to the accepting officer well in advance. The Accepting Officer reserves the right whether to change the staff. However he can remove any staff on the basis of Non Performance. (xii) Contractor shall be liable to comply with all the relevant rules and regulations as issued and revised by Labour commission time to time regarding wages. (xiii) The operator shall not leave the installation without reliever and Installation shall not be left unmanned in any case. If any staff found absent, Three times of the min wages prescribed as per the Govt charges as penalty (xiv) Weekly Area cleaning including cutting of grass, etc all around the installations as directed otherwise penalty @ 500/- per day imposed or decision of GE will be final & Binding. (xv) Any abnormality observed to be immediately intimated to the maintenance team with intimation to the concerned MES Personnel / in charge. (xvi) Minimum required tools, T&P, safety equipment etc always available with the operator
134(xvii) Log sheets to be maintained regularly in binding book with respect to detailed parameters of AC parameter such as DBT, WBT, RH, Power consumed, etc and signed by the contractor him self or his authorised rep all as directed by the Engr-in-Charge (xviii) First aid box including medicines shall be kept in the installations (xix) All consumable items such as refrigrant Gas, compressor Oil, Greece, including descaling with chemicals, servicing of plants. AHU , Ducts , Filters, Condensing Pipes and Coil, Cooling Tower, fire damper, Heaters etc required for operation of plants hshall be provided by contractor at his own cost as per the manufacturer"s instruction and direction of GE during period of manning and operation, cost of the same shall be deemed to include in the unit rate quoted by the contractor. (xx)All the personnel employed for operation and maintenance should be in proper uniform with firm name and safety outfits as per relevant norms. They may also be required to be deployed in any other locations other than mentioned above as per the site requirements and exigencies. (xxi) The rates are deemed to include minimum fair wages, EPF, ECIS etc to paid to the employed personnel as per the rules enforced by the Govt time to time and payment of all taxes as per govt rule. (xxii) The rates quoted by the tenderer shall be deemed to include wages including revised rate of variable Dearness Allowance (VDA) alongwith all taxes, statutory levies/duties such as Labour Welfare tax, Govt Service Tax (GST), EPF, ESI, Bonus, etc as applicable on date and levied by the Central/State Govt payable under respective statutes as applicable from time to time. For this account nothing extrashall be admissible. (xxiii) In case of any changes in the minimum wages or any statutory wage component as per the Applicable Laws during the Contract period, Service provider has to cater for the same in this quote. In this regard, no extra claim is admissible.
135SECTION-III (MANNING & OPERATION AND COMPREHENSIVE MAINTENANCE AFTER DEFECT LIABILITY PERIOD)
136Manning & Operation of Central type AC plant 3X35 TR (2W + 1SB) installed at MPO Bldg of ITR Chandipur with 02 shifts/day (08 hours per Shift) (0600 hrs to 1400hrs & 1400 hrs to 2200 hrs ) excluding Sunday & holiday with deployment of one operator per shift (ITI/ diploma holder having adequate experience in the respective trade) during the following period, starting from satisfactory completion of Defect liability period complete all as specified and directed.
137Twelve (12) Months after completion of Defect liability period
138Twelve (12) Months after completion of item 58.10 above
139Twelve (12) Months after completion of item 58.20 above
140NOTE (For item 58 to 58.30 above) : The rates quoted for operation and maintenance of installations will include the following :- (i) Providing optimum manpower. Minimum qualification of all the manpower employed will be ITI passed in respective field of work with minimum 3 years experience. The contractor will submit the details of manpower employed before commencement of work. (ii) Duty timings will be as follows. For round the clock duties: 1st shift - 06:00 - 14:00 Hrs, 2nd shift - 14:00 - 22:00 Hrs, 3rd shift - 22:00 Hrs - 06:00 Hrs. For General duty/one shift - 08:30 - 16:30 Hrs. (iii) Al the tradesmem shall wear proper uniform with firm name and shoes at the installation, colour of uniform will be dircted by Engineer in Charge. (iv) Daily cleaning and maintenance of equipement and inside the installation shall be carried out by the staff employed by contractor without any exta cost to the departement and if fail to do the maintenance panelty @ 500/- per day imposed or decision of GE will be final & Binding. (v) Quoted rate is deemed to be inclusive of all consumables includingtoppingup required refrigerant gas, compressor oil required for maintaining the plant at good working condition & desired condition of 22ºC ± 3ºC and relative humidity 50 % ± 5 %. (vi) Daily consumables such as grease, gland rope, cotton waste etc shall be provided by contractor at installations and the unit rate quoted shall be inclusive of the same (vii) The contractor shall be responsible for safe custody of all the plants / equipements under his contract. (viii) Contractor shall solely responsible for any mishappening / accident and loss to life due to negligence of the workmen engaged in the work. No compensation shall be admissible on this account. (ix) The Contractor shall sign inventory of the equipment/Bldg of MES installation before commencement of work any damage/theft to the Govt. property, the contractor will be responsible and recovery to this effect will be made as decided.
141(x)The operators should have a sound knowledge of plants equipment . (xi) During currency of contract If there is any change of staff, same to be informed in writing to the accepting officer well in advance. The Accepting Officer reserves the right whether to change the staff. However he can remove any staff on the basis of Non Performance. (xii) Contractor shall liable to comply with all the relevant rules and regulations as issued and revised by Labour commission. (xiii) The operator shall not leave the installation without reliever and Installation shall not be left unmanned in any case. If any staff found absent, Three times of the min wages prescribed as per the Govt charges as penalty (xiii) Weekly Area cleaning including cutting of grass, etc all around the installations as directed otherwise penalty @ 500/- per day imposed or decision of GE will be final & Binding. Any abnormality observed to be immediately intimated to the maintenance team with intimation to the concerned MES Personnel / in charge. (xv) Minimum required tools, T&P, safety equipment etc always available with the operator (xvi) Log sheets to be maintained regularly in binding book with respect to detailed parameters of AC parameter such as DBT, WBT, RH, Power consumed, etc and signed by the contractor him self or his authorised rep all as directed by the Engr-in-Charge (xvii) First aid box including medicines shall be kept in the installations
142(xviii) All consumable items such as refrigrant Gas, compressor Oil, Greece, including descaling with chemicals, servicing of plants. AHU , Ducts , Filters, Condensing Pipes and Coil, Cooling Tower, fire damper, Heaters etc required for operation of plants hshall be provided by contractor at his own cost as per the manufacturer"s instruction and direction of GE during period of manning and operation, cost of the same shall be deemed to include in the unit rate quoted by the contractor. (xix)All the personnel employed for operation and maintenance should be in proper uniform with firm name and safety outfits as per relevant norms. They may also be required to be deployed in any other locations other than mentioned above as per the site requirements and exigencies. (xx) The rates are deemed to include minimum fair wages, EPF, ECIS etc to paid to the employed personnel as per the rules enforced by the Govt time to time and payment of all taxes as per govt rule.(xxi) The rates quoted by the tenderer shall be deemed to include wages including revised rate of variable Dearness Allowance (VDA) alongwith all taxes, statutory levies/duties such as Labour Welfare tax, Govt Service Tax (GST), EPF, ESI, Bonus, etc as applicable on date and levied by the Central/State Govt payable under respective statutes as applicable from time to time. For this account nothing extrashall be admissible. (xxii) In case of any changes in the minimum wages or any statutory wage component as per the Applicable Laws during the Contract period, Service provider has to cater for the same in this quote. In this regard, no extra claim is admissible.
143M&L for servicing AHU of AC plant3x35 TR including cleaningaccessories ducts,filters, cooling coil greasing bearing, checking the alignment etc and servicing to blower motor by replacing bearing/ bushes etc and greasing oiling and refixing the same testing and commissioning all as directed.
144Material and labour fordescaling the condenser of capacity 3x35 TR afterdismantling the inlet and out let water connections providing the necessary dummies and circulating descaling acid with help of external pump, brushing the condenser tubes removing the scale neutralizing the base of tubes by circulating neutralizing agent replacement of rubber gasket for the end covers of the condenser removing the dummies connecting the water pipe line connections removing the air lock testing and commissioning complete all as specified and as directed.
145Manning & Operation of Central type AC plant 3X30 TR (2W + 1SB) installed at TTD Bldg of ITR Chandipur with 03 shifts/day (08 hours per Shift) (0600 hrs to 1400hrs, 1400 hrs to 2200 hrs & 2200 hrs to 0600 hrs) including Saturdays, Sundays and holidays with deployment of one operator per shift (ITI/ diploma holder having adequate experience in the respective trade) during the following period, starting from satisfactory completion of Defect liability period complete all as specified and directed.
146Twelve (12) Months after completion of Defect liability period
147Twelve (12) Months after completion of item 61.10 above
148Twelve (12) Months after completion of item 61.20 above
149NOTE (For item 61 to 61.30above) : The rates quoted for operation and maintenance of installations will include the following :- (i) Providing optimum manpower. Minimum qualification of all the manpower employed will be ITI passed in respective field of work with minimum 3 years experience. The contractor will submit the details of manpower employed before commencement of work. (ii) Duty timings will be as follows. For round the clock duties: 1st shift - 06:00 - 14:00 Hrs, 2nd shift - 14:00 - 22:00 Hrs, 3rd shift - 22:00 Hrs - 06:00 Hrs. For General duty/one shift - 08:30 - 16:30 Hrs. (iii) Al the tradesmem shall wear proper uniform with firm name and shoes at the installation, colour of uniform will be dircted by Engineer in Charge. (iv) Daily cleaning and maintenance of equipement and inside the installation shall be carried out by the staff employed by contractor without any exta cost to the departement and if fail to do the maintenance panelty @ 500/- per day imposed or decision of GE will be final & Binding. (v) Quoted rate is deemed to be inclusive of all consumables includingtoppingup required refrigerant gas, compressor oil required for maintaining the plant at good working condition & desired condition of 22ºC ± 3ºC and relative humidity 50 % ± 5 %. (vi) Daily consumables such as grease, gland rope, cotton waste etc shall be provided by contractor at installations and the unit rate quoted shall be inclusive of the same (vii) The contractor shall be responsible for safe custody of all the plants / equipements under his contract. (viii) Contractor shall solely responsible for any mishappening / accident and loss to life due to negligence of the workmen engaged in the work. No compensation shall be admissible on this account. (ix) The Contractor shall sign inventory of the equipment/Bldg of MES installation before commencement of work any damage/theft to the Govt. property, the contractor will be responsible and recovery to this effect will be made as decided.
150(x)The operators should have a sound knowledge of plants equipment . (xi) During currency of contract If there is any change of staff, same to be informed in writing to the accepting officer well in advance. The Accepting Officer reserves the right whether to change the staff. However he can remove any staff on the basis of Non Performance. (xii) Contractor shall liable to comply with all the relevant rules and regulations as issued and revised by Labour commission.(xii) The operator shall not leave the installation without reliever and Installation shall not be left unmanned in any case. If any staff found absent, Three times of the min wages prescribed as per the Govt charges as penalty (xiii) Weekly Area cleaning including cutting of grass, etc all around the installations as directed otherwise penalty @ 500/- per day imposed or decision of GE will be final & Binding. (xiv) Any abnormality observed to be immediately intimated to the maintenance team with intimation to the concerned MES Personnel / in charge. (xv) Minimum required tools, T&P, safety equipment etc always available with the operator (xvi) Log sheets to be maintained regularly in binding book with respect to detailed parameters of AC parameter such as DBT, WBT, RH, Power consumed, etc and signed by the contractor him self or his authorised rep all as directed by the Engr-in-Charge
151(xvii) First aid box including medicines shall be kept in the installations (xviii) All consumable items such as refrigrant Gas, compressor Oil, Greece, including descaling with chemicals, servicing of plants. AHU , Ducts , Filters, Condensing Pipes and Coil, Cooling Tower, fire damper, Heaters etc required for operation of plants hshall be provided by contractor at his own cost as per the manufacturer"s instruction and direction of GE during period of manning and operation, cost of the same shall be deemed to include in the unit rate quoted by the contractor. (xix)All the personnel employed for operation and maintenance should be in proper uniform with firm name and safety outfits as per relevant norms. They may also be required to be deployed in any other locations other than mentioned above as per the site requirements and exigencies. (xx) The rates are deemed to include minimum fair wages, EPF, ECIS etc to paid to the employed personnel as per the rules enforced by the Govt time to time and payment of all taxes as per govt rule. (xxi) The rates quoted by the tenderer shall be deemed to include wages including revised rate of variable Dearness Allowance (VDA) alongwith all taxes, statutory levies/duties such as Labour Welfare tax, Govt Service Tax (GST), EPF, ESI, Bonus, etc as applicable on date and levied by the Central/State Govt payable under respective statutes as applicable from time to time. For this account nothing extrashall be admissible. (xxii) In case of any changes in the minimum wages or any statutory wage component as per the Applicable Laws during the Contract period, Service provider has to cater for the same in this quote. In this regard, no extra claim is admissible.
152M&L for servicing AHU of AC plant3x30 TR including cleaningaccessories ducts,filters, cooling coil greasing bearing, checking the alignment etc and servicing to blower motor by replacing bearing/ bushes etc and greasing oiling and refixing the same testing and commissioning all as directed.
153Material and labour fordescaling the condenser of capacity 3x30 TR afterdismantling the inlet and out let water connections providing the necessary dummies and circulating descaling acid with help of external pump, brushing the condenser tubes removing the scale neutralizing the base of tubes by circulating neutralizing agent replacement of rubber gasket for the end covers of the condenser removing the dummies connecting the water pipe line connections removing the air lock testing and commissioning complete all as specified and as directed.
154M&L for servicing AHU of AC plant3x30 TR including cleaningaccessories ducts,filters, cooling coil greasing bearing, checking the alignment etc and servicing to blower motor by replacing bearing/ bushes etc and greasing oiling and refixing the same testing and commissioning all as directed.
155M&L for painting to complete chilled water type Central Air Conditioningplant of3x 30 TR to 3X90 TR capacity at AC Magzine,including completechiller unit, compressor, motor, condenser refrigerant pipe, water pipe, chilled water pipe line,AHU, cooling tower, LT panel board complete plant with two coat of synthetic enamelled paint including preparation ofsurfaces and as per colour code all as specified and directedby Engineer - in - charge .
156M&L fordismantling and overhauling ofcondenser/Chiller/Hot water generator/Cooling tower pump set of capacity upto 15 HP, dismantling pump and motor separately, cutting the burnt out winding from slots and rewinding the same by existing size and gauge of super enamalled copper wire including varnishing, heating, repairing the insulating materials, repalcing bearings, bushes and remetalling the shaft including necessary heat treatment ,and repairing the pump , including replacing the gland packing , bearingsand all rustednuts and bolts, washersand remetaling the Impeller of suitable size and bore for lifting the water from sourceand reassembling the motor and pump with gland packing includings painting of pump amd motor assambly complete with two coats ofsuper enameled paints over one coats of red oxide,fixing the motor & pump at its position and connecting the suction and delivery water pipe and testing under working conditions, complete all as specified anddirected.
157M&L for repair and servicing to squirrel cage induction motor 3 phase 415V, upto 15.0 HP as per existing make and model by dismantling of motor from the pump set removing the stater/rotor separately, cleaning, varnishing, heating and drying re-erecting, aligning with the pump, testing, including replacing the bearing and bush, polishing and re-metalling the shaft including necessary heat treatment.Reassembling the motor and pump with newgland packing, supply and fix new gland nuts, bolts, with gland mounting nuts & bolts washers complete , painting the motor and pumpswith two coats of synthetic enamel paint after preparing the surfaces all as directed by Engineer-in-charge. fixing the motor & pump on their own base and connecting the suction and delivery water pipes and testing with proper working condition complete all as directed .
158S&F of following items as on requirement basis :
159Motorized butter fly valve as per existing make and model
160Actuator for operation of damper as per existing make and model
161Water flow switch as per existing make and model
162Pressure gauge as per existing make and model
163Piston ring set as per existing make and model
164Oil ring set as per existing make and model
165Charging/top up of compressor oil in various central type AC plants, Type : HPL-68 or equivalent as per existing sample (Make : SERVO/INDIAN OIL or equivalent as approved)
166Suction Reed as per existing make and model
167Discharge Reed as per existing make and model
168Oil pump assembly
169Shaft seal assembly
170Main bearing as per existing make and model
171Thrust bearing as per existing make and model
172Pump and plate
173Solenoid assembly
174HP/LP cut out
175OP cut out
176V Belt
177Piston pins
178Contactor of existing capacity
179Recharge/Top up refrigerant R134a/R407c/R410a or equivalent in Centraltype AC Plants of variouscapacities
180oil filter as per existing make and model
181head gasket as per existing make and model
182manifold gasket as per existing make and model
183pump gasket as per existing make and model
184crankcase Heater 230 V
185drier core
186Slight glass
187Fan motor pulley
18815W 40 Oil
189Ball bearing
190Necessery lathe work for mshaft mentling and turning
191Bearing housing
192S&F in repair of refillable type drier filter suitable for central type AC Plant of capacity 30/35 TR capacity as per existing make and model.
193S&F in repair Entering water temperature (EWT) sensor suitable for 30/35 TR scroll typeAC Plant. Make: As per existing model
194Supply and fixing of of PVC Fills of size (600x300x150mm), blue colour,sutable for any type of cooling tower of central air conditioning plant
195S&F in repair of single phase preventeras per existing make and model
196S&F in repair Safety valve of copper material suitable for 30/35 TR capacity Central AC plant all as per existing make and model
197S&F in repairfan capacitor as per exisitng capacity suitable for out door unit ofCentral type AC plant of 30/35 TR Capacity all as specified and directed by Engr - in - Charge.
198M & L for replacement of U/S canvas cloth of Centralt ype AC plantincluding provisiong of zip 150 mm lenth for opening and closing arrangements and properly fasterners with bolts and nuts between the ducts all as directed by the Eng-in-charge
199BLANK
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail